Home / Browse projects / Palghar, Maharashtra / EVERSHINE AMAVI 303 PHASE 3

Registration lapsed No litigation declared Residential / Group Housing project

EVERSHINE AMAVI 303 PHASE 3

By EVERSHINE DEVELOPERS

RG-MH-28084 · RERA P99000024753 · Last updated on MahaRERA portal: 8 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
35 of 77Construction stages doneacross 7 buildings; furthest along: Internal walls, 60%
385 of 568Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

EVERSHINE AMAVI 303 PHASE 3 is a Residential / Group Housing project by EVERSHINE DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000024753 on 2 Mar 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 183 of the 568 units on this registration are recorded sold or booked, and 35 of 77 construction stages are filed complete.

At a glance

Project

  • NameEVERSHINE AMAVI 303 PHASE 3
  • TypeResidential / Group Housing
  • Location
    • Chikhadongari Road
    • Global City Virar West
    • Dongare
    • Palghar
    • 401303
  • Pincode401303
  • RERA no.P99000024753
  • ReraGenie IDRG-MH-28084

Builder

  • NameEVERSHINE DEVELOPERS
  • Entity typePartnership
  • PartnerSANTOSH RAJKUMAR LUDHANI
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

10 months past promisethis monthRegisteredMar 2020First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Mar 2020
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 30 Dec 2024)
  • Buildings7 building records
  • Documents filed63 files

Current status

32%183 of 568 units booked
68.0%Work done, per cost certificate

Figures as on 8 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 6NA161454458
BUILDING NO 7NA161454963
BUILDING NO 8NA161454458
BUILDING NO 9NA161454559
BUILDING NO 24NA16141100110
BUILDING NO 25NA16141100110
BUILDING NO 26NA16141100110

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 8 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

35 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Internal walls, at 60%.

BUILDING NO 670%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 770%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 870%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 970%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 2470%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 2570%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
BUILDING NO 2670%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 8 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes70%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes40%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes-
Open ParkingYes0%

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Closed/Covered7
Open Space59
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 6189
BUILDING NO 7189
BUILDING NO 811112
BUILDING NO 9189
BUILDING NO 24189
BUILDING NO 25189
BUILDING NO 26189

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,650 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2025

