Home / Browse projects / Raigarh, Maharashtra / MAULI NIWAS
MAULI NIWAS
RG-MH-15177 · RERA P52000022764 · Last updated on MahaRERA portal: 10 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MAULI NIWAS is a Others project by Pandurang Sukir Koli in Raigarh, Maharashtra, registered with MahaRERA as P52000022764 on 16 Oct 2019. Possession is promised by 31 Mar 2028. The completion date has moved by 48 months from the original filing. 2 of the 12 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameMAULI NIWAS
- TypeOthers
- Location
- Sector -24
- Pushpak New
- Wahal
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000022764
- ReraGenie IDRG-MH-15177
Builder
- NamePandurang Sukir Koli
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Oct 2019
- Promised completion31 Mar 2028
- Revised completionRevised to 31 Mar 2028 (originally 30 Mar 2024)
- Buildings1 building record
- Documents filed106 files
Current status
Figures as on 10 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MAULI NIWAS | NA | 6 | 4 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 72%.
MAULI NIWAS: 47% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 72% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 39% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 8% |
Progress on shared amenities15
As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MAULI NIWAS | NA | Rs 84.15 lakh | Rs 49.65 lakh |
| - | NA | Rs 10.10 lakh | Rs 1.01 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Atul Patel Architects |
| Architect | Atul Manubhai Patel |
| Engineer | B S Sukhtankar |
| Engineer | VIJAY KUMAR SINGH |
| Engineer | Sujal P Koli |
| Chartered Accountant | Rutuja Sajjan Narsingh |
| Chartered Accountant | BHRASADIYA PRAVINKUMAR DHARAMSHIBHAI |
| Chartered Accountant | RAHUL AMBAVIBHAI BERA |
| Partner | Role in project |
|---|---|
| Pandurang Sukir Koli | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterwe are under process of completion of project We need extension till 31-03-2028
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed106
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A (2) (1).pdf | 10 Jun 2026 |
| Withdrawal Update Form 1File: 483-24-PUSHPAK RERA (2026 MARCH).pdf | 28 May 2026 |
| Withdrawal Update Form 2File: Form2.pdf | 28 May 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf | 28 May 2026 |
| Form 5 (FY 2025-2026)File: Form 5 (1).pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 7 Mar 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 7 Mar 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 7 Mar 2026 |
| Withdrawal Update Form 1File: 483-24-PUSHPAK RERA (2025 SEPTEMBER).pdf | 20 Nov 2025 |
| Withdrawal Update Form 1File: 483-24-PUSHPAK RERA (2025 SEPTEMBER).pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: 483-Form2-(2025 September).pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: 483-Form2-(2025 September).pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q2 Aashirwad developers.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q2 Aashirwad developers.pdf | 20 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2023 JUNE).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, June 2023.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 23-24 _Q1 Aashirwad developers.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2023-24 Q1.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2023-24 Q2.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2022 SEPTEMBER).pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 23-24 _Q2 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, Sep 2023.pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, Dec 2023.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2022 DEC).pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 23-24 _Q3 Aashirwad developers.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2023-24 Q3.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2023-24 Q4.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2024 MARCH).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, March 2024.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 23-24 _Q4 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 24-25 _Q1 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2024 JUNE).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, June 2024.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2024-25 Q1.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2024-25 Q2.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2024 SEPTEMBER).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, Sep 2024.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 24-25 _Q2 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 24-25 _Q3 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2024 DECEMBER).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, Dec 2024.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2024-25 Q3.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2024-25 Q4.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2025 MARCH).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, March 2025.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 24-25 _Q4 Aashirwad developers.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2025 JUNE).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, June 2025.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 25-26 _Q1 Aashirwad developers.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2025-26 Q1.pdf | 4 Nov 2025 |
| Form 1File: 483-24-PUSHPAK RERA (2025 SEPTEMBER).pdf | 4 Nov 2025 |
| Form 2File: Form2, P-483,S-24, Sep 2025.pdf | 4 Nov 2025 |
| Form 3File: FORM 3 v2 25-26 _Q2 Aashirwad developers.pdf | 4 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 2025-26 Q2.pdf | 4 Nov 2025 |
| Form 5 (FY 2023-2024)File: Aashirwad developers-Form-5 23-24.pdf | 4 Nov 2025 |
| Form 5 (FY 2024-2025)File: Aashirwad developers-Form-5 24-25.pdf | 4 Nov 2025 |
| Layout approvalFile: ACC DRG (1).pdf | 30 Dec 2024 |
| Building plan approvalFile: ACC DRG (1).pdf | 30 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: ACC DRG (1).pdf | 30 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: ACC.pdf | 30 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: ACC DRG (1).pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_1 (6 files merged).pdf | 15 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 NEW.pdf | 10 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 10 Jun 2024 |
| CERSAI detailsFile: Cersai_Declaration.pdf | 10 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD INV.pdf | 10 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of Interest in other real estate organization.pdf | 10 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 sign.pdf | 10 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5 22-23 sign.pdf | 10 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla.pdf | 10 Jun 2024 |
| PAN CardFile: PAN.pdf | 31 May 2024 |
| Declaration in FORM BFile: Form B Pandurang (2 files merged).pdf | 31 May 2024 |
| Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf | 31 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf | 31 May 2024 |
| Details of encumbrances concerned to FinanceFile: 1 Details of encumbrances.pdf | 25 May 2024 |
| Details of encumbrances concerned to LegalFile: 1 Details of encumbrances.pdf | 25 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 106 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MAULI NIWAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pushpak New5,900+ in Raigarh
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Pandurang Sukir Koli
Pandurang Sukir Koli has 1 registration on MahaRERA, including MAULI NIWAS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if MAULI NIWAS is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MAULI NIWAS?
The registered promoter entity is Pandurang Sukir Koli, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MAULI NIWAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MAULI NIWAS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MAULI NIWAS?
The professionals named in the filing: Architect: Atul Patel Architects; Architect: Atul Manubhai Patel; Engineer: B S Sukhtankar; Engineer: VIJAY KUMAR SINGH; Engineer: Sujal P Koli; Chartered Accountant: Rutuja Sajjan Narsingh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAULI NIWAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback