ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / MANASAROVAR

Registration lapsed Litigation declared Residential / Group Housing project

MANASAROVAR

By HARASIDDH PROJECTS

RG-MH-23420 · RERA P51800078732 · Last updated on MahaRERA portal: 7 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
80 of 88Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

MANASAROVAR is a Residential / Group Housing project by HARASIDDH PROJECTS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800078732 on 8 Jan 2025. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 8 of the 88 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.

At a glance

Project

  • NameMANASAROVAR
  • TypeResidential / Group Housing
  • Location
    • Ram Galli
    • Kandivali (W)
    • Malad
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800078732
  • ReraGenie IDRG-MH-23420

Builder

  • NameHARASIDDH PROJECTS
  • Entity typePartnership

Key dates

7 months past promisethis monthRegisteredJan 2025PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Jan 2025
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed45 files

Current status

9%8 of 88 units booked
95.7%Work done, per cost certificate

Figures as on 7 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WINGNA252244044
A WINGNA252244044

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

B WING98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
A WING98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 7 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed144

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots144
Closed/Covered144
BuildingClosed/CoveredTotal
B WING7272
A WING7272

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,089 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jul 2025
LandownerVillageDistrict
BHOUMIK CO-OP HSG LTDMaladMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8339.44
Proposed, not sanctioned8,339 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR A WING SHOP NO 2 3 4 SANGAM CO OP HOUSING SOC S V ROAD SANTACRUZ WEST MUMBAI 400054
Estimated costRs 90.00 cr
Cost incurredRs 86.13 cr
Work done95.7%
BuildingWingEstimatedIncurred
B WINGNARs 45.00 crRs 43.07 cr
A WINGNARs 45.00 crRs 43.07 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPUSHKAR CONSULTANT
Engineerkaushal gandhi
EngineerARVIND VASUDEV MAHADIK
Chartered AccountantNEHALI DHAVAL DOSHI
Chartered AccountantM.S PARIKH & CO
PartnerRole in project
HARASIDDH PROJECTS-

Litigation declared2

CaseCourtStatus
76/2021HIGH COURTPENDING
1190/2019HIGH COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf7 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf7 Apr 2026
Withdrawal Update Form 3File: FORM 3.pdf7 Apr 2026
Layout approvalFile: OC Plans.pdf10 Mar 2026
Withdrawal Update Form 1File: Architect Certificate Dec 2025.pdf23 Feb 2026
Withdrawal Update Form 2File: Engineer Certificate Dec 2025.pdf23 Feb 2026
Withdrawal Update Form 3File: CA Certificate Dec 2025.pdf23 Feb 2026
Withdrawal Update Form 1File: form 1.pdf13 Oct 2025
Withdrawal Update Form 1File: form 1.pdf13 Oct 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate 30092025.pdf13 Oct 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate 30092025.pdf13 Oct 2025
Withdrawal Update Form 3File: CA Certificate 30092025.pdf13 Oct 2025
Withdrawal Update Form 3File: CA Certificate 30092025.pdf13 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A Supervisor Certificate 2025.pdf11 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 CA Certificate 2025.pdf11 Oct 2025
Details of encumbrances concerned to FinanceFile: Legal Encumbrance Declaration.pdf18 Dec 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrance Declaration.pdf18 Dec 2024
Other - FinanceFile: Finance Query Reply.pdf14 Dec 2024
Copy of the legal title reportFile: Title Certificate.pdf6 Dec 2024
Details of encumbrances concerned to FinanceFile: No Financial Encumbrance Declaration.pdf6 Dec 2024
Declaration about Commencement CertificateFile: CC Covering Letter (3).pdf6 Dec 2024
Details of encumbrances concerned to LegalFile: No Financial Encumbrance Declaration.pdf6 Dec 2024
Other - TechnicalFile: Declaration Cum Undertaking (4).pdf6 Dec 2024
Proforma of Agreement for saleFile: Proforma of Agreement For Sale.pdf6 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI 3.pdf6 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Loans.pdf6 Dec 2024
Layout approvalFile: Final approved plan.pdf4 Dec 2024
Copy of the legal title reportFile: Title Report (4).pdf4 Dec 2024
Copy of Layout Approval (in case of layout)File: Final approved plan.pdf4 Dec 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER (3).pdf4 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement (1).pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (11).pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate (9).pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (5).pdf3 Dec 2024
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment.pdf3 Dec 2024
Building plan approvalFile: IOD 10022022.pdf19 Nov 2024
PAN CardFile: HAP PAN Copy.pdf19 Nov 2024
Declaration in FORM BFile: FORM B Developer (1).pdf19 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Manasarovar Full CC.pdf19 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD 10022022.pdf19 Nov 2024
CERSAI detailsFile: CERSAI Declaration (35).pdf19 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Letter A.pdf19 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI 1.pdf19 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI 2 (1).pdf19 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Letter B.pdf19 Nov 2024

How this compares with Mumbai Suburban

9%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANASAROVAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali (W)6,700+ in Mumbai Suburban

2 kmMANASAROVARCompleted 160Lapsed / revoked 101Other 165Dot size: filed unitsN

Filed coordinates, straight-line distance. 426 registered projects within 2 km.

Builder: HARASIDDH PROJECTS

HARASIDDH PROJECTS has 1 registration on MahaRERA, including MANASAROVAR. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MANASAROVAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MANASAROVAR is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANASAROVAR?

The registered promoter entity is HARASIDDH PROJECTS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANASAROVAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANASAROVAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANASAROVAR?

The professionals named in the filing: Architect: PUSHKAR CONSULTANT; Engineer: kaushal gandhi; Engineer: ARVIND VASUDEV MAHADIK; Chartered Accountant: NEHALI DHAVAL DOSHI; Chartered Accountant: M.S PARIKH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANASAROVAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANASAROVAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANASAROVAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.