Home / Browse projects / Raigarh, Maharashtra / MARATHON NEXZONE TRITON -1
MARATHON NEXZONE TRITON -1
RG-MH-09656 · RERA P52000000663 · Last updated on MahaRERA portal: 18 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MARATHON NEXZONE TRITON -1 is a Residential / Group Housing project by SANVO RESORTS PVT. LTD. in Raigarh, Maharashtra, registered with MahaRERA as P52000000663 on 19 Jul 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameMARATHON NEXZONE TRITON -1
- TypeResidential / Group Housing
- Location
- JN PT ROAD
- PALASPE PHATA
- Kolkhe
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000000663
- ReraGenie IDRG-MH-09656
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Jul 2017
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed171 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MARATHON NEXZONE TRITON -1 | NA | 20 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
MARATHON NEXZONE TRITON -1: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed107
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANTOSH KUMAR PREMCHANDRA DUBEY |
| Engineer | URVESH VIRENDRA MEHTA |
| Engineer | GURRUNATH DHAVAN |
| Chartered Accountant | Apurva Shah |
| Chartered Accountant | Akshay Shah |
| Chartered Accountant | PREETI SINGH |
| Chartered Accountant | Dinesh Ganpat Pai |
| Chartered Accountant | K K Desai |
| Partner | Role in project |
|---|---|
| SANVO RESORTS PVT. LTD. | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000429459 | Sameer Prabhakar Rane | Sanvo Resorts Private Limited | 28/02/2024 |
| CC12602759 | Yadav Ombir | SANVO RESORTS PVT. LTD. | 11/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Jan 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Nov 2024
Documents filed171
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 171 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Q3_AC_Form-1_Triton-1_2024.pdf | 18 Jul 2025 |
| Form 2File: FORM 2_Engg Certificate Triton-1 Dec 2024.pdf | 18 Jul 2025 |
| Form 3File: Triton 1 Form 03 Rera Certificate Dec 2024.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DSUI Triton 1 Dec 2024.pdf | 18 Jul 2025 |
| Form 1File: Q2_AC_Form-1_Triton-1_2024.pdf | 18 Jul 2025 |
| Form 2File: signedFORM 2_Engg Certificate Triton-1 Sep 2024.pdf | 18 Jul 2025 |
| Form 3File: Rera Certificate foerm 03 Triton-1 Sep 2024.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DSUI Triton-1 Sep 2024.pdf | 18 Jul 2025 |
| Form 1File: Q1_AC_Form-1_Triton-1_2024.pdf | 18 Jul 2025 |
| Form 2File: signedFORM 2_Engg Certificate Triton-1 June 2024.pdf | 18 Jul 2025 |
| Form 3File: Form 03 Triton 1Rera Certicate June 2024.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DSUI Triton 1 June 2024.pdf | 18 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q4_AC_Form-1_Triton-1_2025.pdf | 24 Apr 2025 |
| Certificates of CA (Form 3)File: Rera Certificate Triton 1 March 25.pdf | 24 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: signedFORM 2_Engg Certificate Triton-1 Mar 2025.pdf | 24 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert Triton 1 Dec 2020.pdf | 14 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Triton 1 Jun 2021.pdf | 14 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Triton 1 Sep 2021.pdf | 14 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Triton 1 Dec 2021.pdf | 14 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 2_Engg Certificate Triton 1-DEC 21.pdf | 13 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert Triton 1 Jun 2020.pdf | 13 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg cert triton 1 Dec 2021.pdf | 13 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert Triton 1 Dec 21.pdf | 13 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Mar 2018.pdf | 13 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Dec 2017.pdf | 13 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Sep 2017.pdf | 13 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Jun 2017.pdf | 13 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Ca Cert TRITON 1 Jun 2020.pdf | 6 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Dec 2017.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Sep 2021.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Jun 2021.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Dec 2020.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Sep 2020.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Trition 1 Sep 2018.pdf | 3 Feb 2025 |
| Certificates of CA (Form 3)File: Triton 1 Form 03 Rera Certificate Dec 2024.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Engg Certificate Triton-1 Dec 2024.pdf | 27 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_AC_Form-1_Triton-1_2024.pdf | 13 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Triton 1 Dec-18.pdf | 23 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: triton1 JN 18.pdf | 23 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Engg Certificate Triton 1-Mar21.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Triton 1 Sep-18.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Triton 1 Mar 19.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Triton 1-Sep19.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Triton 1-Sep19.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Engg Certificate Triton 1-Jun21.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: triton1 JN 18.pdf | 18 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Triton 1-Sep 2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Sep 2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Mar 2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Dec 2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Triton 1 Jun 2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Triton 1 Jun 2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Triton 1 Sep 2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Triton 1 Dec 2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Triton 1 2021.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Triton 1 2021.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Triton 1 2022.pdf | 18 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: TRITION 1 Form 5.pdf | 18 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Trition-1 Arc Cer Form 1 Jun20.pdf | 7 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Trition -1 Arc Cert Form 1 Q4 19-20.pdf | 7 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Trition-1 Arc Cert Form 1 19-20.pdf | 7 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Trition -1 Arc Cert Form Q1 19-20.pdf | 7 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Trition- 1 Arc Cert Form 1 17-18.pdf | 7 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 UT Trition -1.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Triton 1 Rera Certificate June 23.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Triton-1 Rera Certi Mar 22.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Triton 1 Rera Certi Dec 21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Triton 1 Rera Certi 21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Triton 1 Rera Cert June 21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: NEXZONE TRITON-1_MAR 21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Rera Nexzone TRITON -1 Dec 20.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: TRITON-1 RERA MAR 2020.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: TRITON- 2 RERA AS ON DEC 2019.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: TRITON-1 RERA CERTIFICATE Dec 18.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: TRITON-1 RERA CERTIFICATE SEP 2018.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Rera Nexzone Triton-1 _ Sep 20.pdf | 7 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 UT Trition -1.pdf | 15 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Trition.pdf | 15 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CIDCO_NAINA_BP-00081_2020_OCC005.pdf | 15 Nov 2024 |
| Certificates of CA (Form 3)File: Rera Certificate foerm 03 Triton-1 Sep 2024.pdf | 22 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 36 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 171 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MARATHON NEXZONE TRITON -1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PALASPE PHATA5,900+ in Raigarh
Filed coordinates, straight-line distance. 139 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: SANVO RESORTS PVT. LTD.
SANVO RESORTS PVT. LTD. has 37 registrations on MahaRERA, including MARATHON NEXZONE ZODIAC -1 and MARATHON NEXZONE ZODIAC -2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that MARATHON NEXZONE TRITON -1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MARATHON NEXZONE TRITON -1 is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MARATHON NEXZONE TRITON -1?
The registered promoter entity is SANVO RESORTS PVT. LTD., a company as per the filing. Its CIN U55103MH2001PTC132675 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MARATHON NEXZONE TRITON -1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MARATHON NEXZONE TRITON -1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MARATHON NEXZONE TRITON -1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MARATHON NEXZONE TRITON -1?
The professionals named in the filing: Architect: SANTOSH KUMAR PREMCHANDRA DUBEY; Engineer: URVESH VIRENDRA MEHTA; Engineer: GURRUNATH DHAVAN; Chartered Accountant: Apurva Shah; Chartered Accountant: Akshay Shah; Chartered Accountant: PREETI SINGH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MARATHON NEXZONE TRITON -1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback