ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / MIND SPACE

Registration approved Commercial project

MIND SPACE

By PARADISE CITADEL PROJECTS PRIVATE LIMITED

RG-KA-62920 · RERA PRM/KA/RERA/1257/334/PR/200811/003512 · Last updated on RERA Karnataka portal: 25 Jul 2020

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 48 documents Report an error

MIND SPACE is a Commercial project by PARADISE CITADEL PROJECTS PRIVATE LIMITED in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200811/003512 on 11 Aug 2020. Possession is promised by 30 Jun 2023.

At a glance

Project

  • NameMIND SPACE
  • TypeCommercial
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/200811/003512
  • ReraGenie IDRG-KA-62920

Builder

  • NamePARADISE CITADEL PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatorySANDEEP K
  • DirectorsAJITH KUMAR, RAM KUMAR BEKAL

Key dates

this monthRegisteredAug 2020PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Aug 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MINDSPACE---07878

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 25 Jul 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 25 Jul 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,659 sq m
Named landowners4
LandownerVillageDistrict
AVALON LENNOX PATRAO--
PARADISE CITADEL PROJECTS PRIVATE LIMITED--
PUSHPARAJ JAIN--
K ARAVIND SHENOY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.50 cr

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200811/003512 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
SPECIFICATION OF MINDSPACEFile: MINDSPACE SPECIFICATION 25-07-2020.pdf25 Jul 2020
BANK ACCOUNT CLARIFICATIONFile: CHARTERED ACCOUNT LETTER.pdf25 Jul 2020
AFFIDAVIT UNDER SECTION 3(1)File: MS RERA AFDVT.pdf13 Jul 2020
SELF ATTESTED PANFile: PAN PARADISE CITADEL20200713_12450562.pdf13 Jul 2020
PAYMENT RECIEPTFile: RERA RECIEPT.pdf6 Jul 2020
ACCOUNT IS OPENED AS PER RERA GUIDELINES ONLY AND THE NAME OF ACCOUNT IS PROJECT MINDSPACEFile: MINDSPACE RERA ACCOUNT STATEMENT.pdf6 Jul 2020
IT S A CO-OWNERSHIP AND NOT JOINT DEVELOPMENT --E-KHATA ENCLOSEDFile: E KHATA.pdf6 Jul 2020
LOWER GROUND FLOORFile: LOWER GROUND FLOOR.PDF6 Jul 2020
AND 2 BASEMENT FLOORFile: 1ST AND 2ND BASEMENT.PDF6 Jul 2020
TYPICAL FLOOR PLAN OF ALL FLOORSFile: TYPICAL FLOOR PLAN.PDF6 Jul 2020
APPROVED SITE PLANFile: SITE PLAN.PDF6 Jul 2020
ENCUMBRANCE CERTIFICATEFile: FINAL EC.pdf6 Jul 2020
CertificateFile: CERTIFICATE OF INCORPORATION (1).PDF-
Plan 1-
Licence-
Plan 3-
Sale Deed Abish_compressed-
Plan 3-
Plan 2-
ALLOTMENT LETTER-converted-
Latest EC Mindspace-
41 cents Khata-
SALE DEED & UR COMPRESSED-
SALE DEED & UR-
CONVERSION ORDER-
SINGLE SITE APPROVAL-
FIRE NOC MINDSPACE20200623_11062454-
Unnamed document-
Plan 1-
Plan 3-
Plan 1-
CONVERSION ORDER-
FORM B MINDSPACE20200623_11123785-
Prospectus/BrochureFile: MindSpace Broucher.pdf-
Advertisement Copy 1File: MindSpace Broucher.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_200811_003512.xlsx-
Stability CertificateFile: STABILITY MINDSPACE.pdf-
NOC issued by the Fire Force department after completion of workFile: FIRE NOC MS20230622_12005759.pdf-
Occupancy CertificateFile: Mindspace Completion Certificate.pdf-
Consent for operation issued by KSPCBFile: CFO.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT 1_LIFT 2.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Mind Space Mescom.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: WATER CONNECTION.jpg-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: INFRA20230629_17283853.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: AMENITIES20230629_17295553.pdf-
Architect certificate for having completed the work(in format no 5)File: FORM 5 ARCHITECT.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: MINDSPACE rera completion.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep MIND SPACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmMIND SPACEOther 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: PARADISE CITADEL PROJECTS PRIVATE LIMITED

PARADISE CITADEL PROJECTS PRIVATE LIMITED has 1 registration on RERA Karnataka, including MIND SPACE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if MIND SPACE is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MIND SPACE?

The registered promoter entity is PARADISE CITADEL PROJECTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MIND SPACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in MIND SPACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MIND SPACE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MIND SPACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.