Mayur Samruddhi Phase - II D wing
By Bunty Properties Unit No. X
RG-MH-20646 · RERA P52100007199 · Last updated on MahaRERA portal: 1 Mar 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mayur Samruddhi Phase - II D wing is a Residential / Group Housing project by Bunty Properties Unit No. X in Pune, Maharashtra, registered with MahaRERA as P52100007199 on 17 Aug 2017. The registration is recorded completed; possession was promised by 31 Jul 2028.
At a glance
Project
- NameMayur Samruddhi Phase - II D wing
- TypeResidential / Group Housing
- Location
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411035
- Pincode411035
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100007199
- ReraGenie IDRG-MH-20646
Builder
- NameBunty Properties Unit No. X
- Entity typePartnership
- PartnersRoshanlal Rameshwar Agarwal, Mahendra Ramkarandas Agarwal, Ishwardas Dariyanmal Valecha, Subhash Ramkarandas Agarwal, Subhash Ramprakash Agarwal, Sanjay Shamlal Singhal, Sandeep Shrikrishna Goyal
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on17 Aug 2017
- Promised completion31 Jul 2028
- Revised completionNone
- Buildings2 building records
- Documents filed122 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing D - 1st and 2nd Floor | NA | 2 | 0 | 0 | 0 | 0 |
| Wing D - 2nd to 5th Floor | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 1 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 33%.
Wing D - 1st and 2nd Floor45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 33% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 5% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Wing D - 2nd to 5th Floor31%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 33% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 5% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 20% |
| Open Parking | Yes | 50% |
Parking filed73
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing D - 1st and 2nd Floor | 0 | 3 | 3 |
| Wing D - 2nd to 5th Floor | 70 | 0 | 70 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Agarwal Consultants |
| Engineer | Spectrum Consultants |
| Partner | Role in project |
|---|---|
| Bunty Properties Unit No. X | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jan 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jan 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Mar 2025
Documents filed122
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: D_COMPLETION CERTIFICATE PH-II_10-1-2025_compressed.pdf | 1 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 22.pdf | 25 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 22.pdf | 25 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 22.pdf | 25 Mar 2023 |
| Form 2AFile: Form 2A March 22.pdf | 25 Mar 2023 |
| Form 2AFile: Form 2A Sept 22.pdf | 25 Mar 2023 |
| Form 2AFile: Form 2A Dec 22.pdf | 25 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Cert MS D TILL-MARCH-2022.pdf | 25 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Cert MS D TILL-SEP-2022.pdf | 25 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Cert MS D TILL-DEC-2022.pdf | 25 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch till Mar 22.pdf | 24 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch till Sept 22.pdf | 24 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch till Dec 22.pdf | 24 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Certificate.pdf | 11 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch certificate.pdf | 24 Feb 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng certificate.pdf | 24 Feb 2022 |
| Form 2AFile: Form2A Eng certificate.pdf | 24 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold- booked inventory.pdf | 24 Feb 2022 |
| Certificates of CA (Form 3)File: Form 3 CA certificate.pdf | 24 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architch Certificate.pdf | 12 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 11 Oct 2021 |
| Form 2AFile: Form 2A.pdf | 11 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold- booked inventory.pdf | 11 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf | 12 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf | 12 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 12 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineers.pdf | 12 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineers.pdf | 12 Aug 2021 |
| Form 2AFile: Form 2A.pdf | 12 Aug 2021 |
| Form 2AFile: Form 2A.pdf | 12 Aug 2021 |
| Form 2AFile: Form 2A.pdf | 12 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf | 12 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf | 12 Aug 2021 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf | 12 Aug 2021 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf | 12 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: MAYUR SAMRUDDHI.pdf | 12 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Annual Report.pdf | 12 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Annual Report.pdf | 12 Aug 2021 |
| Proforma of Allotment letterFile: Performa agreement.pdf | 28 Jan 2021 |
| Building plan approvalFile: 2-13-Layout.pdf | 27 Jan 2021 |
| Building plan approvalFile: 3-13-basement floor and club house.pdf | 27 Jan 2021 |
| Building plan approvalFile: 4-13-E wing ground and first floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 5-13-E wing second, third, fifth and ninth floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 6-13-E wing fourth, sixth, seventh, eighth and tenth floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 7-13-E wing sections.pdf | 27 Jan 2021 |
| Building plan approvalFile: 8-13-E wing elevation.pdf | 27 Jan 2021 |
| Building plan approvalFile: 9-13-D wing ground and first floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 10-13-D wing second and third floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 11-13-D wing fourth and fifth floor.pdf | 27 Jan 2021 |
| Building plan approvalFile: 12-13-D wing sixth floor and sections.pdf | 27 Jan 2021 |
| Building plan approvalFile: 13-13-D wing sections and elevation.pdf | 27 Jan 2021 |
| Layout approvalFile: 1-13-subdivision.pdf | 27 Jan 2021 |
| Building plan approvalFile: 1-13-subdivision.pdf | 27 Jan 2021 |
| Copy of Layout Approval (in case of layout)File: 1-13-subdivision.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 1-13-subdivision.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 2-13-Layout.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 3-13-basement floor and club house.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 4-13-E wing ground and first floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 5-13-E wing second, third, fifth and ninth floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 6-13-E wing fourth, sixth, seventh, eighth and tenth floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 7-13-E wing sections.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 8-13-E wing elevation.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 9-13-D wing ground and first floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 10-13-D wing second and third floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 11-13-D wing fourth and fifth floor.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 12-13-D wing sixth floor and sections.pdf | 27 Jan 2021 |
| Building Plan Approval (IOD)File: 13-13-D wing sections and elevation.pdf | 27 Jan 2021 |
| Details of encumbrancesFile: RELEASE DEED.pdf | 25 Jan 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 25 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architct.pdf | 31 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 31 Jan 2020 |
| Form 2AFile: Form 2A.pdf | 31 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architct.pdf | 2 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form no 2.pdf | 2 Nov 2019 |
| Form 2AFile: Form 2A.pdf | 2 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1.pdf | 30 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2.pdf | 30 Apr 2019 |
| Form 2AFile: FORM-2A D-WING.pdf | 30 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE D-WING PH-II-20-01-2019.pdf | 29 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-1 Architch Certificate.pdf | 23 Jan 2019 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Mayur Samruddhi Phase - I | Survey no 180 Hissa no 1 Akurdi Pune | 86 | Completed | Jun 2014 | Late, Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 122 filed documents as one ZIP, foldered, with a manifest
Keep Mayur Samruddhi Phase - II D wing on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune
Filed coordinates, straight-line distance. 86 registered projects within 2 km.
YOO PRISTINE
M/S MEGAPILLAR REALTY LLP
ENVOGUE2
Zenethist Realty LLP
ONE PLATINUM
MATRIX DEVELOPERS
VITTHAL CAPITAL
M/S A. V. CORPORATION
Vasant Estella
SHRIKRISHNA WONDER PROPERTIES
MY HOME AKURDI
RAVET LAND DEVELOPERS LLP
Builder: Bunty Properties Unit No. X
BUNTY PROPERTIES UNIT NO. X has 3 registrations on MahaRERA, including Mayur Samruddhi Phase-I Building B and MAYUR SAMRUDDHI PHASE- II. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Mayur Samruddhi Phase - II D wing is delayed beyond 31 Jul 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mayur Samruddhi Phase - II D wing?
The registered promoter entity is Bunty Properties Unit No. X, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mayur Samruddhi Phase - II D wing?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mayur Samruddhi Phase - II D wing?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mayur Samruddhi Phase - II D wing?
The professionals named in the filing: Architect: Agarwal Consultants; Engineer: Spectrum Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mayur Samruddhi Phase - II D wing?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.