Home / Browse projects / Nagpur, Maharashtra / Nakshatra Height

Registered No litigation declared Residential / Group Housing project

Nakshatra Height

By NAKSHATRA INFRAVENTURE

RG-MH-97802 · RERA P50500015969 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 50%
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

Nakshatra Height is a Residential / Group Housing project by NAKSHATRA INFRAVENTURE in Nagpur, Maharashtra, registered with MahaRERA as P50500015969 on 10 Apr 2018. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameNakshatra Height
  • TypeResidential / Group Housing
  • Location
    • Jaitala road
    • Near Dhyandeep school
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440036
  • Pincode440036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500015969
  • ReraGenie IDRG-MH-97802

Builder

  • NameNAKSHATRA INFRAVENTURE
  • Entity typePartnership
  • PartnersSADHANA PRAMOD RAKSHAMWAR, ANURADHA PRAVIN GULRANDHE, SHIWANI VIJAY RAUT
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2018PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Apr 2018
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed115 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A- WingNA40000
B- WingNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 50%.

A- Wing50%
ActivityProgress
Excavation50%
Basement (if any)50%
Podiums (if any)50%
Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B- Wing50%
ActivityProgress
Excavation50%
Basement (if any)50%
Podiums (if any)50%
Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntYes60%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes60%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered2
Open Space22
BuildingClosed/CoveredOpen SpaceTotal
A- Wing11011
B- Wing11213

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,845 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jun 2025

Approvals and building plan

Sanctioning authorityNagpur Improvement Trust
Permissible FSI2234.0
Proposed, not sanctioned2,234 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMadhav Nagar, Mate Square

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Bahadure
ArchitectMahesh Padole
EngineerMahesh Padole
Chartered AccountantRishi Lashkare
Chartered AccountantRavindra Lashkare
PartnerRole in project
NAKSHATRA INFRAVENTURE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500009526Dec 2028 → Sep 2021

Reason as filed by the promoterWe are re-sanctioning 2nd building according to new UDPCR. It will take time to sanction and construction hence need extension.

EXT50500024520Dec 2028 → Dec 2028

Reason as filed by the promoterDue to the amended rules in the UDCPR we have applied for re sanctioning of the said plan in one of the wings of the project. Pursuant to this we are applying for extension.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory - Nakshatra Heights - March 2023.pdf4 Jul 2026
Form 1File: FORM 1 - Architect Certificate - Nakshatra Heights - March 2023.pdf4 Jul 2026
Form 2File: FORM 2 - Engineer Certificate - Nakshatra Heights - March 2023.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - March 2023_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Nakshatra Heights - June 2023.pdf4 Jul 2026
Form 1File: FORM 1 - Architect Certificate - Nakshatra Heights - June 2023.pdf4 Jul 2026
Form 2File: FORM 2 - Engineer Certificate - Nakshatra Heights - June 2023.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - June 2023_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Nakshatra Heights - September 2023.pdf4 Jul 2026
Form 1File: FORM 1 - Architect Certificate - Nakshatra Heights - September 2023.pdf4 Jul 2026
Form 2File: FORM 2 - Engineer Certificate - Nakshatra Heights - September 2023.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - September 2023_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Nakshatra Heights - December 2023.pdf4 Jul 2026
Form 1File: FORM 1 - Architect Certificate - Nakshatra Heights - December 2023.pdf4 Jul 2026
Form 2File: FORM 2 - Engineer Certificate - Nakshatra Heights - December 2023.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - December 2023_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Nakshatra Heights - March 2024.pdf4 Jul 2026
Form 1File: FORM 1 Corrected - Architect Certificate - Nakshatra Heights - March 2024.pdf4 Jul 2026
Form 2File: FORM 2 Corrected - Engineer Certificate - Nakshatra Heights - March 2024.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - March 2024_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of solde - Nakshatra Heights - June 2024.pdf4 Jul 2026
Form 1File: Form 1 Corrected - Architect Certificate - Nakshatra Heights - June 2024.pdf4 Jul 2026
Form 2File: Form 2 Corrected - Engineer Certificate - Nakshatra Heights - June 2024.pdf4 Jul 2026
Form 3File: FORM 3 - CA Certificate - Nakshatra Heights - June 2024_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold Inventry - Nakshatra Heights - September 2024.pdf4 Jul 2026
Form 1File: Form 1 - Architects Certificate -Nakshatra Heights - September 2024.pdf4 Jul 2026
Form 2File: Form 2 - Engineer Certificate -Nakshatra Heights - September 2024.pdf4 Jul 2026
Form 3File: Form 3 - C A Certificate - Nakshatra Heights - September 2024_compressed.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold Inventry - Nakshatra Heights - December 2024.pdf4 Jul 2026
Form 1File: Form 1 - Architects Certificate - Nakshatra Heights - December 2024.pdf4 Jul 2026
Form 2File: Form 2 - Engineer Certificate - Nakshatra Heights - December 2024.pdf4 Jul 2026
Form 3File: Form 3 - C A Certificate - Nakshatra Heights - December 2024_compressed.pdf4 Jul 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 1 - December 2024.pdf12 Feb 2025
Certificates of CA (Form 3)File: Nakshatra Heights - Form 3 - December 2024_compressed.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 2 - December 2024.pdf12 Feb 2025
Disclosure of sold/ booked inventoryFile: Nakshatra Heights - Disclosure - December 2024.pdf12 Feb 2025
Building plan approvalFile: Sanction Map NEW - 1-4.pdf9 Jan 2025
Building plan approvalFile: Sanction Map NEW - 2-4.pdf9 Jan 2025
Building plan approvalFile: Sanction Map NEW - 3-4.pdf9 Jan 2025
Building plan approvalFile: Sanction Map NEW - 4-4.pdf9 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate NEW.pdf9 Jan 2025
Building Plan Approval (IOD)File: Sanction Map NEW - 1-4.pdf9 Jan 2025
Building Plan Approval (IOD)File: Sanction Map NEW - 2-4.pdf9 Jan 2025
Building Plan Approval (IOD)File: Sanction Map NEW - 3-4.pdf9 Jan 2025
Building Plan Approval (IOD)File: Sanction Map NEW - 4-4.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 1 Corrected - June 2024.pdf2 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 1 - September 2024.pdf2 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 1 Corrected - March 2024.pdf2 Jan 2025
Certificates of CA (Form 3)File: Nakshatra Heights - Form 3 - September 2024_compressed.pdf2 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 2 - September 2024.pdf2 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 2 Corrected - June 2024.pdf2 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nakshatra Heights - Form 2 Corrected - March 2024.pdf2 Jan 2025
Disclosure of sold/ booked inventoryFile: Nakshatra Heights - Disclosure - September 2024.pdf2 Jan 2025
Declaration about Commencement CertificateFile: Format D - Declaration About Commencement Certificate.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2021-22.pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2022-23.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23.pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2023-24.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf2 Jan 2025
CERSAI detailsFile: CERSAI Nakshatra.pdf16 Dec 2024
Other - TechnicalFile: Order 50.pdf21 Oct 2024
Declaration in FORM BFile: Form B - Nakshatra Heights.pdf17 Oct 2024
Declaration about Commencement CertificateFile: Format D Declaration of CC - Nakshatra.pdf17 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf17 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Shiwani.pdf17 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Sadhana.pdf17 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - Anuradha.pdf17 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf17 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured Unsecured Finance.pdf17 Oct 2024
Proforma of Agreement for saleFile: Draft Agreement to Sell.pdf14 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate - Legal - D (2).pdf11 Oct 2024
CERSAI detailsFile: Self Declaration of CERSAI (1).pdf11 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter - D (2).pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate - Legal - D (2).pdf11 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model agreement - D.pdf11 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - June 2024.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - June 2024.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of solde - June 2024.pdf26 Jul 2024
Certificates of CA (Form 3)File: CA Certificate - June 2024_compressed.pdf26 Jul 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHIWANI REGENCYPlot No. 4 Mouza Jaitala Natraj Co Operative Housing Society Nagpur24CompletedSep 2015Sep 2015

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nakshatra Height on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Dhyandeep school2,800+ in Nagpur

2 kmNakshatra HeightCompleted 13Lapsed / revoked 6Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: NAKSHATRA INFRAVENTURE

NAKSHATRA INFRAVENTURE has 2 registrations on MahaRERA, including NAKSHATRA-I and Nakshatra Height. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Nakshatra Height is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nakshatra Height?

The registered promoter entity is NAKSHATRA INFRAVENTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nakshatra Height?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nakshatra Height?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nakshatra Height?

The professionals named in the filing: Architect: Sanjay Bahadure; Architect: Mahesh Padole; Engineer: Mahesh Padole; Chartered Accountant: Rishi Lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nakshatra Height?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nakshatra Height. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nakshatra Height to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.