Home / Browse projects / Raigarh, Maharashtra / Mountain View Residency 2
Mountain View Residency 2
RG-MH-81902 · RERA P52000009051 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mountain View Residency 2 is a Residential / Group Housing project by Immaculate Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000009051 on 19 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 24 months from the original filing. 177 of the 278 units on this registration are recorded sold or booked, and 29 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameMountain View Residency 2
- TypeResidential / Group Housing
- Location
- WAROSE TARF WANKHAL
- RAIGARH
- Khalapur
- 410203
- Pincode410203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000009051
- ReraGenie IDRG-MH-81902
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Aug 2017
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 30 Mar 2025)
- Buildings5 building records
- Documents filed136 files
Current status
Figures as on 3 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| G | NA | 12 | 7 | 26 | 50 | 76 |
| I1 | NA | 10 | 7 | 70 | 0 | 70 |
| I2 | NA | 9 | 7 | 70 | 0 | 70 |
| H | NA | 9 | 3 | 27 | 0 | 27 |
| J | NA | 9 | 7 | 35 | 0 | 35 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
29 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.
G82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
H0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
J91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 80% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed82
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| G | 4 | 20 | 24 |
| I1 | 1 | 15 | 16 |
| I2 | 1 | 15 | 16 |
| H | 1 | 15 | 16 |
| J | 1 | 9 | 10 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| H | NA | Rs 9.67 cr | - |
| I1 | NA | Rs 9.67 cr | Rs 9.67 cr |
| I2 | NA | Rs 9.67 cr | - |
| G | NA | Rs 8.71 cr | Rs 8.57 cr |
| J | NA | Rs 5.53 cr | Rs 5.53 cr |
| - | NA | Rs 3.84 cr | Rs 2.41 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sunil Nawale |
| Architect | ROSHNI GUPTA |
| Engineer | Deltacom Structural Consultant LLP |
| Engineer | DIWAKAR R PATHAK |
| Chartered Accountant | MUKESH SONI |
| Chartered Accountant | NITIN B DHAVAN |
| Chartered Accountant | MAYURI NITIN DHAVAN |
| Partner | Role in project |
|---|---|
| Immaculate Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterEXPLAINED IN DECLARATION ATTACHED FOR EXTENSION
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197893 | Balasaheb Maruti Ugale | Immaculate Developers | 04/08/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Feb 2024
Documents filed136
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 - IMM PHASE 2 - SEPT 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 - IMM PHASE 2 - DEC 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 - IMM PHASE 2 - MAR 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 - IMM PHASE 2 - SEPT 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 - IMM PHASE 2 - DEC 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 - IMM PHASE 2 - MAR 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 - IMM P2 - SEPT 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 - IMM P2 - DEC 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 - IMM P2 - MARCH 2026.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 - IMM PHASE 2 - JUNE 2025.pdf | 2 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 - IMM PHASE 2 - JUNE 2025.pdf | 2 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 - IMM P2 - JUNE 2025_11zon.pdf | 2 Jun 2026 |
| Form 1File: FORM 1 - IMM PH 2 - EXTENSION.pdf | 17 Feb 2026 |
| Form 2File: FORM 2 - IMM PH2 - EXTENSION.pdf | 17 Feb 2026 |
| Form 3File: FORM 3 - DEC 2025 - IMM PH2.pdf | 17 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCL FOR SOLD UNSOLD - IMM PH 2 - EXTENSION.pdf | 17 Feb 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 - FY 24-25.pdf | 17 Feb 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IMM DEV DEC 23.pdf | 21 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IMM DEV MAR 24.pdf | 21 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IMM DEV JUN 24.pdf | 21 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IMM DEV SEPT 24.pdf | 21 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 IMM DEV DEC 24.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 IMM DEV DEC 23_11zon.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 IMM DEV MAR 24_11zon.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 IMM DEV JUN 24_11zon.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 IMM DEV SEPT 24_11zon.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 IMM DEV DEC 24_11zon.pdf | 21 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IMM DEV DEC 23.pdf | 21 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IMM DEV MAR 24.pdf | 21 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IMM DEV JUN 24.pdf | 21 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IMM DEV SEPT 24.pdf | 21 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 IMM DEV DEC 24.pdf | 21 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 3581 2019.pdf | 21 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PHASE 2 MARCH 23.pdf | 2 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 PHASE 2 SEPT 2023.pdf | 2 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 PHASE 2 MARCH 23.pdf | 2 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PHASE 2 JUNE 2023.pdf | 2 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PHASE 2 SEPT 23.pdf | 2 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A MARCH 23 PHASE 2.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: FORM3 IMMACULATE DEVELOPERS MARCH 2023 PHASE-II-1_11zon.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: FORM3 IMMACULATE DEVELOPERS JUNE 2023 PHASE-II-2_11zon.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3 IMMACULATE DEVELOPERS SEPT 2023 PHASE-II_11zon.pdf | 2 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 IMMACULATE DEVELOPERS MARCH 23-PHASE-II.pdf | 2 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 IMMACULATE PHASE-2 19.pdf | 30 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 IMMACULATE PHASE-2 20.pdf | 30 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 IMMACULATE PHASE-2 21.pdf | 30 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 IMMACULATE PHASE-2 22.pdf | 30 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-06-2018.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-09-2018.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-12-2018.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-03-2019.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-06-2019.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-09-2019.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-12-2019.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-03-2020.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-06-2020.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-09-2020.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-12-2020.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-03-2021.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-06-2021.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-09-2021.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-12-2021.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-03-2022.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-06-2022.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_30-09-2022.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase II_Rera Form 1_31-12-2022.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-06-2018.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-09-2018.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-12-2018.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-12-2019.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-06-2019.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-09-2019.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-12-2019.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-03-2020.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-06-2020.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-09-2020.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-12-2020.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_31-03-2021.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-06-2021.pdf | 8 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase II_Rera Form 2_30-09-2021.pdf | 8 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| MOUNTAIN VIEW RESIDENCY | Khopoli 410203. | 180 | Completed | Jun 2013 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 136 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mountain View Residency 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAIGARH5,900+ in Raigarh
Filed coordinates, straight-line distance. 70 registered projects within 2 km.
Godrej Hillview Estate
Godrej Projects Development Limited
Haware My First Home Shil Phata Phase 2 Bldg 1
Haware Properties LLP
UNIMONT IMPERIA
RSM DESIGNERS
Haware My First Home Shil Phata Phase 1 Bldg 1
Haware Properties LLP
AeroEstate
HOABL Landmark Realty Private Limited
Haware My First Home Shil Phata Phase 2 Bldg 2
Haware Properties LLP
See every Raigarh project, with the district possession charts
Builder: Immaculate Developers
Immaculate Developers has 2 registrations on MahaRERA, including MOUNTAIN VIEW RESIDENCY 1 and Mountain View Residency 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Mountain View Residency 2 is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mountain View Residency 2?
The registered promoter entity is Immaculate Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mountain View Residency 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mountain View Residency 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mountain View Residency 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mountain View Residency 2?
The professionals named in the filing: Architect: Sunil Nawale; Architect: ROSHNI GUPTA; Engineer: Deltacom Structural Consultant LLP; Engineer: DIWAKAR R PATHAK; Chartered Accountant: MUKESH SONI; Chartered Accountant: NITIN B DHAVAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mountain View Residency 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback