Red flags

  • Completion date moved by 55 months, 4 of them under MahaRERA's automatic 4-month extension
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedmoved 55 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
6 of 41Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 221 documents Report an error

MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD is a Residential / Group Housing project by MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD in Raigarh, Maharashtra, registered with MahaRERA as P52000020663 on 30 Apr 2019. Possession is promised by 30 Jun 2028. The completion date has moved by 55 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 35 of the 41 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameMAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD
  • TypeResidential / Group Housing
  • Location
    • SECTOR 21 TRANS RAILWAY AREA
    • NEW PANVEL WEST
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000020663
  • ReraGenie IDRG-MH-03212

Builder

  • NameMAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD
  • Entity typeSociety
  • GSTIN27AAFAM7988M1ZL
  • ChairpersonSAMBHAJI BHIKU NIKAM
  • SecretoryMAKRAND J NARGOLKAR

Key dates

this monthRegisteredApr 2019First promiseNov 2023Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Apr 2019
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 28 Nov 2023)
  • Buildings2 building records
  • Documents filed221 files

Current status

85%35 of 41 units booked
74.4%Work done, per cost certificate

Figures as on 19 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD PHASE INA16041041
NOT APPLICABLENA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD PHASE I81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
NOT APPLICABLE0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered40
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,655 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Oct 2026
LandownerVillageDistrict
MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTDNew PanvelRaigarh

Approvals and building plan

Sanctioning authorityPanvel Municipal Corporation
Permissible FSI2483.0
Proposed, not sanctioned1,655 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch82 C RAJASHREE BLDG N G ACHARYA MARG CHEMBUR MUMBAI 400071
Estimated costRs 16.00 cr
Cost incurredRs 11.91 cr
Work done74.41%
BuildingWingEstimatedIncurred
MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD PHASE INARs 16.00 crRs 11.91 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLILADHAR PARAB ARCHITECTS & DESIGNERS
EngineerRusheekesh Pujari
EngineerSTRUCTWEL DESIGNERS & CONSULTANTS PVT LTD
Chartered AccountantB N DUDANI & CO
Chartered AccountantAmitha Vittala Shetty
PartnerRole in project
MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD-

Extensions4

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jun 2026 → Oct 2026

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EXT52000017990Nov 2023 → Nov 2024

Reason as filed by the promoterDue to introduction of UDCPR there were many changes in the development control regulations. Hence we had to take approval of amended plans for which NOC from CIDCO was necessary. There were some issues in CIDCO regarding issuance of NOC and hence it took quite some time for the same. We expect to get the same shortly after that we will submit the plans for amended approvals. Hence we request extension of a year for our project completion.

EXT52000027504Nov 2023 → Jun 2026

Reason as filed by the promoterWe have applied to CIDCO for additional strip of Land lying between the boundary and 20 mtrs wide road in the front of the Plot on 08.01.19 and then again on 13.06.24. We expect to receive the same by 31stMar'25 and after we get the land we will apply for converting residential plot to Residential plus commercial plot. Approval of amended plans after consuming FSI available due to additional strip of land and conversion from Residential to Residential plus commercial from Panvel Municipal Corporation is expected by 31stJul'25

EA24102640601Nov 2023 → Jun 2028

Reason as filed by the promoterDear Sir/Ma’am, We, MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD, hereby declare the following with respect to the project “MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD” bearing registration number P52000020663 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to comp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed221

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 221 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Qtr2.pdf19 Oct 2026
Withdrawal Update Form 2File: Form 2 Qtr2.pdf19 Oct 2026
Withdrawal Update Form 3File: Form 3 Qtr2.pdf19 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q2.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q3.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q4.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q2.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q3.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q4.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q2.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q3.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q4.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q2.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q3.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q4.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: Form 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q2.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026
Form 2File: Form 2.pdf6 Oct 2026
Form 3File: From 3.pdf6 Oct 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q3.pdf6 Oct 2026
Form 1File: Form 1.pdf6 Oct 2026

How this compares with Raigarh

85%of this project is bookeddistrict median 28%
21%of Raigarh projects moved their completion datethis one moved by 55 months
25%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEW PANVEL WEST5,900+ in Raigarh

2 kmMAZAGON DOCK SWAPNAPURTICompleted 202Lapsed / revoked 53Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 366 registered projects within 2 km.

Builder: MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD

MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD has 1 registration on MahaRERA, including MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD?

The registered promoter entity is MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD, a society as per the filing. Its GSTIN 27AAFAM7988M1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD?

The professionals named in the filing: Architect: LILADHAR PARAB ARCHITECTS & DESIGNERS; Engineer: Rusheekesh Pujari; Engineer: STRUCTWEL DESIGNERS & CONSULTANTS PVT LTD; Chartered Accountant: B N DUDANI & CO; Chartered Accountant: Amitha Vittala Shetty. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAZAGON DOCK SWAPNAPURTI CO-OP HSG SOC LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.