Home / Browse projects / Palghar, Maharashtra / MARATHE COMPLEX

Registered No litigation declared Residential / Group Housing project

MARATHE COMPLEX

By GPRS REALTY

RG-MH-27758 · RERA P99000024943 · Last updated on MahaRERA portal: 6 May 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
86 of 154Construction stages doneacross 14 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
42 of 64Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

MARATHE COMPLEX is a Residential / Group Housing project by GPRS REALTY in Palghar, Maharashtra, registered with MahaRERA as P99000024943 on 12 Mar 2020. Possession is promised by 30 Dec 2026. 22 of the 64 units on this registration are recorded sold or booked, and 86 of 154 construction stages are filed complete.

At a glance

Project

  • NameMARATHE COMPLEX
  • TypeResidential / Group Housing
  • Location
    • NEAR SHRI NIWAS PARK BOISAR
    • PALGHAR
    • Man
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000024943
  • ReraGenie IDRG-MH-27758

Builder

  • NameGPRS REALTY
  • Entity typePartnership
  • PartnersRAKESH RAJENDRA PRASAD KHETAN, PRITI RAKESH KHETAN
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredMar 2020PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Mar 2020
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings14 building records
  • Documents filed115 files

Current status

34%22 of 64 units booked

Figures as on 6 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA6610010
BUILDING NO 2NA6628028
BUILIDNG NO 3NA44044
BUILDING NO 4NA44044
BUILDING NO 5NA44044
BUILDING NO 6NA44066
BUILDING NO 7ANA55011
BUILDING NO 7BNA55011
BUILDING NO 7CNA55011
BUILDING NO 7DNA55011
BUILDING NO 7ENA55011
BUILDING NO 7FNA55011
BUILDING NO 7GNA55011
BUILDING NO 7HNA55011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building14

As on 6 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

86 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

BUILDING NO 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 287%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILIDNG NO 354%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
BUILDING NO 479%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 7A86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7B86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7C86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7D86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7E86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7F86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7G87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING NO 7H87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 6 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered22
Open Space1
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 1819
BUILDING NO 214014

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,460 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Sep 2025
LandownerVillageDistrict
SHOBHA SANTOSH MARATHEBoisarPalghar
SANTOSH PANDURANG MARATHEBoisarPalghar

Approvals and building plan

Sanctioning authorityPalghar District Planning Authority
Permissible FSI6852.6
Proposed, not sanctioned6,852 sq m
Buildings approved14
Buildings sanctioned14

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch248 ANDHERI KURLA ROAD JB NAGAR ANHDERI EAST MUMBAI 40059

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectOAA ODYSSEY ARCHITECTS & ASSOCIATES
EngineerAWHAD CONSULTING ENGINEERS
Chartered AccountantD P SHEJWAL AND ASSOCIATES
PartnerRole in project
GPRS REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 May 2025

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - converted.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf6 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf15 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GPRS REALTY 23-24 - converted.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30-09-24 - converted.pdf22 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED (2).pdf20 Aug 2024
Building plan approvalFile: PLAN 1.PDF27 May 2024
Building plan approvalFile: PLAN 2.PDF27 May 2024
Building plan approvalFile: PLAN 3.PDF27 May 2024
Building plan approvalFile: PLAN 4.PDF27 May 2024
Building plan approvalFile: PLAN 5.PDF27 May 2024
Building plan approvalFile: PLAN 6.PDF27 May 2024
Building plan approvalFile: PLAN 7.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 4.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 5.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 6.PDF27 May 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 7.PDF27 May 2024
Commencement Certificates / NA Order for plotted developmentFile: GPRS REWISE CC - converted.pdf27 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 signed - converted.pdf27 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SIGNED.pdf27 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed.pdf27 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGN.pdf15 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf1 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GPRS FORM 3.pdf22 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-09-2023.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-09-2023.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-06-2023.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 as on 30-06-2023_1 (6 files merged).pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf13 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3.pdf13 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf8 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20230123 Khetan RERA Completion - 52.pdf7 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE FOR MARATHE COMPLEX 31-12-2022.pdf7 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: site superviser certificate.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archt Cert.pdf25 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE FOR MARATHE COMPLEX 30-09-2022.pdf25 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT 30062022.pdf6 Aug 2022
Declaration about Commencement CertificateFile: CC DECLARATION.pdf25 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECK CERTIFICATE.pdf25 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SITE ENGINEER CERTIFICATE.pdf25 Jul 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf25 Jul 2022
Declaration about Commencement CertificateFile: CC DECLARATION 01.pdf2 May 2022
Declaration about Commencement CertificateFile: CC DECLARATION 02.pdf2 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH MARCH.pdf2 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DEC.pdf2 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG DEC.pdf2 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG MARCH.pdf2 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A DEC.pdf2 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A MARCH.pdf2 May 2022
CERSAI detailsFile: CERSAI REPORT.pdf2 May 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DEC.pdf2 May 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD MARCH.pdf2 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC.PDF2 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA MARCH.PDF2 May 2022
Declaration about Commencement CertificateFile: DECLARATION OF CC.pdf31 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A SITE ENGINEER CERTIFICATE.pdf31 Jan 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf31 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf21 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf21 Oct 2021

How this compares with Palghar

34%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARATHE COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR3,200+ in Palghar

2 kmMARATHE COMPLEXCompleted 3Lapsed / revoked 13Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: GPRS REALTY

GPRS REALTY has 2 registrations on MahaRERA, including IMPERIA HOMES and MARATHE COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if MARATHE COMPLEX is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARATHE COMPLEX?

The registered promoter entity is GPRS REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARATHE COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MARATHE COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARATHE COMPLEX?

The professionals named in the filing: Architect: OAA ODYSSEY ARCHITECTS & ASSOCIATES; Engineer: AWHAD CONSULTING ENGINEERS; Chartered Accountant: D P SHEJWAL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARATHE COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARATHE COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARATHE COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.