Home / Browse projects / Nashik, Maharashtra / MANOKAMNESHWAR PARK

Registered No litigation declared Residential / Group Housing project

MANOKAMNESHWAR PARK

By AARAMBH REALTY

RG-MH-41804 · RERA P51600055287 · Last updated on MahaRERA portal: 1 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
44 of 198Construction stages doneacross 18 buildings; furthest along: Internal walls, 90%
27 of 54Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

MANOKAMNESHWAR PARK is a Residential / Group Housing project by AARAMBH REALTY in Nashik, Maharashtra, registered with MahaRERA as P51600055287 on 14 Mar 2024. Possession is promised by 31 Dec 2027. 27 of the 54 units on this registration are recorded sold or booked, and 44 of 198 construction stages are filed complete.

At a glance

Project

  • NameMANOKAMNESHWAR PARK
  • TypeResidential / Group Housing
  • Location
    • VIHITGAON
    • Deolaligaon
    • Nashik
    • 422101
  • Pincode422101
  • RERA no.P51600055287
  • ReraGenie IDRG-MH-41804

Builder

  • NameAARAMBH REALTY
  • Entity typePartnership
  • PartnersCHETAN SURESH KADBHANE, BHIMA GANGADHAR MHASKE, ABHIJIT VISHNU GODHADE, AKSHAY BALASAHEB MHASKE
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Mar 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings18 building records
  • Documents filed64 files

Current status

50%27 of 54 units booked

Figures as on 1 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSE NO 1NA33303
ROW HOUSE NO 2NA30303
ROW HOUSE NO 3NA30303
ROW HOUSE NO 6NA30303
ROW HOUSE NO 4NA30303
ROW HOUSE NO 5NA30303
ROW HOUSE NO 7NA30303
ROW HOUSE NO 8NA30303
ROW HOUSE NO 9NA30303
ROW HOUSE NO 10NA30303
ROW HOUSE NO 11NA30303
ROW HOUSE NO 12NA30303
ROW HOUSE NO 13NA30303
ROW HOUSE NO 14NA30303
ROW HOUSE NO 15NA30303
ROW HOUSE NO 16NA30303
ROW HOUSE NO 17NA30303
ROW HOUSE NO 18NA30303

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building18

As on 1 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

44 of 198 construction stages are filed complete across 18 buildings. The stage furthest along is Internal walls, at 90%.

ROW HOUSE NO 152%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 252%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 352%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 654%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 452%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 554%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 754%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 854%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 99%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 109%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 119%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 129%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 130%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 160%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 170%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE NO 180%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered17
Open Space36
BuildingClosed/CoveredOpen SpaceTotal
ROW HOUSE NO 1022
ROW HOUSE NO 2123
ROW HOUSE NO 3123
ROW HOUSE NO 6123
ROW HOUSE NO 4123
ROW HOUSE NO 5123
ROW HOUSE NO 7123
ROW HOUSE NO 8123
ROW HOUSE NO 9123
ROW HOUSE NO 10123
ROW HOUSE NO 11123
ROW HOUSE NO 12123
ROW HOUSE NO 13123
ROW HOUSE NO 14123
ROW HOUSE NO 15123
ROW HOUSE NO 16123
ROW HOUSE NO 17123
ROW HOUSE NO 18123

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
FAKIRA SANTU KOTHULEDeolaligaonNashik
SUSHILA SHANTARAM VAYKARNashik (M Corp.)Nashik
BHAGIRATHIBAI BAJIRAO KOTHULEDeolaligaonNashik
SAMADHAN BAJIRAO KOTHULEDeolaligaonNashik
KAVITA SUBHASH KASBENashik (M Corp.)Nashik
CHANDRAKALA PANDU GODSEDeolaligaonNashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI1881.82
Proposed, not sanctioned1,882 sq m
Buildings approved18
Buildings sanctioned18

