Home / Browse projects / Mumbai Suburban, Maharashtra / MESACON CROWN

Registered No litigation declared Residential / Group Housing project

MESACON CROWN

By MESACON SPACES LLP

RG-MH-06827 · RERA P51800055536 · Last updated on MahaRERA portal: 19 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 50.00 crore secured on the land, in favour of Aditya Birla Capital Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 92%
53 of 87Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

MESACON CROWN is a Residential / Group Housing project by MESACON SPACES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800055536 on 2 Apr 2024. Possession is promised by 30 Jun 2027. 34 of the 87 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameMESACON CROWN
  • TypeResidential / Group Housing
  • Location
    • S V ROAD
    • ANDHERI WEST
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • RERA no.P51800055536
  • ReraGenie IDRG-MH-06827

Builder

  • NameMESACON SPACES LLP
  • Entity typePartnership
  • PartnerVIKRAM RASHMIKANT MEHTA
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2024PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Apr 2024
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed56 files

Current status

39%34 of 87 units booked
80.6%Work done, per cost certificate

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA13042244
B WINGNA13043043

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 92%.

A WING72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises43%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed135

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots135
Closed/Covered135
BuildingClosed/CoveredTotal
A WING6868
B WING6767

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,337 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on12 Aug 2025
LandownerVillageDistrict
SHALIMAR APARTMENTS CHSLVileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI7769.88
Proposed, not sanctioned5,805 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSANGHAVI VILLA S V ROAD OPPOSITE ANDHERI FIRE STATION ANDHERI WEST MUMBAI 400058
Estimated costRs 46.05 cr
Cost incurredRs 37.12 cr
Work done80.61%
BuildingWingEstimatedIncurred
B WINGNARs 22.90 crRs 19.18 cr
A WINGNARs 21.40 crRs 17.94 cr
-NARs 1.75 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRIYANK BHATT
EngineerGANGA RAM SAHANI
EngineerCHANDRAKANT T PANDESHWAR
EngineerPRASANT SAHOO
Chartered AccountantDEEP GOKANI & CO.
Chartered AccountantBhavin Shah Associates
PartnerRole in project
MESACON SPACES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Crown - RERA Form 1 Arch Cert 31-03-26 - Q4.pdf19 May 2026
Withdrawal Update Form 2File: Crown RERA FORM 2_Eng Cert FY 25-26 Q4.pdf19 May 2026
Withdrawal Update Form 3File: Crown_CA Certificate_Form-3 FY 25-26 Q4.pdf19 May 2026
Withdrawal Update Form 1File: Crown - RERA Form 1 Arch Cert 31-12-25 - Q3.pdf18 May 2026
Withdrawal Update Form 2File: Crown RERA FORM 2_Eng Cert FY 25-26 Q3.pdf18 May 2026
Withdrawal Update Form 3File: Crown_CA Certificate_Form-3 FY 25-26 Q3.pdf18 May 2026
Withdrawal Update Form 1File: Crown Architect Certificate 30 Sep 2025 - RERA Portal - Q2.pdf16 May 2026
Withdrawal Update Form 2File: Crown RERA FORM 2_Eng Cert FY 25-26 Q2.pdf16 May 2026
Withdrawal Update Form 3File: Crown_CA Certificate_Form-3 FY 25-26 Q2.pdf16 May 2026
Withdrawal Update Form 1File: Crown Architect Certificate 30 June 2025.pdf15 May 2026
Withdrawal Update Form 2File: Crown RERA FORM 2_Eng Cert FY 25-26 Q1.pdf15 May 2026
Withdrawal Update Form 3File: Crown_CA Certificate_Form-3_RERA Portal_Q1.pdf15 May 2026
Form 2A (FY 2025-2026)File: Crown_Form-2A_25-26.pdf28 Apr 2026
Form 5 (FY 2024-2025)File: Mesacon Crown_RERA Form 5_FY 24-25.pdf5 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Crown_CA Certificate_31-03-25 - Signed.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mesacon Crown Engineer Certificate 31Mar25.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Crown Architect Certificate 31 Mar 2025 signed.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Crown_CA Certificate_31-12-24 Signed.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mesacon Crown Engineer Certificate 31Dec24.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Crown Architect Certificate 31 Dec 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Crown_Engineers Certificate_30-09-24.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Crown_CA Certificate_30-09-24 Signed.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Crown_Architech Certificate_30-09-24.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MSLLP_Mesacon Crown_Architect Certificate_30-06-24.pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MSLLP_Mesacon Crown_Engineers Certificate_30-06-24.pdf9 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MSLLP_Mesacon Crown_CA Certificate_30-06-24_Signed.pdf9 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate - Crown (Shalimar).pdf8 Jul 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate - Crown (Shalimar).pdf8 Jul 2024
Copy of the legal title reportFile: Mesacon Crown_Titel Certificate_14-05-24 (1).pdf17 May 2024
Building plan approvalFile: IOD_Mesacon Crown(Shalimar.pdf6 May 2024
Layout approvalFile: 04-04-2024_DRAWING Shalimar.pdf6 May 2024
Copy of Layout Approval (in case of layout)File: 04-04-2024_DRAWING Shalimar.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD_Mesacon Crown(Shalimar.pdf6 May 2024
Other - TechnicalFile: 1 Other - Technical.pdf11 Mar 2024
Declaration about Commencement CertificateFile: Mesacon Crown_CC Declaration (1).pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate CROWN.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate (7).pdf8 Mar 2024
Deviation Report with respect to model copy of AgreementFile: deviation agreement.pdf8 Mar 2024
Copy of the legal title reportFile: Legal Title Reports_Mesacon Crown (1).pdf7 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: 2412502_FirstCC_signed.pdf7 Mar 2024
Proforma of Allotment letterFile: final allotment letter.pdf15 Feb 2024
Deviation Report with respect to Allotment letterFile: Mesacon Crown_Deviation Allotment Letter.pdf15 Feb 2024
Proforma of Agreement for saleFile: mesacon crown.pdf17 Jan 2024
Layout approvalFile: Drawing Amended on 16102023_1-4.pdf11 Jan 2024
Layout approvalFile: Drawing Amended on 16102023_5-end.pdf11 Jan 2024
Copy of Layout Approval (in case of layout)File: Drawing Amended on 16102023_1-4.pdf11 Jan 2024
Copy of Layout Approval (in case of layout)File: Drawing Amended on 16102023_5-end.pdf11 Jan 2024
Declaration in FORM BFile: Mesacon Crown_Form B Promoter (1).pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI (4).pdf20 Nov 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance Self Declaration (6).pdf18 Nov 2023
Details of encumbrances concerned to LegalFile: No Encumbrance Self Declaration (6).pdf18 Nov 2023
CERSAI detailsFile: Cresai Declaration.pdf18 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Separate Bank Account.pdf18 Nov 2023
Building plan approvalFile: 2390947_IOD_signed.pdf7 Oct 2023
PAN CardFile: MS LLP PAN.pdf7 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: 2390947_IOD_signed.pdf7 Oct 2023

How this compares with Mumbai Suburban

39%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MESACON CROWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI WEST6,700+ in Mumbai Suburban

Builder: MESACON SPACES LLP

MESACON SPACES LLP has 2 registrations on MahaRERA, including MESACON CROWN and MESACON GREENS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MESACON CROWN is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MESACON CROWN?

The registered promoter entity is MESACON SPACES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MESACON CROWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MESACON CROWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MESACON CROWN?

The professionals named in the filing: Architect: PRIYANK BHATT; Engineer: GANGA RAM SAHANI; Engineer: CHANDRAKANT T PANDESHWAR; Engineer: PRASANT SAHOO; Chartered Accountant: DEEP GOKANI & CO.; Chartered Accountant: Bhavin Shah Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MESACON CROWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MESACON CROWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MESACON CROWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.