Approvals and building plan

Permissible FSI24001.2
Proposed, not sanctioned24,001 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGABBANA HOUSE 15TH ROAD KHAR WEST MUMBAI 400052 MAHARASTRA
Estimated costRs 119.25 cr
Cost incurredRs 81.13 cr
Work done68.03%
BuildingWingEstimatedIncurred
BUILDING NO 24NARs 18.67 crRs 12.37 cr
BUILDING NO 25NARs 18.67 crRs 12.37 cr
BUILDING NO 26NARs 18.67 crRs 12.37 cr
BUILDING NO 7NARs 13.03 crRs 8.63 cr
-NARs 12.94 crRs 10.69 cr
BUILDING NO 6NARs 12.43 crRs 8.23 cr
BUILDING NO 8NARs 12.43 crRs 8.23 cr
BUILDING NO 9NARs 12.43 crRs 8.23 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShah Gattani Consultants
EngineerAbhijeet Londhe
Chartered AccountantRishi Sekhri
Chartered AccountantBanshi Jain and Associate
Chartered AccountantAmit Verma& Co
PartnerRole in project
EVERSHINE DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000024879Dec 2024 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Feb 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate-phase-3-Jun25.pdf8 Oct 2025
Withdrawal Update Form 1File: Architect Certificate-phase-3-Jun25.pdf8 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate Phase-3 June25.pdf8 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate Phase-3 June25.pdf8 Oct 2025
Withdrawal Update Form 3File: FORM 3 AMAVI PHASE3 Jun-25.pdf8 Oct 2025
Withdrawal Update Form 3File: FORM 3 AMAVI PHASE3 Jun-25.pdf8 Oct 2025
Withdrawal Update Form 1File: Architect Certificate-phase-3-Jun25.pdf7 Oct 2025
Withdrawal Update Form 2File: Engineer's Certificate Phase-3.pdf7 Oct 2025
Withdrawal Update Form 3File: FORM 3 AMAVI PHASE3 Jun-25.pdf7 Oct 2025
Form 1File: Architect Certificate Form 1phase-3-Mar25.pdf27 Sep 2025
Form 2File: Engineer's Certificate Form 2phase 3-Mar 2025.pdf27 Sep 2025
Form 3File: CA Amavi 3 Form3 form March25.pdf27 Sep 2025
Disclosure of Sold and Booked InventoryFile: CA Amavi 3 Form3 form March25.pdf27 Sep 2025
Withdrawal Update Form 1File: Architect Certificate-phase-3-Mar25.pdf27 Sep 2025
Withdrawal Update Form 1File: Architect Certificate-phase-3-Mar25.pdf27 Sep 2025
Withdrawal Update Form 1File: Architect Certificate-phase-3-Mar25.pdf27 Sep 2025
Withdrawal Update Form 2File: Engineer's Certificate Phase-3.pdf27 Sep 2025
Withdrawal Update Form 2File: Engineer's Certificate Phase-3.pdf27 Sep 2025
Withdrawal Update Form 2File: Engineer's Certificate Phase-3.pdf27 Sep 2025
Withdrawal Update Form 3File: Form3-Evershine Amavi 303 Phase 3.pdf27 Sep 2025
Withdrawal Update Form 3File: Form3-Evershine Amavi 303 Phase 3.pdf27 Sep 2025
Withdrawal Update Form 3File: Form3-Evershine Amavi 303 Phase 3.pdf27 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-AMAVI PHASE 3(Dec-24)1.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Form-1-PhaseIII.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: Circular 29_11zon (1).pdf23 Oct 2024
Declaration about Commencement CertificateFile: Format D.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate-Form2-phase-3.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-AMAVI PHASE 3(Sept-24).pdf20 Oct 2024
Declaration in FORM BFile: Affidavit cum Declaration for Extenstion(Amavi PH3).pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1-Form 2A - Evershine Amavi 303 Phase 3 2019-20.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2-Form 2A - Evershine Amavi 303 Phase 3 2020-21.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3-Form 2A - Evershine Amavi 303 Phase 3 2021-22.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4-Form 2A - Evershine Amavi 303 Phase 3 2022-23.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5-Form 2A - Evershine Amavi 303 Phase 3 2023-24.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23 24.pdf18 Oct 2024
Details of encumbrancesFile: DETAILS OF ENCUMBRANCE BAJAJ 50CCCCCR.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3-Evershine Amavi 303 Phase 3.pdf9 Nov 2023
Proforma of Agreement for saleFile: 1 Proforma of Agreement.pdf4 Oct 2023
Proforma of Allotment letterFile: Model Allotment Letter.pdf4 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Amavi Phase 3_Form 5 (FY 22-23).pdf3 Oct 2023
Details of encumbrancesFile: Bajaj Loan Encumbrance for Phase 3.pdf4 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 Fy21-22 EAmaviphase3.pdf15 Nov 2022
Details of encumbrancesFile: Detail of Encumbrance From Bajaj housing Finance Ltd.pdf13 Oct 2021
Copy of the legal title reportFile: Evershine Amavi Avenue I Title Certificate.pdf28 Feb 2020
Proforma of Allotment letterFile: Model Allotment Letter Evershine Amavi.pdf28 Feb 2020
Layout approvalFile: Layout 2019.pdf25 Feb 2020
Building plan approvalFile: RSI 1 21-26 Typ.pdf25 Feb 2020
Building plan approvalFile: TI 1 - 6-9 Typ.pdf25 Feb 2020
PAN CardFile: Evershine Developers PAN.pdf25 Feb 2020
Details of encumbrancesFile: Declatration.pdf25 Feb 2020
Copy of Layout Approval (in case of layout)File: Layout 2019.pdf25 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: RSI 1 21-26 Typ.pdf25 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: TI 1 - 6-9 Typ.pdf25 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE 2018.pdf25 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: REVISED COMMENCEMENT CERTIFICATE2019.pdf25 Feb 2020
Declaration in FORM BFile: Evershine Amavi303 Form B phase3.pdf25 Feb 2020
Declaration in FORM BFile: Avenue I Release cum Transfer(Ev Amavi303)1.pdf25 Feb 2020
Declaration in FORM BFile: Avenue I Release cum Transfer(Ev Amavi303)2.pdf25 Feb 2020
Declaration in FORM BFile: Avenue I Release cum Transfer(Ev Amavi303)3.pdf25 Feb 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amavi 303 Phase 3 Architect Certificate.pdf25 Feb 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Phase-3.pdf25 Feb 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE phase3.pdf25 Feb 2020
Proforma of Allotment letterFile: draft agreement for sale.pdf25 Feb 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GLOBAL CITY AVENUE JMGHGLOBAL CITY4,500CompletedDec 2014May 2014
EVERSHINE EMBASSYVEERA DASAI ROAD ANDHERI WEST208CompletedMay 2010May 2010

How this compares with Palghar

32%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EVERSHINE AMAVI 303 PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Global City Virar West3,200+ in Palghar

Builder: EVERSHINE DEVELOPERS

EVERSHINE DEVELOPERS has 4 registrations on MahaRERA, including EVERSHINE AMAVI 303 PHASE 1 and EVERSHINE AMAVI 303 PHASE 2. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that EVERSHINE AMAVI 303 PHASE 3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if EVERSHINE AMAVI 303 PHASE 3 is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EVERSHINE AMAVI 303 PHASE 3?

The registered promoter entity is EVERSHINE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EVERSHINE AMAVI 303 PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EVERSHINE AMAVI 303 PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EVERSHINE AMAVI 303 PHASE 3?

The professionals named in the filing: Architect: Shah Gattani Consultants; Engineer: Abhijeet Londhe; Chartered Accountant: Rishi Sekhri; Chartered Accountant: Banshi Jain and Associate; Chartered Accountant: Amit Verma& Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EVERSHINE AMAVI 303 PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EVERSHINE AMAVI 303 PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EVERSHINE AMAVI 303 PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.