MUKUNDAM
RG-MH-54435 · RERA P51700017888 · Last updated on MahaRERA portal: 15 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Completion date moved by 40 months
- 4 extensions taken
Clear
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MUKUNDAM is a Residential / Group Housing project by Shree Ramjeevdani Realtors in Thane, Maharashtra, registered with MahaRERA as P51700017888 on 24 Sep 2018. Possession is promised by 28 Dec 2027. The completion date has moved by 40 months from the original filing. 144 of the 250 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete.
At a glance
Project
- NameMUKUNDAM
- TypeResidential / Group Housing
- Location
- 150 FT ROAD UTTAN ROAD
- BHAYANDER WEST
- BHAYANDAR
- Thane
- 401101
- Pincode401101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700017888
- ReraGenie IDRG-MH-54435
Builder
- NameShree Ramjeevdani Realtors
- Entity typePartnership
- PartnersKISHOR MORESHWAR BHOIR HUF, NAROTTAM MORESHWAR BHOIR HUF, KAPIL KIMTILAL GUPTA, MORESHWAR MUKUND BHOIR HUF
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Sep 2018
- Promised completion28 Dec 2027
- Revised completionRevised to 28 Dec 2027 (originally 29 Aug 2024)
- Buildings2 building records
- Documents filed193 files
Current status
Figures as on 15 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 27 | 27 | 150 | 0 | 150 |
| B WING | NA | 27 | 27 | 100 | 0 | 100 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 80%.
A WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B WING70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 66% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed186
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A WING | 93 | 93 |
| B WING | 93 | 93 |
Land and ownership14
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| BHASKAR MORESHWAR BHOIR | BHAYANDAR | Thane |
| BHUPESH BHASKAR BHOIR | BHAYANDAR | Thane |
| BHAGASHRI BHASKAR BHOIR | BHAYANDAR | Thane |
| HANSA BHASKAR BHOIR | BHAYANDAR | Thane |
| NEETA NANDAN PATIL | BHAYANDAR | Thane |
| KISHOR MORESHWAR BHOIR | BHAYANDAR | Thane |
| SUNANDA KISHOR BHOIR | BHAYANDAR | Thane |
| PRAJAKTA KISHOR BHOIR | BHAYANDAR | Thane |
| VASUNDHARA PRAVIN MHATRE | BHAYANDAR | Thane |
| NAROTTAM MORESHWAR BHOIR | BHAYANDAR | Thane |
| HITESH NAROTTAM BHOIR | BHAYANDAR | Thane |
| NAMRATA NAROTTAM BHOIR | BHAYANDAR | Thane |
| REKHA NAROTTAM BHOIR | BHAYANDAR | Thane |
| LATE MORESHWAR MUKUND BHOIR | BHAYANDAR | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 100.00 cr | Rs 89.00 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUDHIN PATIL |
| Engineer | RAJESH B DUBEY |
| Engineer | SAHIL SIDDIQUE |
| Engineer | JIGNESH HEMJI MACHHI |
| Chartered Accountant | NITESH MAHENDRA KOTHARI |
| Chartered Accountant | NIKUNJ G BHANGARIA |
| Partner | Role in project |
|---|---|
| Shree Ramjeevdani Realtors | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B.
Reason as filed by the promoter1. We have completed 75% work of the Project. 2. We are in the process of completing the remaining project work and procuring the Occupancy Certificate & Form 4 - Architect’s Certificate on Completion of Project. 3. We have already received part occupancy certificate for our project. 4. We have also taken consent for extension from more than 51% of allottees. 5. The remaining project work & process of procuring the Occupancy Certificate will be completed by 29/08/2026.
Reason as filed by the promoter1. We have completed 85% work of the Project. 2. We are in the process of completing the remaining project work and procuring the Occupancy Certificate & Form 4 - Architect’s Certificate on Completion of Project. 3. We have already obtained Part Occupancy Certificate for Wing A, pursuant to which possession of units in Wing A has been handed over to the respective allottees. 4. The balance work pertaining to Wing B and allied infrastructure is presently under execution. However, the progress of the remaining construction activities has been adversely affected due to disruptions in the supply c
Reason as filed by the promoterNA
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 755/2019 | THANE, DISTRICT AND SESSIONS COURT | Ongoing |
| 277/2020 | THANE COURT | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Aug 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 28 Dec 2027
Documents filed193
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 193 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A_ FY 24-25.pdf | 15 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_ FY 25-26.pdf | 15 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Architect certificate_Jun 26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_Engineers Certifiacte_Jun 26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_Jun 26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Architect Certificate_Mar 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: Form 2_Engineers Certificate_Mar 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_Mar 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: Form 1_ Architech Certificate_31-12-2025.pdf | 20 Feb 2026 |
| Withdrawal Update Form 2File: Form 2_Engineers Certificate.pdf | 20 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_31-12-2025.pdf | 20 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5_CA Certificate_01042024-31032025.pdf | 20 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 30 Sep 2025.pdf | 12 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Engineers Certificate 30 Sep 2025.pdf | 12 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 30 Sep 2025.pdf | 12 Dec 2025 |
| Commencement certificateFile: Commencement Certificate_B_Dec 2024.pdf | 7 Aug 2025 |
| Form 1File: Form 1_Architech Certificate_June 2024.pdf | 7 Aug 2025 |
| Form 2File: Form 2_Engineer Certificate_June 2024.pdf | 7 Aug 2025 |
| Form 3File: Form 3_CA Certificate_Jun 2024.pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory_Jun 2024.pdf | 7 Aug 2025 |
| Form 1File: Form 1_Architect Certificate _Sept 2024.pdf | 7 Aug 2025 |
| Form 2File: Form 2_Engineers Certificate Sept 2024.pdf | 7 Aug 2025 |
| Form 3File: Form 3_CA Certificate_Sept 2024 (2).pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory_Sep 2024.pdf | 7 Aug 2025 |
| Form 1File: Form 1_Architect Certificate _Dec 2024.pdf | 7 Aug 2025 |
| Form 2File: Form 2_Engineers Certificate Dec 2024.pdf | 7 Aug 2025 |
| Form 3File: Form 3_CA_Dec 2024.pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory_Dec 2024.pdf | 7 Aug 2025 |
| OthersFile: Form 5_CA_2023-24.pdf | 7 Aug 2025 |
| Form 1File: Form 1 Architect Certificate_Mar 2025.pdf | 7 Aug 2025 |
| Form 2File: Form 2_Engineers Certificate Mar 2025.pdf | 7 Aug 2025 |
| Form 3File: Form 3_CA Certificate_Mar 2025.pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory_Mar 2025.pdf | 7 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate_Mar 2025.pdf | 23 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate Mar 2025.pdf | 23 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Mar 2025.pdf | 23 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_CA_2023-24.pdf | 26 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate_Sept 2024.pdf | 13 Feb 2025 |
| Layout approvalFile: Approved Plan_Layout_Dec 2024.pdf | 25 Jan 2025 |
| Building plan approvalFile: Approved Plan_Bldg Plan_Dec 2024.pdf | 25 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: Approved Plan_Layout_Dec 2024.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate _Dec 2024.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate Dec 2024.pdf | 25 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Dec 2024.pdf | 25 Jan 2025 |
| Building Plan Approval (IOD)File: Approved Plan_Bldg Plan_Dec 2024.pdf | 25 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Dec 2024.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate _Sept 2024.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate Sept 2024.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Sep 2024.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate_Jun 2024.pdf | 17 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024 Signed.pdf | 30 Jul 2024 |
| Form 2AFile: Form 2A 19-20.pdf | 29 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 29 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 29 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 29 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 13 Disclosure of sold_ booked inventory.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Jun 2024.pdf | 26 Jul 2024 |
| Layout approvalFile: Sheet 1_2024.pdf | 24 Jul 2024 |
| Building plan approvalFile: Sheet 2_2024.pdf | 24 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Sheet 1_2024.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: Sheet 2_2024.pdf | 24 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_2024.pdf | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architech Certificate_June 2024.pdf | 24 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_June 2024.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Jun 2024.pdf | 24 Jul 2024 |
| Declaration in FORM BFile: Form-B-Affidavit.pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Information of Sold_Booked Inventory March 2024.pdf | 16 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3_CA_Mar 2024.pdf | 7 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect's Certificate_Mar 2024.pdf | 8 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer's Certificate_Mar 2024.pdf | 8 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Quality Certificate_Mar 2024.pdf | 8 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Mar 2024.pdf | 8 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_CA_Dec 2023.pdf | 15 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Dec 2023.pdf | 9 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate_Dec 2023.pdf | 9 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Quality Certificate_Dec 2023.pdf | 9 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Dec 2023.pdf | 9 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_CA_2022-23.pdf | 1 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2021-22 (2).pdf | 1 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 193 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MUKUNDAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHAYANDER WEST7,600+ in Thane
Filed coordinates, straight-line distance. 76 registered projects within 2 km.
North Westend Tower 1
JP Infra Realty Private Limited
MAN MANDIR
TRITONIA BUILDCON AND INFRA PRIVATE LIMITE
North Westend Tower 2
JP Infra Realty Private Limited
WINDERMERE TOWER A
A G SUPERSTRUCTURES PRIVATE LIMITED
WINDERMERE TOWER B
A G SUPERSTRUCTURES PVT LTD
SKYLINE D
M/s Sai Shakti Creation
See every Thane project, with the district possession charts
Builder: Shree Ramjeevdani Realtors
Shree Ramjeevdani Realtors has 1 registration on MahaRERA, including MUKUNDAM. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if MUKUNDAM is delayed beyond 28 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MUKUNDAM?
The registered promoter entity is Shree Ramjeevdani Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MUKUNDAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MUKUNDAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MUKUNDAM?
The professionals named in the filing: Architect: SUDHIN PATIL; Engineer: RAJESH B DUBEY; Engineer: SAHIL SIDDIQUE; Engineer: JIGNESH HEMJI MACHHI; Chartered Accountant: NITESH MAHENDRA KOTHARI; Chartered Accountant: NIKUNJ G BHANGARIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MUKUNDAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback