Home / Browse projects / Raigarh, Maharashtra / MARATHON NEXZONE BODHI - 1

Registered No litigation declared Residential / Group Housing project

MARATHON NEXZONE BODHI - 1

By SANVO RESORTS PVT. LTD.

RG-MH-15763 · RERA P52000029858 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 245.00 crore secured on the land, in favour of Piramal Capital and Housing Finance Ltd

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 4 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 98%
4 of 206Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 160 documents Report an error

MARATHON NEXZONE BODHI - 1 is a Residential / Group Housing project by SANVO RESORTS PVT. LTD. in Raigarh, Maharashtra, registered with MahaRERA as P52000029858 on 8 Jul 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 4 months from the original filing. 202 of the 206 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameMARATHON NEXZONE BODHI - 1
  • TypeResidential / Group Housing
  • Location
    • J N PT ROAD
    • PALASPE PHATA
    • Kolkhe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000029858
  • ReraGenie IDRG-MH-15763

Builder

  • NameSANVO RESORTS PVT. LTD.
  • Entity typeCompany
  • CINU55103MH2001PTC132675
  • DirectorsSAMYAG MAYUR SHAH, URVESH VIRENDRA MEHTA
  • Other registrations36 more →
  • Completed18 of 37
  • No longer live8 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2021First promiseJun 2026Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jul 2021
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed160 files

Current status

98%202 of 206 units booked
70.8%Work done, per cost certificate

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MARATHON NEXZONE BODHI - 1NA28202060206

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

MARATHON NEXZONE BODHI - 1: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)97%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.89%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered35

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area743 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPiramal Capital and Housing Finance Ltd
Secured amountRs 245.00 crore
CERSAI search filedYes
Declared on16 Jun 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI14500.0
Proposed, not sanctioned9,500 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5 6 7 JALARAM ASHISH CO OP HSG SOCIETY DEVIDAYAL ROAD MULUND WEST MUMBAI 400080
Estimated costRs 71.60 cr
Cost incurredRs 50.66 cr
Work done70.75%
BuildingWingEstimatedIncurred
MARATHON NEXZONE BODHI - 1NARs 56.66 crRs 38.14 cr
-NARs 14.94 crRs 12.53 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTOSH KUMAR PREMCHANDRA DUBEY
EngineerURVESH VIRENDRA MEHTA
EngineerGURRUNATH DHAVAN
Chartered AccountantDinesh Ganpat Pai
Chartered AccountantAkshay Shah
Chartered AccountantApurva Shah
PartnerRole in project
SANVO RESORTS PVT. LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30062621637Jun 2026 → Oct 2026

Reason as filed by the promoterIn connection with our application filed under Form ‘E’ for the extension of registration of the project “MARATHON NEXZONE BODHI - 1” for a period of 4 Months ending on 31/10/2026, we hereby submit this Explanatory Note detailing the unavoidable reasons, force majeure scenarios, and reasonable grounds that led to the delay in the development works

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000591603ALTAF CHIKTESANVO RESORTS PVT LTD20/08/2024
CC12500571Srinivas Sundaram IyerSANVO RESORTS PVT. LTD.19/02/2025
CC12602992SANVO RESORTS PVT. LTD.Yogesh Chandra Srivastava20/05/2026
CC12603025SANVO RESORTS PVT. LTD.Sunny Suresh Jadhav22/05/2026
CC12603027SANVO RESORTS PVT. LTD.Suryakant Vasant Kate22/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed160