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDEOLALI CAMP BRANCH, HOWSON ROAD, DEOLALI CAMP, NASHIK - 422401

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEJAS MORE
EngineerGANESH KAWALE
Chartered AccountantBHUSHAN GOSAR
Chartered AccountantChetan Anand & Co
Chartered AccountantBhavana Loya
PartnerRole in project
AARAMBH REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form-1 architects certificate.pdf1 Apr 2026
Form 2File: Form 2 Engineers certificate Q1 on Enginers LH.pdf1 Apr 2026
Form 3File: Aarambh Realty(Q-3)_-Final Form 3.pdf1 Apr 2026
Disclosure of Sold and Booked InventoryFile: sold unsold final.pdf1 Apr 2026
Form 1File: Form-1.pdf28 Nov 2025
Form 2File: Form2 Q2.pdf28 Nov 2025
Form 3File: Form3 Q2.pdf28 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold&Unsold Letterhead - Copy.pdf28 Nov 2025
Form 1File: Form 1.pdf7 Oct 2025
Form 2File: Rera structural engineer certificate 29-09-25.pdf7 Oct 2025
Form 3File: Form 3 final.pdf7 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold unit 29-09-25.pdf7 Oct 2025
Form 5 (FY 2024-2025)File: Form 5.pdf29 Sep 2025
Form 1File: Form 1 Q3.PDF13 Jun 2025
Form 2File: Q3 Form 2 Engineers certificate.pdf13 Jun 2025
Form 3File: Form 3 Q3 Final.pdf13 Jun 2025
Disclosure of Sold and Booked InventoryFile: Q3 sold unsold.pdf13 Jun 2025
Self-declaration of Quarterly ProgressFile: Q3 Self declaration.pdf13 Jun 2025
Form 1File: Form 1 Q4.PDF13 Jun 2025
Form 2File: Q4 Form 2 -Engineers certificate 11062025_250611_191848.pdf13 Jun 2025
Form 3File: Form 3 Q4.pdf13 Jun 2025
Disclosure of Sold and Booked InventoryFile: Q4 Sold Unsold.pdf13 Jun 2025
Self-declaration of Quarterly ProgressFile: Q4 Self Declaration.pdf13 Jun 2025
Form 1File: Form 1 Q2.pdf13 Jun 2025
Form 2File: Form 2 Q2.pdf13 Jun 2025
Form 3File: 4 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf13 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf13 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 24.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 24.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 24.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 24.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 24.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 24.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf24 Dec 2024
Other - LegalFile: Annexure Rera .pdf28 Feb 2024
Layout approvalFile: Building Plan.pdf14 Feb 2024
Layout approvalFile: Aarambh muncipal drawing.pdf14 Feb 2024
Building plan approvalFile: Building Plan.pdf14 Feb 2024
Building plan approvalFile: Aarambh muncipal drawing.pdf14 Feb 2024
PAN CardFile: AARAMBH PAN.pdf14 Feb 2024
Copy of Layout Approval (in case of layout)File: Building Plan.pdf14 Feb 2024
Copy of Layout Approval (in case of layout)File: Aarambh muncipal drawing.pdf14 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf14 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Aarambh muncipal drawing.pdf14 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Comencement.pdf14 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Aarambh.pdf14 Feb 2024
Copy of the legal title reportFile: Title search Aarambh.pdf12 Feb 2024
Details of encumbrances concerned to FinanceFile: Declaration of encumbrance 2.pdf12 Feb 2024
Details of encumbrances concerned to LegalFile: Declaration of encumbrance 2.pdf12 Feb 2024
Declaration about Commencement CertificateFile: Commencement Aarambh rera.pdf12 Feb 2024
Declaration in FORM BFile: Form B Chetan.pdf12 Feb 2024
CERSAI detailsFile: Cresai 2.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Abhijjet Godhade.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure AKSHAY MHASKE.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure BHIMA MHASKE.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Chetan kadbhane.pdf12 Feb 2024
Proforma of Allotment letterFile: Proforma allotment letter_Aarambh Realty.pdf12 Feb 2024
Proforma of Agreement for saleFile: New Rera Agreement For Aarambh realty 001.pdf12 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Bank Aarambh.pdf12 Feb 2024
Deviation Report with respect to Allotment letterFile: No Deviation Aarambh Allotment.pdf12 Feb 2024
Deviation Report with respect to model copy of AgreementFile: No deviation Agreement to sale.pdf12 Feb 2024

How this compares with Nashik

50%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANOKAMNESHWAR PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIHITGAON4,100+ in Nashik

Builder: AARAMBH REALTY

AARAMBH REALTY has 2 registrations on MahaRERA, including MANOKAMNESHWAR PARK and AMBE ASHIRWAD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if MANOKAMNESHWAR PARK is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANOKAMNESHWAR PARK?

The registered promoter entity is AARAMBH REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANOKAMNESHWAR PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANOKAMNESHWAR PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANOKAMNESHWAR PARK?

The professionals named in the filing: Architect: TEJAS MORE; Engineer: GANESH KAWALE; Chartered Accountant: BHUSHAN GOSAR; Chartered Accountant: Chetan Anand & Co; Chartered Accountant: Bhavana Loya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANOKAMNESHWAR PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANOKAMNESHWAR PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANOKAMNESHWAR PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.