Home / Browse projects / Thane, Maharashtra / Midas Enclave

Registration lapsed No litigation declared Others project

Midas Enclave

By Mayra Developers

RG-MH-29569 · RERA P51700028808 · Last updated on MahaRERA portal: 1 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 25 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2024Possession promised25 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 7%
1Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

Midas Enclave is a Others project by Mayra Developers in Thane, Maharashtra, registered with MahaRERA as P51700028808 on 30 Mar 2021. Possession was promised by 30 Sep 2024 and is now 25 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMidas Enclave
  • TypeOthers
  • Location
    • OPP.JSW Gate
    • JSW Company
    • Washind (CT)
    • Shahapur
    • Thane
    • 421601
  • Pincode421601
  • RERA no.P51700028808
  • ReraGenie IDRG-MH-29569

Builder

  • NameMayra Developers
  • Entity typePartnership
  • PartnersPratik Gunwant Jain, Gunwant Manshalal Jain, Dinesh Sunderji Gosar, Ajay Kedarnath Gupta

Key dates

25 months past promisethis monthRegisteredMar 2021PromisedSep 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Mar 2021
  • Promised completion30 Sep 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed25 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 1NA80000
Building No 2NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 7%.

Building No 155%
ActivityProgress
Excavation100%
Basement (if any)1%
Podiums (if any)0%
Plinth1%
Stilt Floor1%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 255%
ActivityProgress
Excavation100%
Basement (if any)1%
Podiums (if any)0%
Plinth1%
Stilt Floor0%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,440 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Krushna Gajanan JadhavWashind (CT)Thane

Approvals and building plan

Permissible FSI4270.56
Proposed, not sanctioned4,271 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSMC Square Khopat Makhmali Talao Thane

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASHANT CHAWAN Kala Vastu
EngineerAjay Mahale
Chartered AccountantSagar Joshi & Associates
PartnerRole in project
Mayra Developers-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600689BHAWESH KHANDU PATILMayra Developers06/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Apr 2024

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy_compressed.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 85 WORK COMPETION CERTIFICATE B1.pdf25 Apr 2023
OtherFile: revised development agreement vasind_compressed-1-17.pdf7 Jul 2021
OtherFile: revised development agreement vasind_compressed-18-34.pdf7 Jul 2021
OtherFile: rera declaration mayra.pdf7 Jul 2021
Copy of the legal title reportFile: title certificate rera format.pdf26 Mar 2021
Declaration in FORM BFile: form B land owner new_compressed (1).pdf26 Mar 2021
Layout approvalFile: PLAN NO 3 compressed compressed.pdf20 Mar 2021
Copy of Layout Approval (in case of layout)File: PLAN NO 3 compressed compressed.pdf20 Mar 2021
Proforma of Allotment letterFile: Allotment Letter.pdf20 Mar 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf20 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER NEW_compressed (1)-1-2.pdf19 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER NEW_compressed (1)-3-4.pdf19 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER NEW_compressed (1)-5-6.pdf19 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER NEW_compressed (1)-7-8.pdf19 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_compressed.pdf19 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Compliance Certificate - Mayra Developers_compressed (1).pdf19 Mar 2021
Building plan approvalFile: PLAN NO 1 compressed.pdf6 Mar 2021
Building plan approvalFile: PLAN NO 2 compressed.pdf6 Mar 2021
Building plan approvalFile: PLAN NO 3 compressed compressed.pdf6 Mar 2021
PAN CardFile: MAYRA DEV PAN CARD.pdf6 Mar 2021
Details of encumbrancesFile: no encumbrance certificate Mayra Developers.pdf6 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN NO 1 compressed.pdf6 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN NO 2 compressed.pdf6 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN NO 3 compressed compressed.pdf6 Mar 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Midas Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JSW Company7,600+ in Thane

Builder: Mayra Developers

Mayra Developers has 1 registration on MahaRERA, including Midas Enclave. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Midas Enclave shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Midas Enclave is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Midas Enclave?

The registered promoter entity is Mayra Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Midas Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Midas Enclave?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Midas Enclave?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Midas Enclave?

The professionals named in the filing: Architect: PRASHANT CHAWAN Kala Vastu; Engineer: Ajay Mahale; Chartered Accountant: Sagar Joshi & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Midas Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Midas Enclave. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Midas Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.