ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / MHDC JV KHAIRI KAMPTEE PMAY PROJECT

Registration lapsed No litigation declared Others project

MHDC JV KHAIRI KAMPTEE PMAY PROJECT

By MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED

RG-MH-87918 · RERA P50500077416 · Last updated on MahaRERA portal: 1 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 6 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Apr 2026Possession promised6 months past this date
2 of 121Construction stages doneacross 11 buildings; furthest along: Excavation, 80%
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

MHDC JV KHAIRI KAMPTEE PMAY PROJECT is a Others project by MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500077416 on 13 Aug 2024. Possession was promised by 1 Apr 2026 and is now 6 months past that date.

At a glance

Project

  • NameMHDC JV KHAIRI KAMPTEE PMAY PROJECT
  • TypeOthers
  • Location
    • KHAIRI
    • BHILGAON
    • Kamptee
    • Nagpur
    • 440026
  • Pincode440026
  • RERA no.P50500077416
  • ReraGenie IDRG-MH-87918

Builder

  • NameMAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED
  • Entity typePublic Authority
  • GSTIN27AAMCM3997M1ZH
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing Director And Chief Executive OfficerAJIT MALHARI KAWADE
  • Other registrations8 more →
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

6 months past promisethis monthRegisteredAug 2024PromisedApr 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Aug 2024
  • Promised completion1 Apr 2026
  • Revised completionNone
  • Buildings11 building records
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 01NA140000
BUILDING NO 02NA140000
BUILDING NO 03NA140000
BUILDING NO 04NA140000
BUILDING NO 05NA140000
BUILDING NO 06NA140000
BUILDING NO 07NA140000
BUILDING NO 08NA140000
BUILDING NO 09NA140000
BUILDING NO 10NA140000
COMMERCIAL BUILDINGNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building11

As on 1 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Excavation, at 80%.

BUILDING NO 010%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 029%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 037%
ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 046%
ActivityProgress
Excavation66%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 050%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 063%
ActivityProgress
Excavation32%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 070%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 082%
ActivityProgress
Excavation26%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 097%
ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 109%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIAL BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed30919

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30,919
Open Space30,919
BuildingOpen SpaceTotal
BUILDING NO 013,0543,054
BUILDING NO 023,0543,054
BUILDING NO 033,0543,054
BUILDING NO 043,0543,054
BUILDING NO 053,0543,054
BUILDING NO 063,0543,054
BUILDING NO 073,0543,054
BUILDING NO 083,0543,054
BUILDING NO 093,0543,054
BUILDING NO 103,0543,054
COMMERCIAL BUILDING379379

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area46,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SANDESH HOMESBhilgaonNagpur
M/S ROYAL SANDESH BUSINESS PARK LLPBhilgaonNagpur

Approvals and building plan

Permissible FSI153835.27
Proposed, not sanctioned153,835 sq m
Buildings approved11
Buildings sanctioned11

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch3 GROUND, ATLANTA BUILDING, SHOP NO 2, NARIMAN POINT, MUMBAI - 400021

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSKYLINE ARCHITECTS
EngineerSKYLINE ARCHITECTSQ
Chartered AccountantEKBOTE DESHMUKH & CO
PartnerRole in project
MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: 01.pdf1 Jul 2024
Other - LegalFile: 02.pdf1 Jul 2024
Other - LegalFile: 03.pdf1 Jul 2024
Other - LegalFile: 04.pdf1 Jul 2024
Other - LegalFile: 05.pdf1 Jul 2024
Other - LegalFile: 06.pdf1 Jul 2024
Other - LegalFile: 07.pdf1 Jul 2024
Other - LegalFile: 08.pdf1 Jul 2024
Other - LegalFile: 09.pdf1 Jul 2024
Other - LegalFile: 10.pdf1 Jul 2024
Details of encumbrances concerned to FinanceFile: F L merged.pdf10 May 2024
Details of encumbrances concerned to LegalFile: F L merged.pdf10 May 2024
Other - LegalFile: 51 52 Sale Deed F.pdf10 May 2024
Other - TechnicalFile: Declartion cum Undertaiking Khairi.PDF10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Khairi Project (1).PDF21 Mar 2024
Layout approvalFile: 51,52- IOA Drawing_rotated-1.pdf15 Mar 2024
Layout approvalFile: 51,52- IOA Drawing_rotated-17.pdf15 Mar 2024
Building plan approvalFile: IOA letter 51, 52_pdf.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-2.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-3.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-4.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-5.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-6.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-7.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-8.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-9.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-10.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-11.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-12.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-13.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-14.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-15.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-16.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-18.pdf15 Mar 2024
Building plan approvalFile: 51,52- IOA Drawing_rotated-19.pdf15 Mar 2024
PAN CardFile: PAN-MHDC_rotated.pdf15 Mar 2024
Copy of the legal title reportFile: TSR 51 Khairi.PDF15 Mar 2024
Copy of the legal title reportFile: TSR 52 Khairi.PDF15 Mar 2024
Details of encumbrances concerned to FinanceFile: finance legal.pdf15 Mar 2024
Details of encumbrances concerned to LegalFile: finance legal.pdf15 Mar 2024
Copy of Layout Approval (in case of layout)File: 51,52- IOA Drawing_rotated-1.pdf15 Mar 2024
Copy of Layout Approval (in case of layout)File: 51,52- IOA Drawing_rotated-17.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: IOA letter 51, 52_pdf.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-2.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-3.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-4.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-5.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-6.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-7.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-8.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-9.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-10.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-11.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-12.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-13.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-14.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-15.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-16.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-18.pdf15 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 51,52- IOA Drawing_rotated-19.pdf15 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Mar 2024
Declaration about Commencement CertificateFile: Commencement cert khairi latest.PDF15 Mar 2024
Declaration in FORM BFile: Form B Promotor Khairi.pdf15 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect F.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Khairi Kamptee.PDF15 Mar 2024
CERSAI detailsFile: Cersai letter.pdf15 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf15 Mar 2024
Proforma of Agreement for saleFile: afs final.pdf15 Mar 2024
Proforma of Allotment letterFile: Allotment Letter Khairi_compressed.pdf15 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Letter Khairi.PDF15 Mar 2024
Deviation Report with respect to Allotment letterFile: No Deviation Allotment Khairi.PDF15 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Devation agreement.pdf15 Mar 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsStatusPromisedDelivered
MHDC JV MAJREWADI SOLAPUR PMAY PROJECTp52600028338GAT NO 67/3 67/2/A/1 69/1/A 67/1/A/1/3 at majrewadi tal north solapur dist solapur3,867OngoingMay 2024Not delivered

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MHDC JV KHAIRI KAMPTEE PMAY PROJECT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHILGAON2,800+ in Nagpur

Builder: MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED

MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED has 9 registrations on MahaRERA, including MHDC JV Wanadongri Nagpur PMAY Project Phase 2 and MHDC JV WANADONGRI NAGPUR PMAY PROJECT. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that MHDC JV KHAIRI KAMPTEE PMAY PROJECT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MHDC JV KHAIRI KAMPTEE PMAY PROJECT is delayed beyond 1 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MHDC JV KHAIRI KAMPTEE PMAY PROJECT?

The registered promoter entity is MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED, a public authority as per the filing. Its GSTIN 27AAMCM3997M1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MHDC JV KHAIRI KAMPTEE PMAY PROJECT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MHDC JV KHAIRI KAMPTEE PMAY PROJECT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MHDC JV KHAIRI KAMPTEE PMAY PROJECT?

The professionals named in the filing: Architect: SKYLINE ARCHITECTS; Engineer: SKYLINE ARCHITECTSQ; Chartered Accountant: EKBOTE DESHMUKH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MHDC JV KHAIRI KAMPTEE PMAY PROJECT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MHDC JV KHAIRI KAMPTEE PMAY PROJECT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MHDC JV KHAIRI KAMPTEE PMAY PROJECT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.