ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / NAMO IMPERIAL

Registration lapsed No litigation declared Residential / Group Housing project

NAMO IMPERIAL

By NAMO REALITY

RG-MH-17388 · RERA P52100028872 · Last updated on MahaRERA portal: 22 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

NAMO IMPERIAL is a Residential / Group Housing project by NAMO REALITY in Pune, Maharashtra, registered with MahaRERA as P52100028872 on 5 Apr 2021. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameNAMO IMPERIAL
  • TypeResidential / Group Housing
  • Location
    • DY PATIL LOHAGAON ROAD
    • LOHAGAON
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411047
  • Pincode411047
  • RERA no.P52100028872
  • ReraGenie IDRG-MH-17388

Builder

  • NameNAMO REALITY
  • Entity typePartnership
  • PartnersNAYANA PRAVIN PHULPHAGAR, VIKAS PREMCHAND GUPTA

Key dates

22 months past promisethis monthRegisteredApr 2021First promiseJun 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Apr 2021
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAMO IMPERIALNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

NAMO IMPERIAL: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 22 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Open Space20

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,162 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NAMO REALITYPune (CB)Pune

Approvals and building plan

Permissible FSI3471.04
Proposed, not sanctioned1,993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYANI NAGAR PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSOMNATH KERUR & ASSOCIATES
EngineerNARAYAN B BASARIKATTI
Chartered AccountantPRAVIN PHULPHAGAR
PartnerRole in project
NAMO REALITY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017215Jun 2023 → Dec 2023

Reason as filed by the promoterI Vikash Premchand Gupta Authorized Partner of NAMO Reality, When we started project 2nd Covid lockdown was started and registration came after that so we did not get 6 months extention from RERA of the same. Also we faced challenges in sale in units at later stage , we have completed 95% of the work.

EXT52100019065Jun 2023 → Dec 2024

Reason as filed by the promoterDue to slow sales of project and extension by PMC is just 3 months before funds problem constructions was delayed and yet muncipal corporation Occupancy certificate is not received yet

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf22 Apr 2024
Declaration in FORM BFile: form b.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate form 2.pdf16 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality assurance form 2A.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annexure D form 3compressed.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate form 2.pdf1 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: annexure D form 3compressed.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate form 2.pdf22 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13annexure D form 3compressed.pdf22 Mar 2024
Declaration in FORM BFile: self declaration 311224.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate.pdf20 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers certificate for quality assurance form 2A.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold.pdf20 Mar 2024
Declaration in FORM BFile: Form B 29 june 2024.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate.pdf11 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate form 2.pdf11 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers certificate for quality assurance form 2A.pdf11 Mar 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold.pdf11 Mar 2024
Layout approvalFile: 1_compressed.pdf12 Jan 2024
Building plan approvalFile: 2_compressed.pdf12 Jan 2024
Building plan approvalFile: 3_compressed.pdf12 Jan 2024
Copy of Layout Approval (in case of layout)File: 1_compressed.pdf12 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf12 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf12 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 Jan 2024
Declaration about Commencement CertificateFile: Declaration about CC new.pdf3 Sep 2023
Declaration in FORM BFile: Self declaration Form B new.pdf3 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2a April2021 to March 2022.pdf3 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2a April2022 to March 2023.pdf3 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of sold unsold inventory.pdf3 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 arch certificate.pdf27 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold inventory.pdf27 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 21to22.pdf27 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5 22To23.pdf27 Aug 2023
Copy of the legal title reportFile: Search and Title Report new.pdf30 Mar 2021
Layout approvalFile: Layout New.pdf27 Mar 2021
Building plan approvalFile: Building Plan Approval New.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: Layout New.pdf27 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval New.pdf27 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf25 Mar 2021
Proforma of Allotment letterFile: Rera Draft Agreement Sale-converted.pdf23 Mar 2021
PAN CardFile: PAN - NAMO REALITY.pdf22 Mar 2021
Details of encumbrancesFile: non encumberance cert.pdf22 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf18 Mar 2021
Declaration in FORM BFile: FORM-B NOTORISED.pdf18 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf18 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf18 Mar 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAMO IMPERIAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LOHAGAON13,700+ in Pune

Builder: NAMO REALITY

NAMO REALITY has 1 registration on MahaRERA, including NAMO IMPERIAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that NAMO IMPERIAL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NAMO IMPERIAL is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAMO IMPERIAL?

The registered promoter entity is NAMO REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAMO IMPERIAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAMO IMPERIAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAMO IMPERIAL?

The professionals named in the filing: Architect: SOMNATH KERUR & ASSOCIATES; Engineer: NARAYAN B BASARIKATTI; Chartered Accountant: PRAVIN PHULPHAGAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAMO IMPERIAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAMO IMPERIAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAMO IMPERIAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.