Home / Browse projects / Raigarh, Maharashtra / MARATHON NEXZONE DAFFODIL - 1

Registration lapsed No litigation declared Residential / Group Housing project

MARATHON NEXZONE DAFFODIL - 1

By SANVO RESORTS PVT. LTD.

RG-MH-15715 · RERA P52000023254 · Last updated on MahaRERA portal: 12 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 3 complaints at MahaRERA
  • Rs 245.00 crore secured on the land, in favour of Piramal Capital and Housing Finance Ltd

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 97%
4 of 141Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 185 documents Report an error

MARATHON NEXZONE DAFFODIL - 1 is a Residential / Group Housing project by SANVO RESORTS PVT. LTD. in Raigarh, Maharashtra, registered with MahaRERA as P52000023254 on 9 Dec 2019. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 137 of the 141 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMARATHON NEXZONE DAFFODIL - 1
  • TypeResidential / Group Housing
  • Location
    • J N PT ROAD
    • PALASPE PHATA
    • Kolkhe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000023254
  • ReraGenie IDRG-MH-15715

Builder

  • NameSANVO RESORTS PVT. LTD.
  • Entity typeCompany
  • CINU55103MH2001PTC132675
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsURVESH VIRENDRA MEHTA, SAMYAG MAYUR SHAH
  • Other registrations36 more →
  • Completed18 of 37
  • No longer live8 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredDec 2019PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Dec 2019
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed185 files

Current status

97%137 of 141 units booked
75.2%Work done, per cost certificate

Figures as on 12 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MARATHON NEXZONE DAFFODIL - 1NA25201410141

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 97%.

MARATHON NEXZONE DAFFODIL - 1: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)97%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered70

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area581 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPiramal Capital and Housing Finance Ltd
Secured amountRs 245.00 crore
CERSAI search filedYes
Declared on8 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI16248.5
Proposed, not sanctioned9,248 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRATAP PALACE GROUND FLR JN ROAD MULUND W MUMBAI 400080
Estimated costRs 43.87 cr
Cost incurredRs 32.98 cr
Work done75.16%
BuildingWingEstimatedIncurred
MARATHON NEXZONE DAFFODIL - 1NARs 34.23 crRs 24.98 cr
-NARs 9.65 crRs 7.99 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTOSH PREMCHAND DUBEY
EngineerURVESH VIRENDRA MEHTA
Chartered AccountantDinesh Ganpat Pai
Chartered AccountantAkshay Shah
PartnerRole in project
SANVO RESORTS PVT. LTD.-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12600771RAJESH NETAJI SHINDESANVO RESORTS PVT. LTD.10/02/2026
CC12601292Sakshi Sachin NagavkarSANVO RESORTS PVT. LTD.10/03/2026
CC12603060Sandeep Gopal ZinjadSANVO RESORTS PVT. LTD.23/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed185

