ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Mungase Towers

Registered No litigation declared Others project

Mungase Towers

By Mr Santosh Vasudev Mungase

RG-MH-95524 · RERA P52100050206 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Internal walls, 98%
62 of 144Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 155 documents Report an error

Mungase Towers is a Others project by Mr Santosh Vasudev Mungase in Pune, Maharashtra, registered with MahaRERA as P52100050206 on 27 Mar 2023. Possession is promised by 26 Dec 2026. 82 of the 144 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameMungase Towers
  • TypeOthers
  • Location
    • Kuruli
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050206
  • ReraGenie IDRG-MH-95524

Builder

  • NameMr Santosh Vasudev Mungase
  • Entity typeIndividual

Key dates

this monthRegisteredMar 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Mar 2023
  • Promised completion26 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed155 files

Current status

57%82 of 144 units booked
60.3%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mungase TowersNA111012321144

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

Mungase Towers: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes65%
Aggregate area of recreational Open SpaceYes25%
Open ParkingNoNot applicable

Parking filed150

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots150
Closed/Covered6
Open Space144

Land and ownership21

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,566 sq m
Land owned byThe promoter, with other names on the file
Named landowners21
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Feb 2026
LandownerVillageDistrict
Mrs Suman Eknath KambleKuruliPune
Mrs Vasanti Chandrakant DeshnehereMumbai CityMumbai City
Mrs Manisha Prashant DolusKuruliPune
Mrs Kaveri Sanjay GaikwadBebad OholPune
Mrs Vandana Santosh DolusBhosariPune
Mrs Ranjana Gulab KambeKuruliPune
Mr Sachin Gulab KambleKuruliPune
mrs Sima Gulab KambleKuruliPune
Mr Lalu Tukaram KambleKuruliPune
Mrs Balu Tukaram KambleKuruliPune
Mrs Bababai Haribhau KamblePune (M Corp.)Pune
Mrs Lata Sakharam NikamPune (M Corp.)Pune
Mrs Sangita Ganesh KamblePimpri Chinchawad (M Corp.)Pune
Mrs Diksha Ganesh KamlePune (M Corp.)Pune
Mr Harshad Ganesh KamblePune (M Corp.)Pune
Mrs Prajakta Ganesh KamblePune (M Corp.)Pune
Mrs Manisha Smitin PawarPune (M Corp.)Pune
Mr Atul Sakharam NikamPune (M Corp.)Pune
Mr Prutviraj Sakharam NikamPune (M Corp.)Pune
Mrs. Kavita Rupesh AgaleKuruliPune
Mrs sarika Mahesh NikajeKuruliPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority, Pune
Permissible FSI7585.89
Proposed, not sanctioned5,677 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNigdi Pune
Estimated costRs 19.11 cr
Cost incurredRs 11.52 cr
Work done60.3%
BuildingWingEstimatedIncurred
Mungase TowersNARs 9.55 crRs 8.22 cr
-NARs 9.55 crRs 3.31 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Milind Gavali
EngineerRohinee Engineers
EngineerMAYUR SANDBHOR
Chartered AccountantMr Pravin Pise
Chartered AccountantVaibhav S Bhise
PartnerRole in project
Mr Santosh Vasudev Mungase-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 26 Dec 2026

Documents filed155

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 (8).pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 (3).pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 (9)_compressed.pdf16 Jul 2026
Withdrawal Update Form 1File: Work Progress Mungase Towers Form 1.pdf7 May 2026
Withdrawal Update Form 2File: Form 2 with sign (1) (1).pdf7 May 2026
Withdrawal Update Form 3File: form 3 mar 26 (1) (2) (1).pdf7 May 2026
Form 2A (FY 2025-2026)File: Form 2A (5)-signed.pdf14 Mar 2026
Withdrawal Update Form 1File: Work Progress Mungase Towers - Form 1 with sign.pdf9 Mar 2026
Withdrawal Update Form 2File: mungase tower Dec 25 (1)-signed (1) (1).pdf9 Mar 2026
Withdrawal Update Form 3File: form 3.pdf9 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf5 Dec 2025
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf5 Dec 2025
Form 2A (FY 2023-2024)File: Form 2A 23-24 (1).pdf5 Dec 2025
Form 5 (FY 2022-2023)File: FY 2022-23 (3).pdf20 Nov 2025
Form 5 (FY 2023-2024)File: FY 2023-24 (2).pdf20 Nov 2025
Form 1File: Form 1 Sep 2025 s.pdf1 Nov 2025
Form 2File: Form 2Sep 2025.pdf1 Nov 2025
Form 3File: FORM-3 Sep 2025.pdf1 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf1 Nov 2025
Form 5 (FY 2024-2025)File: form 5 sign.pdf25 Aug 2025
Form 1File: f1 m23.pdf23 Jul 2025
Form 2File: f2 m23.pdf23 Jul 2025
Form 3File: f3 mar 23.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 j 23.pdf23 Jul 2025
Form 2File: f2 j 23.pdf23 Jul 2025
Form 3File: f3 j 23.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 s 23.pdf23 Jul 2025
Form 2File: f2 sep 23 (1).pdf23 Jul 2025
Form 3File: f3 s 23.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 dec 23.pdf23 Jul 2025
Form 2File: f2 d 23 (1).pdf23 Jul 2025
Form 3File: f3 d 23.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: form 1.pdf23 Jul 2025
Form 2File: 2.pdf23 Jul 2025
Form 3File: 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: 1.pdf23 Jul 2025
Form 2File: 2.pdf23 Jul 2025
Form 3File: 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: 1.pdf23 Jul 2025
Form 2File: 2.pdf23 Jul 2025
Form 3File: 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 d 24.pdf23 Jul 2025
Form 2File: f2 d 24.pdf23 Jul 2025
Form 3File: 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 m 25.pdf23 Jul 2025
Form 2File: 2.pdf23 Jul 2025
Form 3File: form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold.pdf23 Jul 2025
Form 1File: f1 j 25.pdf23 Jul 2025
Form 2File: engg certificate (2).pdf23 Jul 2025
Form 3File: f3 j 25.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTERY New.pdf23 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 sign (1)_compressed.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sign_compressed.pdf9 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTERY New.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter RERAMUNGASE TOWERS.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate (3).pdf2 Apr 2025
Layout approvalFile: Main Layout.pdf5 Mar 2025
Building plan approvalFile: Binder2.pdf5 Mar 2025
Building plan approvalFile: 11_Page7.pdf5 Mar 2025
Building plan approvalFile: 11_Page6.pdf5 Mar 2025
Building plan approvalFile: 11_Page5.pdf5 Mar 2025
Building plan approvalFile: 11_Page4.pdf5 Mar 2025
Building plan approvalFile: 11_Page3.pdf5 Mar 2025
Building plan approvalFile: 11_Page1.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: Main Layout.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate new_compressed.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Binder2.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 11_Page7.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 11_Page6.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 11_Page5.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 11_Page4.pdf5 Mar 2025

How this compares with Pune

57%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mungase Towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kuruli13,700+ in Pune

Builder: Mr Santosh Vasudev Mungase

Mr Santosh Vasudev Mungase has 1 registration on MahaRERA, including Mungase Towers. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mungase Towers is delayed beyond 26 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mungase Towers?

The registered promoter entity is Mr Santosh Vasudev Mungase, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mungase Towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mungase Towers?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mungase Towers?

The professionals named in the filing: Architect: Mr Milind Gavali; Engineer: Rohinee Engineers; Engineer: MAYUR SANDBHOR; Chartered Accountant: Mr Pravin Pise; Chartered Accountant: Vaibhav S Bhise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mungase Towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mungase Towers. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mungase Towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.