Home / Browse projects / Mumbai Suburban, Maharashtra / MOHINI CASTLE

Completed No litigation declared Residential / Group Housing project

MOHINI CASTLE

By MOHINI SHELTORS PRIVATE LIMITED

RG-MH-12385 · RERA P51800005492 · Last updated on MahaRERA portal: 11 Jul 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 21 documents Report an error

MOHINI CASTLE is a Residential / Group Housing project by MOHINI SHELTORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005492 on 11 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameMOHINI CASTLE
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005492
  • ReraGenie IDRG-MH-12385

Builder

  • NameMOHINI SHELTORS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorH G CHAWLA
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed21 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MOHINI CASTLENA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

MOHINI CASTLE: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered1
Open Space31

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,459 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3927.48
Proposed, not sanctioned3,239 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJUHU VERSOVA LINK ROAD ANDHERI WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUDAY D TAMBE
EngineerMANOJ RAMKRISHNAN
PartnerRole in project
MOHINI SHELTORS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010218Jun 2021 → Dec 2022

Reason as filed by the promoterThe project has been completed upto 15th floor as per the CC granted by MCGM. The project has been delayed due to the under mentioned reasons which were beyond the control of the developers. 1. A stay granted by High Court Bombay, in NOM 534 of 2017 in suit No. 166 of 2017 filed by one Jyoti Khubchandani & Anr. Vs. Prem Bhuvan CHSL & Ors. on 10th Sept 2018, where the high Court directed the developer (Mohini Sheltors Pvt. Ltd.) not to carry out construction over and above the 10th floor. The said order was set aside by an appeal filed by Mohini Sheltors Pvt. Ltd. Vs. Jyoti Khubchandani & Anr.

Litigation declared3

CaseCourtStatus
01/2015HIGH COURT BOMBAYDue for Admission
40/2015HIGH COURT BOMBAYDue for Admission
373/2017HIGH COURT BOMBAYDue for Admission

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Jun 2023

Documents filed21

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: MOHINI CASTLE - FORM 4.pdf11 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MOHINI CASTLE - Occupancy Certificate.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 FY 20-21.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5 FY 21-22.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5(UT) FY 2018-2019_compressed.pdf26 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5(UT) FY 2019-2020_compressed.pdf26 Jul 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE_compressed.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY_compressed.pdf3 Jul 2021
Certificates of CA (Form 5)File: Mohini Castle - form 5.pdf16 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: MOHINI CASTLE 10TH FLOOR CC 11 JULY 2017.pdf6 Apr 2018
Building plan approvalFile: Building Plan Approval IOD Mohini Castle.pdf29 Jul 2017
Layout approvalFile: Copy of layout approval Mohini Castle.pdf29 Jul 2017
Copy of the legal title reportFile: Copy of the legal title report Mohini Castle.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of layout approval Mohini Castle.pdf29 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval IOD Mohini Castle.pdf29 Jul 2017
Declaration in FORM BFile: Declaration in FORM B Mohini Castle.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect Form 1 Mohini Castle.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineer FORM 2 Mohini Castle.pdf29 Jul 2017
Certificates of CA (Form 3)File: Certificate of CA Form 3 Mohini Castle.pdf29 Jul 2017
Details of encumbrancesFile: CERTIFICATE OF ENCUMBRANCES - MC.pdf28 Jul 2017
Proforma of Allotment letterFile: RERA DRAFT CASTLE AGREEMENT.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MOHINI CASTLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmMOHINI CASTLECompleted 144Lapsed / revoked 74Other 165Dot size: filed unitsN

Filed coordinates, straight-line distance. 383 registered projects within 2 km.

Builder: MOHINI SHELTORS PRIVATE LIMITED

MOHINI SHELTORS PRIVATE LIMITED has 2 registrations on MahaRERA, including MOHINI CASTLE and MOHINI TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MOHINI CASTLE is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MOHINI CASTLE?

The registered promoter entity is MOHINI SHELTORS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MOHINI CASTLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MOHINI CASTLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MOHINI CASTLE?

The professionals named in the filing: Architect: UDAY D TAMBE; Engineer: MANOJ RAMKRISHNAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MOHINI CASTLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MOHINI CASTLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MOHINI CASTLE to a free account