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 185 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2019-2020)File: Foem 2A Daffodil 1 Mar 2020.pdf12 Feb 2026
Form 2A (FY 2021-2022)File: Form 2A Daffodil 1 Mar 2022.pdf12 Feb 2026
Form 2A (FY 2022-2023)File: Form 2A Daffodil-1 Mar 2023.pdf12 Feb 2026
Withdrawal Update Form 1File: Q3_AC_Form-1_Daffodil-1_2025.pdf27 Jan 2026
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Dec 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Daffodil 1 Form 03 Rera Certificate Dec 2025.pdf27 Jan 2026
Withdrawal Update Form 1File: Q2_AC_Form-1_Daffodil-1_2025.pdf31 Oct 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Sep 2025.pdf31 Oct 2025
Withdrawal Update Form 3File: From 3 CA Cert Daffodil 1 Sep 2025.pdf31 Oct 2025
Withdrawal Update Form 1File: Q1_AC_Form-1_Daffodil-1_2025.pdf9 Oct 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Jun 2025.pdf9 Oct 2025
Withdrawal Update Form 3File: Rera Certificate Daffodil 1 June 25.pdf9 Oct 2025
Form 1File: Q3_AC_Form-1_Daffodil-1_2019.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Dec 19.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate DAFFODIL 1 Dec 2019.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL 1 Dec 2019.pdf22 Aug 2025
Form 1File: Q4_AC_Form-1_Daffodil-1_2020.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Mar 2020.pdf22 Aug 2025
Form 3File: Form 3 Rera Certiifcate DAFFODIL 1 MAR 2020.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL 1 MAR 2020.pdf22 Aug 2025
Form 1File: Form 1 Arc Cert Daffodil 1 Jun 2020.pdf22 Aug 2025
Form 2File: Form 2 Eng Cert Daffodil 1 Jun 2020.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate DAFFODIL 1 Jun 2020.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL 1 Jun 2020.pdf22 Aug 2025
Form 1File: Q3_AC_Form-1_Daffodil-1_2020.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1-Dec 2020.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate DAFFODIL - 1 Dec 2020.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL - 1 Dec 2020.pdf22 Aug 2025
Form 1File: Form 1 Arc Cert Daffodil 1 Mar 2021.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1-Mar 21.pdf22 Aug 2025
Form 3File: RERA--DAFFODIL-1 As On Mar 21.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL-1 Mar 21.pdf22 Aug 2025
Form 1File: Q1_AC_Form-1_Daffodil-1_2021.pdf22 Aug 2025
Form 2File: Form 2 Eng Cert Daffodil 1 Jun 2021.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate Daffodil 1 June 21.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 June 21.pdf22 Aug 2025
Form 1File: Form 1 Arc Cert Daffodil 1 Sep 2021.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1-Sep 2021.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate Daffodil 1 Sep 21.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 Sep 21.pdf22 Aug 2025
Form 1File: Q1_AC_Form-1_Daffodil-1_2022.pdf22 Aug 2025
Form 2File: From 2 Engg Cert Daffodil 1 Jun 2022.pdf22 Aug 2025
Form 3File: Form 3 DAFFODIL 1 Jun 2022.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI DAFFODIL 1 Jun 2022.pdf22 Aug 2025
Form 1File: Q2_AC_Form-1_Daffodil-1_2022.pdf22 Aug 2025
Form 2File: Daffodil -1 RERA Eng Cert Sep 22.pdf22 Aug 2025
Form 3File: Daffodil-1 Form 03 Rera Certificate Sep22.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil-1 Sep22.pdf22 Aug 2025
Form 1File: Q3_AC_Form-1_Daffodil-1_2022.pdf22 Aug 2025
Form 2File: Daffodil 1 RERA Eng Cert Dec 2022.pdf22 Aug 2025
Form 3File: Form 3 Rera Certificate Daffodil 1 Dec 2022.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 Dec 2022.pdf22 Aug 2025
Form 1File: Q4_AC_Form-1_Daffodil-1_2023.pdf22 Aug 2025
Form 2File: Daffodil-1 Eng Certificate.pdf22 Aug 2025
Form 3File: Daffodil 1 Rera Certificate March 23.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 March 23.pdf22 Aug 2025
Form 1File: Q1_AC_Form-1_Daffodil-1_2023.pdf22 Aug 2025
Form 2File: Daffodil 1 RERA Eng Cert June 2023.pdf22 Aug 2025
Form 3File: Daffodil 1 Rera Certificate June 23.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 June 23.pdf22 Aug 2025
Form 1File: Q2_AC_Form-1_Daffodil-1_2023.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1-Sep 2023.pdf22 Aug 2025
Form 3File: Form 3 Marathon Nexzone Daffodil 1 Sep 23.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 Sep 23.pdf22 Aug 2025
Form 1File: Q3_AC_Form-1_Daffodil-1_2023.pdf22 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1-Dec 2023.pdf22 Aug 2025
Form 3File: Form 03 Daffodil-1 Rera Certificate Dec 2023.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil-1 Dec 2023.pdf22 Aug 2025
Form 1File: Q4_AC_Form-1_Daffodil-1_2024.pdf22 Aug 2025
Form 2File: signedFORM 2_Engg Certificate Ph II Daffodil-1 Mar 2024.pdf22 Aug 2025
Form 3File: Form 03 Daffodil-1 Rera Certificate March 2024.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil-1 March 2024.pdf22 Aug 2025
Withdrawal Update Form 1File: Q1_AC_Form-1_Daffodil-1_2025.pdf6 Aug 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Jun 2025.pdf6 Aug 2025
Withdrawal Update Form 3File: Rera Certificate Daffodil 1 June 25.pdf6 Aug 2025
Form 1File: Q3_AC_Form-1_Daffodil-1_2024.pdf17 Jul 2025
Form 2File: FORM 2_Engg Certificate Ph II Daffodil-1 Dec 2024.pdf17 Jul 2025
Form 3File: Daffodil 1 Form 03 Rera Certificate Dec 2024.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: DSUI Daffodil 1 Dec 2024.pdf17 Jul 2025
Form 1File: Q2_AC_Form-1_Daffodil-1_2024.pdf17 Jul 2025

How this compares with Raigarh

97%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARATHON NEXZONE DAFFODIL - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALASPE PHATA5,900+ in Raigarh

Builder: SANVO RESORTS PVT. LTD.

SANVO RESORTS PVT. LTD. has 37 registrations on MahaRERA, including MARATHON NEXZONE ZODIAC -1 and MARATHON NEXZONE ZODIAC -2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that MARATHON NEXZONE DAFFODIL - 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MARATHON NEXZONE DAFFODIL - 1 is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARATHON NEXZONE DAFFODIL - 1?

The registered promoter entity is SANVO RESORTS PVT. LTD., a company as per the filing. Its CIN U55103MH2001PTC132675 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARATHON NEXZONE DAFFODIL - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARATHON NEXZONE DAFFODIL - 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARATHON NEXZONE DAFFODIL - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARATHON NEXZONE DAFFODIL - 1?

The professionals named in the filing: Architect: SANTOSH PREMCHAND DUBEY; Engineer: URVESH VIRENDRA MEHTA; Chartered Accountant: Dinesh Ganpat Pai; Chartered Accountant: Akshay Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARATHON NEXZONE DAFFODIL - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARATHON NEXZONE DAFFODIL - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARATHON NEXZONE DAFFODIL - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.