Home / Browse projects / Nagpur, Maharashtra / SHREE SHIVGAURI RESIDENCY
SHREE SHIVGAURI RESIDENCY
By M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS
RG-MH-59297 · RERA P50500026071 · Last updated on MahaRERA portal: 2 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 47 months
- 5 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE SHIVGAURI RESIDENCY is a Residential / Group Housing project by M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS in Nagpur, Maharashtra, registered with MahaRERA as P50500026071 on 15 Aug 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 47 months from the original filing. 194 of the 199 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameSHREE SHIVGAURI RESIDENCY
- TypeResidential / Group Housing
- Location
- jaitala road
- JAITALA
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440036
- Pincode440036
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500026071
- ReraGenie IDRG-MH-59297
Builder
- NameM/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS
- Entity typePartnership
- PartnerMADHAV WAMANRAO DESHPANDE
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Aug 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Jan 2023)
- Buildings1 building record
- Documents filed131 files
Current status
Figures as on 2 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE SHIVGAURI RESIDENCY | NA | 14 | 12 | 199 | 0 | 199 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 97%.
SHREE SHIVGAURI RESIDENCY: 88% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREE SHIVGAURI RESIDENCY | NA | Rs 40.72 cr | Rs 37.87 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP PANDIT |
| Engineer | VIKESH MESHRAM |
| Engineer | AASHAY KUKDE |
| Chartered Accountant | SUMIT CHANDWANI |
| Chartered Accountant | ASHISH LAXMINARAYAN AGARWAL |
| Partner | Role in project |
|---|---|
| M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project mainly has been delayed due to surge in the price of raw material due to which the arragements with vendors got delayed, which leads to disputes with contractors. Current status of project is near completion and the same will be completed within extended time period.
Reason as filed by the promoterDue to Covid Pandemic. Our project is delayed and now our new completion date is 30/01/2024
Reason as filed by the promoterDue to unforeseen circumstances beyond our control, the completion certificate for the aforementioned project was delayed from the concerned department. This delay has arisen due to pending approvals and administrative procedures.
Reason as filed by the promoterHowever, due to unforeseen circumstances beyond our control, the completion certificate for the aforementioned project was delayed from the concerned department. This delay has arisen due to pending approvals and administrative procedures.
Reason as filed by the promoterDue to unforeseen circumstances beyond our control, the completion certificate for the aforementioned project was delayed from the concerned department. This delay has arisen due to pending appravals and administrative procedures.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Aug 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed131
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: Form3 CA Certificate Jan-March26.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Sept 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Dec 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate JAN 2026.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificae Sept 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate Dec 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate JAN 26.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Sept 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Dec 25.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Dec 25.pdf | 15 Apr 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A FY 24-25.pdf | 11 Sep 2025 |
| Form 5 (FY 2024-2025)File: FORM 5_FY 24-25 Shiv Gauri.pdf | 11 Sep 2025 |
| Form 1File: Form 1 Architect Certificate Mar 2025.pdf | 23 Aug 2025 |
| Form 2File: Form 2 Engineer Certificate Mar 2025.pdf | 23 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Booked Inventory mar 2025.pdf | 23 Aug 2025 |
| Form 3File: Form 3 CA CERTIFICATE Mar 25.pdf | 23 Aug 2025 |
| Form 1File: Form 1 Architect Certificate June 2025.pdf | 23 Aug 2025 |
| Form 2File: Form 2 Engineer certificate June 2025.pdf | 23 Aug 2025 |
| Form 3File: Form 3 CA Certificate June 25.pdf | 23 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory june2025.pdf | 23 Aug 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate June 2025.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate June 2025.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf | 23 Aug 2025 |
| Disclosure of sold/ booked inventoryFile: sold booked inventory.pdf | 17 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Undertaking.pdf | 13 Mar 2025 |
| OtherFile: index II swadesh mishra.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 shivgauri.pdf | 8 Mar 2025 |
| Declaration in FORM BFile: DocScanner Mar 5, 2025 12-21 PM.pdf | 5 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 - Shree Shivgauri Residency - March 24.pdf | 14 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - FY 23-24.pdf | 14 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 - Shree Shivgauri Residency - June 24.pdf | 5 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 - Shree Shivgauri Residency - Sep 24.pdf | 5 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 - Shree Shivgauri Residency - Dec 24.pdf | 5 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Shree Shivgauri Residency - June 24.pdf | 5 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Shree Shivgauri Residency - Sep 24.pdf | 5 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Shree Shivgauri Residency - Dec 24.pdf | 5 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4 Sold Booked Inv - Shree Shivgauri Residency - June 24.pdf | 5 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4 Sold Booked Inv - Shree Shivgauri Residency - Sep 24.pdf | 5 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4 Sold Booked Inv - Shree Shivgauri Residency - Dec 24.pdf | 5 Feb 2025 |
| Declaration in FORM BFile: From B.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Shree Shivgauri Residency - June 24.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Shree Shivgauri Residency - Sep 24.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Shree Shivgauri Residency - Dec 24.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 mar 24.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 mar 24.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 mar 24.pdf | 13 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf | 13 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch December.pdf | 31 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng December.pdf | 31 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DECEMBER.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 dec 21 Finale.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Marc 22 final.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 june 22.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 SEPT 22.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form 3 march 23 a.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Form 3 June 23.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Form 3 Sept 23 a.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sept 23 Final.pdf | 27 Jan 2024 |
| Declaration in FORM BFile: form b.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 31-12-21.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 31-03-22.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 30-06-22.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 30-09-22.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 30-06-23.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 30-09-23.pdf | 26 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 30-09-23.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-12-2021.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-2022.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-06-2022.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-09-2022.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-2023.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: architect 30-06-23.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-09-2023.pdf | 26 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30-09-2023.pdf | 26 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a 21.pdf | 26 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a 23.pdf | 26 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold MARCH 23.pdf | 26 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHIVPRIYA TOWRES | KH. NO. 82 JAITLA | 204 | Completed | Jul 2015 | Late, Aug 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 131 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREE SHIVGAURI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JAITALA2,800+ in Nagpur
Filed coordinates, straight-line distance. 34 registered projects within 2 km.
MATOSHRI
SANDESH DEVELOPERS
SITAI PARK
GANRAJ INFRA
AADITYA PREMIUM 6
R S ENTERPRISES
KRISHNA LEELA
Krishna Constructions
ATLANTIC APARTMENT
DHUNI CONSTRUCTIONS PVT.LTD.
ORBIT APARTMENT
DHUNI CONSTRUCTIONS PVT.LTD.
See every Nagpur project, with the district possession charts
Builder: M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS
M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including SHREE SHIVGAURI RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if SHREE SHIVGAURI RESIDENCY is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE SHIVGAURI RESIDENCY?
The registered promoter entity is M/S SHRI KEDARESHWAR BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE SHIVGAURI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE SHIVGAURI RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE SHIVGAURI RESIDENCY?
The professionals named in the filing: Architect: SANDEEP PANDIT; Engineer: VIKESH MESHRAM; Engineer: AASHAY KUKDE; Chartered Accountant: SUMIT CHANDWANI; Chartered Accountant: ASHISH LAXMINARAYAN AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE SHIVGAURI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback