ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / MANGALMURTI RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

MANGALMURTI RESIDENCY

By VICKY KASHINATH BHOIR

RG-MH-29245 · RERA P52000028029 · Last updated on MahaRERA portal: 20 Mar 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 50%
0Complaints at MahaRERAon this registration
Jump to the 18 documents Report an error

MANGALMURTI RESIDENCY is a Residential / Group Housing project by VICKY KASHINATH BHOIR in Raigarh, Maharashtra, registered with MahaRERA as P52000028029 on 26 Jan 2021. Possession was promised by 30 Jun 2023 and is now 40 months past that date.

At a glance

Project

  • NameMANGALMURTI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • SECTOR 19B
    • ULWE
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000028029
  • ReraGenie IDRG-MH-29245

Builder

  • NameVICKY KASHINATH BHOIR
  • Entity typeIndividual

Key dates

40 months past promisethis monthRegisteredJan 2021PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jan 2021
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed18 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MANGALMURTI RESIDENCYNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

MANGALMURTI RESIDENCY: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area200 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI299.61
Proposed, not sanctioned300 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHUBHAM PALACE, SECTOR 15 ,KOPERKHAIRANE ,NAVI MUMBAI-400709

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFASCINATE ARCHITECTS
EngineerPRAPTI ASSOCIATE CONSULTING ENGINEER
Chartered AccountantAVINASH SINYAL
PartnerRole in project
VICKY KASHINATH BHOIR-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed18

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Certificate_23_.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mangalmurti Dev RERA Certificate.pdf14 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Any Scanner_04_13_2023(1) (1).pdf14 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate_21_.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate_22_.pdf14 Apr 2023
Layout approvalFile: VICKY LAYOUT.pdf18 Jan 2021
Building plan approvalFile: VICKY LAYOUT.pdf18 Jan 2021
PAN CardFile: VIcky PAN.pdf18 Jan 2021
Copy of the legal title reportFile: vicky Title.pdf18 Jan 2021
Details of encumbrancesFile: VICKY ENCUMBRANCE.pdf18 Jan 2021
Copy of Layout Approval (in case of layout)File: VICKY LAYOUT.pdf18 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: VICKY LAYOUT.pdf18 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: VICKY CC.pdf18 Jan 2021
Declaration in FORM BFile: FORM B VICKY.pdf18 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Vicky-compressed.pdf18 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA VICKY-compressed.pdf18 Jan 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE VICKY PLOT NO A19 ULWE.pdf18 Jan 2021

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANGALMURTI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE5,900+ in Raigarh

2 kmMANGALMURTI RESIDENCYCompleted 133Lapsed / revoked 40Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 302 registered projects within 2 km.

Builder: VICKY KASHINATH BHOIR

VICKY KASHINATH BHOIR has 1 registration on MahaRERA, including MANGALMURTI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that MANGALMURTI RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MANGALMURTI RESIDENCY is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANGALMURTI RESIDENCY?

The registered promoter entity is VICKY KASHINATH BHOIR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANGALMURTI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANGALMURTI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANGALMURTI RESIDENCY?

The professionals named in the filing: Architect: FASCINATE ARCHITECTS; Engineer: PRAPTI ASSOCIATE CONSULTING ENGINEER; Chartered Accountant: AVINASH SINYAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANGALMURTI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANGALMURTI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANGALMURTI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.