Home / Browse projects / Nashik, Maharashtra / MATRUCHAYA

Registered No litigation declared Residential / Group Housing project

MATRUCHAYA

By BALDEOSINGH JAISINGH BAGGA

RG-MH-14205 · RERA P51600032066 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 50 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Aug 2030Possession promisedmoved 50 months from the original
7 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 90%
107 of 109Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 116 documents Report an error

MATRUCHAYA is a Residential / Group Housing project by BALDEOSINGH JAISINGH BAGGA in Nashik, Maharashtra, registered with MahaRERA as P51600032066 on 3 Dec 2021. Possession is promised by 15 Aug 2030. The completion date has moved by 50 months from the original filing. 2 of the 109 units on this registration are recorded sold or booked, and 7 of 33 construction stages are filed complete.

At a glance

Project

  • NameMATRUCHAYA
  • TypeResidential / Group Housing
  • Location
    • NASHIK PUNE ROAD
    • SHINDE PALSE
    • PALSE
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600032066
  • ReraGenie IDRG-MH-14205

Builder

  • NameBALDEOSINGH JAISINGH BAGGA
  • Entity typeIndividual

Key dates

this monthRegisteredDec 2021First promiseJun 2026Revised toAug 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Dec 2021
  • Promised completion15 Aug 2030
  • Revised completionRevised to 15 Aug 2030 (originally 30 Jun 2026)
  • Buildings3 building records
  • Documents filed116 files

Current status

2%2 of 109 units booked
39.9%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MATRUCHAYA 1NA66321345
MATRUCHAYA 2NA6632032
MATRUCHAYA 3NA6632032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 90%.

MATRUCHAYA 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MATRUCHAYA 28%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MATRUCHAYA 372%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes91%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes92%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes93%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes93%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes98%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
MATRUCHAYA 111
MATRUCHAYA 211
MATRUCHAYA 311

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,600 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jun 2025

Approvals and building plan

Sanctioning authorityNashik Metropolitan Region Development Authority, Nashik
Permissible FSI5554.36
Proposed, not sanctioned5,554 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMITHILA BUILDING, NASHIK ROAD
Estimated costRs 7.67 cr
Cost incurredRs 3.06 cr
Work done39.9%
BuildingWingEstimatedIncurred
MATRUCHAYA 1NARs 2.51 cr-
MATRUCHAYA 2NARs 2.33 crRs 27.41 lakh
MATRUCHAYA 3NARs 2.33 crRs 2.32 cr
-NARs 50.00 lakhRs 46.59 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMUKUL PATIL
EngineerACHAL RAJE
EngineerJayesh Banga
Chartered AccountantHSB & CO
Chartered AccountantNitesh Wankhade
Chartered AccountantGirish Lasi
PartnerRole in project
BALDEOSINGH JAISINGH BAGGA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11062621312Jun 2026 → Aug 2030

Reason as filed by the promoterthe construction is delayed due to unavoidable reasons

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Aug 2030

Documents filed116

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A (1).pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf10 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf14 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf14 Jul 2026
Withdrawal Update Form 3File: Form 3_compressed.pdf14 Jul 2026
Withdrawal Update Form 1File: Architectcert31032026.pdf15 Apr 2026
Withdrawal Update Form 2File: engg cert31032026.pdf15 Apr 2026
Withdrawal Update Form 3File: CA CERT31032026_compressed.pdf15 Apr 2026
Withdrawal Update Form 1File: form1-311225.pdf14 Jan 2026
Withdrawal Update Form 2File: form2-311225.pdf14 Jan 2026
Withdrawal Update Form 3File: form-3-311225.pdf14 Jan 2026
Withdrawal Update Form 1File: Form 1-bagga.pdf17 Nov 2025
Withdrawal Update Form 2File: Form 2-bagga.pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3-bagga-1_compressed.pdf17 Nov 2025
Withdrawal Update Form 1File: Form 1-bagga.pdf15 Oct 2025
Withdrawal Update Form 1File: Form 1-bagga.pdf15 Oct 2025
Withdrawal Update Form 2File: Form 2-bagga.pdf15 Oct 2025
Withdrawal Update Form 2File: Form 2-bagga.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3-bagga-1_compressed.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3-bagga-1_compressed.pdf15 Oct 2025
Withdrawal Update Form 1File: arch-bagga.pdf25 Jul 2025
Withdrawal Update Form 2File: form2-bagga.pdf25 Jul 2025
Withdrawal Update Form 3File: form 3-bagga june.pdf25 Jul 2025
Form 1File: Form 1-310325.pdf3 Jul 2025
Form 2File: Form 2-310325.pdf3 Jul 2025
Form 3File: Form 3-310325_compressed.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: soldunsold-310325.pdf3 Jul 2025
OthersFile: Form 2a-310325.pdf3 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-matruchaya.pdf11 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 matruchaya.pdf11 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bagga form 3-310325_compressed.pdf6 May 2025
Disclosure of sold/ booked inventoryFile: Sold unsold-310325.pdf6 May 2025
Details of encumbrances concerned to FinanceFile: No Encumbrance.pdf21 Feb 2025
CERSAI detailsFile: cersai.pdf21 Feb 2025
Details of encumbrances concerned to LegalFile: No Encumbrance.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31032024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-30062024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-3092024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31122024.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-30092023.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-311223.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-310324.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-300624.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-300924.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-311224.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3-june24_compressed.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3-sept24_compressed.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3-dec24_compressed.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-june24.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-sept24.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-dec 24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-dec23.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-dec24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-sept24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-jun24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-mar24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-sept23.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: soldunsold-jun23.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-31324_compressed.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM5-310324_compressed.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062022.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092022.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31032023.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31032023.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062023.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31122023.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-30062022.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-30092022.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31122022.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31122022.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31032023.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-30062023.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-30092023_compressed.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-31122023_compressed.pdf2 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-6-23_compressed.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31122023.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 30062022.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 30092022.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 31032023.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 30062023.pdf1 Mar 2024

How this compares with Nashik

2%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 50 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MATRUCHAYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHINDE PALSE4,100+ in Nashik

Builder: BALDEOSINGH JAISINGH BAGGA

BALDEOSINGH JAISINGH BAGGA has 1 registration on MahaRERA, including MATRUCHAYA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if MATRUCHAYA is delayed beyond 15 Aug 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MATRUCHAYA?

The registered promoter entity is BALDEOSINGH JAISINGH BAGGA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MATRUCHAYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MATRUCHAYA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MATRUCHAYA?

The professionals named in the filing: Architect: MUKUL PATIL; Engineer: ACHAL RAJE; Engineer: Jayesh Banga; Chartered Accountant: HSB & CO; Chartered Accountant: Nitesh Wankhade; Chartered Accountant: Girish Lasi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MATRUCHAYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MATRUCHAYA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MATRUCHAYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.