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q1_AC_Form-1_Bodhi-1_2026.pdf14 Jul 2026
Withdrawal Update Form 1File: Q1_AC_Form-1_Bodhi-1_2026.pdf14 Jul 2026
Withdrawal Update Form 2File: signed Bodhi 1 Form2 June 2026 updated.pdf14 Jul 2026
Withdrawal Update Form 2File: signed Bodhi 1 Form2 June 2026 updated.pdf14 Jul 2026
Withdrawal Update Form 3File: Rera Certificate Bodhi 1 June 26.pdf14 Jul 2026
Withdrawal Update Form 3File: Rera Certificate Bodhi 1 June 26.pdf14 Jul 2026
Withdrawal Update Form 1File: Q4_AC_Form-1_Bodhi-1_2026.pdf28 Apr 2026
Withdrawal Update Form 2File: signedForm 2 Engg Cert Bodhi 1 Mar 2026.pdf28 Apr 2026
Withdrawal Update Form 3File: RERA Certificate for March-2026- Marathon Nexzone Bodhi-1.pdf28 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Bodhi 1 Mar 2026.pdf21 Apr 2026
Form 1File: Form 1 Arc Cert Bodhi 1 Mar 2022.pdf9 Mar 2026
Form 2File: Form 2 Engg Cert Bodhi 1 Mar 2022.pdf9 Mar 2026
Form 3File: Nexzone Bodhi-1 Rera Certi As on Mar 22.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi-1 Mar 22.pdf9 Mar 2026
Withdrawal Update Form 1File: Q3_AC_Form-1_Bodhi-1_2025.pdf27 Jan 2026
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1 Dec 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Bodhi 1 Form 03 Rera Certificate Dec 2025.pdf27 Jan 2026
Withdrawal Update Form 1File: Q2_AC_Form-1_Bodhi-1_2025.pdf28 Oct 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1 Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: From 3 CA Cert Bodhi 1 Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 1File: Q1_AC_Form-1_Bodhi-1_2025.pdf8 Oct 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1 Jun 2025.pdf8 Oct 2025
Withdrawal Update Form 3File: Marathon Nexzone Bodhi I Rera Certificate June 25.pdf8 Oct 2025
Form 2A (FY 2021-2022)File: Form 2A Bodhi 1 Mar 2022.pdf12 Aug 2025
Form 2A (FY 2022-2023)File: Form 2A Bodhi-1.pdf12 Aug 2025
Form 2A (FY 2023-2024)File: FORM-2A BODHI 1_ MAR-2024.pdf12 Aug 2025
Form 1File: Q1_AC_Form-1_Bodhi-1_2022.pdf11 Aug 2025
Form 2File: Bodhi-1_jn-22.pdf11 Aug 2025
Form 3File: BODHI 2 Rera Certificate June 2022.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI BODHI 2 June 2022.pdf11 Aug 2025
Form 1File: Q2_AC_Form-1_Bodhi-1_2022.pdf11 Aug 2025
Form 2File: Bodhi 1RERA Eng Cert Sep 22.pdf11 Aug 2025
Form 3File: Bodhi-1 Form 03 Rera Certificate Sep22.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 Sep22.pdf11 Aug 2025
Form 1File: Q2_AC_Form-1_Bodhi-1_2022.pdf11 Aug 2025
Form 2File: Bodhi 1RERA Eng Cert Sep 22.pdf11 Aug 2025
Form 3File: Bodhi-1 Form 03 Rera Certificate Sep22.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 Sep22.pdf11 Aug 2025
Form 1File: Q2_AC_Form-1_Bodhi-1_2022.pdf11 Aug 2025
Form 2File: Bodhi 1RERA Eng Cert Sep 22.pdf11 Aug 2025
Form 3File: Bodhi-1 Form 03 Rera Certificate Sep22.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 Sep22.pdf11 Aug 2025
Form 1File: Q3_AC_Form-1_Bodhi-1_2022.pdf11 Aug 2025
Form 2File: Bodhi 1 RERA Eng Cert Dec 2022.pdf11 Aug 2025
Form 3File: Form 3 Rera Certificate Bodhi 1 Dec 2022.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 Dec 2022.pdf11 Aug 2025
Form 1File: Q4_AC_Form-1_Bodhi-1_2023.pdf11 Aug 2025
Form 2File: Bodhi-1 Eng Certificate.pdf11 Aug 2025
Form 3File: Bodhi 1 Rera certificate March 23.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 March 23.pdf11 Aug 2025
Form 1File: Q1_AC_Form-1_Bodhi-1_2023.pdf11 Aug 2025
Form 2File: Bodhi 1RERA Eng Cert June 2023.pdf11 Aug 2025
Form 3File: Bodhi 1 Rera Certificate June 23.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 June 23.pdf11 Aug 2025
Form 1File: Q1_AC_Form-1_Bodhi-1_2023.pdf11 Aug 2025
Form 2File: Bodhi 1RERA Eng Cert June 2023.pdf11 Aug 2025
Form 3File: Form 3 Marathon Nexzone Bodhi 1 Sep 23.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi 1 Sep 23.pdf11 Aug 2025
Form 1File: Q3_AC_Form-1_Bodhi-1_2023.pdf11 Aug 2025
Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1-Dec 2023.pdf11 Aug 2025
Form 3File: Form 03 Bodhi-1 Rera Certificate Dec 2023.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi-1 Dec 2023.pdf11 Aug 2025
Form 1File: Q4_AC_Form-1_Bodhi-1_2024.pdf11 Aug 2025
Form 2File: signedFORM 2_Engg Certificate Ph II Bodhi-1 Mar-2024.pdf11 Aug 2025
Form 3File: Form 03 Bodhi-1 Rera Certificate March 2024.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi-1 March 2024.pdf11 Aug 2025
Withdrawal Update Form 1File: Q1_AC_Form-1_Bodhi-1_2025.pdf1 Aug 2025
Withdrawal Update Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1 Jun 2025.pdf1 Aug 2025
Withdrawal Update Form 3File: Marathon Nexzone Bodhi I Rera Certificate June 25.pdf1 Aug 2025
Form 1File: Q1_AC_Form-1_Bodhi-1_2024.pdf16 Jul 2025
Form 2File: signedFORM 2_Engg Certificate Ph II Bodhi-1 June 2024.pdf16 Jul 2025
Form 3File: Form 03 Bhodi-1 Rera Certificate June 2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bhodi-1 June 2024.pdf16 Jul 2025
Form 1File: Q2_AC_Form-1_Bodhi-1_2024.pdf16 Jul 2025
Form 2File: signedFORM 2_Engg Certificate Ph II Bodhi-1 Sep 2024.pdf16 Jul 2025
Form 3File: Rera Certificate form 03 Bodhi-1 Sep 2024.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: DSUI Bodhi-1 Sep 2024.pdf16 Jul 2025
Form 1File: Q3_AC_Form-1_Bodhi-1_2024.pdf16 Jul 2025
Form 2File: FORM 2_Engg Certificate Ph II Bodhi-1 Dec 2024.pdf16 Jul 2025
Form 3File: Bodhi 1 Form 03 Rera Certificate Dec 2024.pdf16 Jul 2025

How this compares with Raigarh

98%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 4 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARATHON NEXZONE BODHI - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALASPE PHATA5,900+ in Raigarh

Builder: SANVO RESORTS PVT. LTD.

SANVO RESORTS PVT. LTD. has 37 registrations on MahaRERA, including MARATHON NEXZONE ZODIAC -1 and MARATHON NEXZONE ZODIAC -2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if MARATHON NEXZONE BODHI - 1 is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARATHON NEXZONE BODHI - 1?

The registered promoter entity is SANVO RESORTS PVT. LTD., a company as per the filing. Its CIN U55103MH2001PTC132675 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARATHON NEXZONE BODHI - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARATHON NEXZONE BODHI - 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARATHON NEXZONE BODHI - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARATHON NEXZONE BODHI - 1?

The professionals named in the filing: Architect: SANTOSH KUMAR PREMCHANDRA DUBEY; Engineer: URVESH VIRENDRA MEHTA; Engineer: GURRUNATH DHAVAN; Chartered Accountant: Dinesh Ganpat Pai; Chartered Accountant: Akshay Shah; Chartered Accountant: Apurva Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARATHON NEXZONE BODHI - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARATHON NEXZONE BODHI - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARATHON NEXZONE BODHI - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.