Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 85%
64 of 82Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Mediterranean is a Residential / Group Housing project by Fortune Investments in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048471 on 3 Jan 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 18 of the 82 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameMediterranean
  • TypeResidential / Group Housing
  • Location
    • V P Road
    • Andheri west
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800048471
  • ReraGenie IDRG-MH-29895

Builder

  • NameFortune Investments
  • Entity typePartnership
  • GSTIN27AABFF6830A1ZW
  • PartnersRahim Raje Sunesara, Imran Rahim Sunesara

Key dates

this monthRegisteredJan 2023First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed57 files

Current status

22%18 of 82 units booked
51.8%Work done, per cost certificate

Figures as on 21 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MediterraneanNA161575782

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

Mediterranean: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes20%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes20%
Water conservation /Rain water harvestingYes20%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,243 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on4 Jun 2025

Approvals and building plan

Sanctioning authorityBrihanmumbai Municipal Corporation
Permissible FSI4363.13
Proposed, not sanctioned3,583 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRoop Apts S V Road, Jogeshwari W Mumbai - 400102
Estimated costRs 17.00 cr
Cost incurredRs 8.80 cr
Work done51.76%
BuildingWingEstimatedIncurred
MediterraneanNARs 16.00 crRs 8.80 cr
-NARs 1.00 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC S AssoCiates
ArchitectCHIRAG S. RAYANI
EngineerUJAS R. LIMBANI
EngineerMr. RAKESH KUMAR A. SINGH
EngineerYUNUS KHAN JAFAR KHAN PATHAN
Chartered AccountantVikas Asawa
Chartered AccountantVahid Maredia
PartnerRole in project
Fortune Investments-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA08052620875Dec 2025 → Mar 2027

Reason as filed by the promoterThe project has experienced delays in completion due to a combination of factors, including slower-than-anticipated construction progress, market conditions affecting sales and cash flow, delays in receipt of funds from customers, and challenges in procurement of materials and deployment of contractors. Additionally, certain statutory approvals, design modifications, and compliance-related requirements required additional time for implementation. The promoter has continued construction activities and remains committed to completing the balance work in accordance with the approved plans and app

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1_Architect 30-06-2025.pdf21 Apr 2026
Withdrawal Update Form 1File: Form_1_Architect 30092025.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1_Architect Certificate_31122025.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2_Engineer Certificate 30-06-2025.pdf21 Apr 2026
Withdrawal Update Form 2File: Form_2_Engineer Certificate 30092025.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2_Enineer Certifiacte_31122025.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3_ Fortune_30062025.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3_30092025.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 - Fortune - 31122025.pdf21 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A-9 Gourav Tajdin.pdf21 Mar 2026
Form 5 (FY 2024-2025)File: Form 5.pdf21 Mar 2026
Withdrawal Update Form 1File: Mediterranean Form I RERA - Architect Certificate Jan 2023.pdf11 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate1.pdf11 Mar 2026
Withdrawal Update Form 3File: Forms 3 Sept 2023-1-231025-163848_compressed.pdf11 Mar 2026
Commencement Certificates / NA Order for plotted developmentFile: Mediterranean RERA Certificate.pdf12 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Mediterranean Full CC.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mediterranean Form I RERA - Architect Certificate Jan 2023.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf25 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate1.pdf25 Oct 2023
Disclosure of sold/ booked inventoryFile: Mediterranean Unsold.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forms 3 Mar 2023-1-231025-163933_compressed.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forms 3 June 2023-1-231025-163450_compressed.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forms 3 Sept 2023-1-231025-163848_compressed.pdf25 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MEDITERRIAN RERA FORM I.pdf21 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MEDITERRIAN RERA Archit.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mediterranean Eng Cerificate.pdf26 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mediterranean Form I RERA - Architect Certificate 2023.pdf1 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS CERTIFICATE Quality Assurance.pdf1 Aug 2023
Proforma of Allotment letterFile: New AL For Fortune.pdf24 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation AL Fortune.pdf24 Dec 2022
Proforma of Agreement for saleFile: New Fortune AFS.pdf23 Dec 2022
Deviation Report with respect to model copy of AgreementFile: ilovepdf_merged (5).pdf23 Dec 2022
Details of encumbrances concerned to FinanceFile: Fortune Fin Encum.pdf8 Dec 2022
Details of encumbrances concerned to LegalFile: Fortune Fin Encum.pdf8 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report_200254295071_For_Asset_Based_Search_08_12_2022_14_55_07_491.pdf8 Dec 2022
Details of encumbrances concerned to FinanceFile: No encumbrance certificate.pdf5 Dec 2022
Details of encumbrances concerned to FinanceFile: Encumbrances of Concern to Legal-No Litigation.pdf21 Nov 2022
Details of encumbrances concerned to LegalFile: Encumbrances of Concern to Legal-No Litigation.pdf21 Nov 2022
Details of encumbrances concerned to LegalFile: No encumbrance certificate.pdf1 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Declaration - T 5.pdf1 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 2311285_FurtherCC_signed.pdf21 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: 2070334943NoteSheet_14992_signed.pdf21 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf21 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate form 3s_p1-4.pdf1 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate form 3s_p5-8.pdf1 Jun 2022
OtherFile: Plan amendment letter.pdf27 May 2022
Copy of the legal title reportFile: Title Certificate For RERA Mediterranean.pdf22 Mar 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf22 Mar 2022
Declaration in FORM BFile: Form B.pdf18 May 2021
Layout approvalFile: Approved Drawing_1.pdf12 May 2021
Layout approvalFile: Approved Drawing_2.pdf12 May 2021
Building plan approvalFile: IOD Mediterranean signed.pdf12 May 2021
PAN CardFile: Fortune Investments Pan Card.pdf12 May 2021
Copy of Layout Approval (in case of layout)File: Approved Drawing_1.pdf12 May 2021
Copy of Layout Approval (in case of layout)File: Approved Drawing_2.pdf12 May 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD Mediterranean signed.pdf12 May 2021

How this compares with Mumbai Suburban

22%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 15 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mediterranean on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri west6,700+ in Mumbai Suburban

2 kmMediterraneanLapsed / revoked 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Fortune Investments

Fortune Investments has 1 registration on MahaRERA, including Mediterranean. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Mediterranean is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mediterranean?

The registered promoter entity is Fortune Investments, a partnership as per the filing. Its GSTIN 27AABFF6830A1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mediterranean?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mediterranean?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mediterranean?

The professionals named in the filing: Architect: C S AssoCiates; Architect: CHIRAG S. RAYANI; Engineer: UJAS R. LIMBANI; Engineer: Mr. RAKESH KUMAR A. SINGH; Engineer: YUNUS KHAN JAFAR KHAN PATHAN; Chartered Accountant: Vikas Asawa. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mediterranean?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mediterranean. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mediterranean to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.