ReraGenieLog inGet a buyer report

Home / Browse projects / Jalgaon, Maharashtra / MANGALAM PARK

Registered No litigation declared Residential / Group Housing project

MANGALAM PARK

By MANGALAM INFRA

RG-MH-13394 · RERA P49900025679 · Last updated on MahaRERA portal: 21 Jan 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalgaon registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedmoved 60 months from the original
72 of 264Construction stages doneacross 24 buildings; furthest along: Slabs of Super Structure, 89%
0Complaints at MahaRERAon this registration
Jump to the 168 documents Report an error

MANGALAM PARK is a Residential / Group Housing project by MANGALAM INFRA in Jalgaon, Maharashtra, registered with MahaRERA as P49900025679 on 1 Jul 2020. Possession is promised by 29 Sep 2028. The completion date has moved by 60 months from the original filing.

At a glance

Project

  • NameMANGALAM PARK
  • TypeResidential / Group Housing
  • Location
    • PACHORA
    • Pachora (M Cl)
    • Jalgaon
    • 424201
  • Pincode424201
  • RERA no.P49900025679
  • ReraGenie IDRG-MH-13394

Builder

  • NameMANGALAM INFRA
  • Entity typePartnership
  • PartnersVASIHALI RITESHKUMAR LALWANI, SANGITA PRAMODKUMAR LALWANI
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2020First promiseSep 2023Revised toSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Jul 2020
  • Promised completion29 Sep 2028
  • Revised completionRevised to 29 Sep 2028 (originally 30 Sep 2023)
  • Buildings24 building records
  • Documents filed168 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 01 TYPE A 1 RKNA10000
BUILDING NO 02 TYPE A 1 RKNA10000
BUILDING NO 03 TYPE A 1 RKNA10000
BUILDING NO 04 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 05 1 BHK DUPLEXNA20000
BUILDING NO 06 TYPE B DUPLEXNA20000
BUILDING NO 07 1 BHK DUPLEXNA30000
BUILDING NO 08 1 BHK DUPLEXNA20000
BUILDING NO 09 1 BHK DUPLEXNA20000
BUILDING NO 10 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 11 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 12 TYPE B 1 BHK DUPEXNA20000
BUILDING NO 13 TYPE B 1 BHK DUPEXNA20000
BUILDING NO 14 TYPE B 1 BHK DUPELXNA20000
BUILDING NO 15 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 16 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 17 TYPE B 1 BHKL DUPLEXNA20000
BUILDING NO 18 TYPE B 1 BHK DUPLEXNA40000
BUILDING NO 19 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 20 TYPE B 1 BHK DUPLEXNA20000
BUILIDING NO 21 TYPE 2 1 BHK DUPLEXNA20000
BUILDING NO 22 TYPE B 1 BHK DUPLEXNA20000
BUILDING NO 23 TYPE C 1 BHKNA20000
BUILDING NO 24 TYPE C 1 BHKNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 21 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 24 buildings; the table lists the first 20.

72 of 264 construction stages are filed complete across 24 buildings. The stage furthest along is Slabs of Super Structure, at 89%.

BUILDING NO 01 TYPE A 1 RK53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 02 TYPE A 1 RK53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 03 TYPE A 1 RK53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 04 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 05 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 06 TYPE B DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 07 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 08 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 09 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 10 TYPE B 1 BHK DUPLEX51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 11 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 12 TYPE B 1 BHK DUPEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 13 TYPE B 1 BHK DUPEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 14 TYPE B 1 BHK DUPELX51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 15 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 16 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 17 TYPE B 1 BHKL DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 18 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 19 TYPE B 1 BHK DUPLEX51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 20 TYPE B 1 BHK DUPLEX53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes28%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes12%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed344

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots344
Open Space344
BuildingOpen SpaceTotal
BUILDING NO 01 TYPE A 1 RK1616
BUILDING NO 02 TYPE A 1 RK1616
BUILDING NO 03 TYPE A 1 RK1616
BUILDING NO 04 TYPE B 1 BHK DUPLEX88
BUILDING NO 05 1 BHK DUPLEX66
BUILDING NO 06 TYPE B DUPLEX88
BUILDING NO 07 1 BHK DUPLEX1414
BUILDING NO 08 1 BHK DUPLEX1515
BUILDING NO 09 1 BHK DUPLEX1616
BUILDING NO 10 TYPE B 1 BHK DUPLEX1111
BUILDING NO 11 TYPE B 1 BHK DUPLEX1616
BUILDING NO 12 TYPE B 1 BHK DUPEX1616
BUILDING NO 13 TYPE B 1 BHK DUPEX1212
BUILDING NO 14 TYPE B 1 BHK DUPELX1616
BUILDING NO 15 TYPE B 1 BHK DUPLEX1616
BUILDING NO 16 TYPE B 1 BHK DUPLEX1616
BUILDING NO 17 TYPE B 1 BHKL DUPLEX1616
BUILDING NO 18 TYPE B 1 BHK DUPLEX1616
BUILDING NO 19 TYPE B 1 BHK DUPLEX1616
BUILDING NO 20 TYPE B 1 BHK DUPLEX1616
BUILIDING NO 21 TYPE 2 1 BHK DUPLEX1414
BUILDING NO 22 TYPE B 1 BHK DUPLEX1616
BUILDING NO 23 TYPE C 1 BHK1616
BUILDING NO 24 TYPE C 1 BHK1616

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area26,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jan 2026

Approvals and building plan

Sanctioning authorityMaharashtra Housing and area development authority
Permissible FSI12445.12
Proposed, not sanctioned12,445 sq m
Buildings approved24
Buildings sanctioned24

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPAHORA

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUJJWAL SATISH BHOLE SATISH BHOLE
EngineerSANDEEP RATANLAL TOSHNIWAL RATANLAL TOSHNIWAL
EngineerBHARATSINGH BHIKAJI VAGHELA
Chartered AccountantRAHUL PRAKASH PATIL
Chartered AccountantSONAWANE MOR AND COMPANY
Chartered AccountantRAHUL KISHOR DAYAMA
Chartered AccountantSANDIP P VYAS AND COMPANY
PartnerRole in project
MANGALAM INFRA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT49900017299Sep 2023 → Sep 2024

Reason as filed by the promoterSeeking 1 Year Rera Extension

EXT49900024775Sep 2023 → Sep 2028

Reason as filed by the promoterWe are expected to complete the project within 3-4 years from its sanctioned but due to seceral factors such as covid etc. such project is delay, we are expected to complete as early as posssible sir as per the query raised we have submiited this docs, further if any doubt plz contact us or provide us specific contact number, we are trying to reached you by mail or by calliing but no reply from the authorities... sir plz update Thanks for valuable co-operation

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 29 Sep 2028

Documents filed168

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 168 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf21 Jan 2026
Form 2File: FORM 2.pdf21 Jan 2026
Form 3File: MANGALAM INFRA FORM 3 WITH DECLARATION.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY DISCLOSURE.pdf21 Jan 2026
Form 2A (FY 2024-2025)File: Form 2 A FY 2024-25 05.pdf21 Jan 2026
Form 2A (FY 2020-2021)File: FORM 2A FY 20-21.pdf21 Jan 2026
Form 2A (FY 2021-2022)File: FORM 2A FY 21-22.pdf21 Jan 2026
Form 2A (FY 2022-2023)File: FORM 2A FY 22-23.pdf21 Jan 2026
Form 2A (FY 2023-2024)File: FORM 2A FY 23-24.pdf21 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: QPR DECL SOLD INVENTORY.pdf20 Jan 2026
Form 1File: QPR DECL FORM 1.pdf20 Jan 2026
Form 2File: QPR DECL FORM 2.pdf20 Jan 2026
Form 3File: QPR DECL FORM 3.pdf20 Jan 2026

How this compares with Jalgaon

5%of Jalgaon projects moved their completion datethis one moved by 60 months
32%of Jalgaon registrations have lapsed or been cancelledthis one is on the register

Computed across the 230+ Jalgaon projects on ReraGenie, from their own filings.

Keep MANGALAM PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PACHORA230+ in Jalgaon

Builder: MANGALAM INFRA

MANGALAM INFRA has 2 registrations on MahaRERA, including RADHE KRISHNA RESIDENCY and MANGALAM PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalgaon district page.

Frequently asked questions

What are my rights if MANGALAM PARK is delayed beyond 29 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANGALAM PARK?

The registered promoter entity is MANGALAM INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANGALAM PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANGALAM PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANGALAM PARK?

The professionals named in the filing: Architect: UJJWAL SATISH BHOLE SATISH BHOLE; Engineer: SANDEEP RATANLAL TOSHNIWAL RATANLAL TOSHNIWAL; Engineer: BHARATSINGH BHIKAJI VAGHELA; Chartered Accountant: RAHUL PRAKASH PATIL; Chartered Accountant: SONAWANE MOR AND COMPANY; Chartered Accountant: RAHUL KISHOR DAYAMA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANGALAM PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANGALAM PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANGALAM PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.