ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Majestic Krishna

Registered No litigation declared Residential / Group Housing project

Majestic Krishna

By Krishna Builders and Developers

RG-MH-06809 · RERA P52000053799 · Last updated on MahaRERA portal: 19 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
8 of 11Construction stages donefurthest along: Installation of Lifts, 83%
0 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

Majestic Krishna is a Residential / Group Housing project by Krishna Builders and Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000053799 on 30 Nov 2023. Possession is promised by 31 Dec 2026. 20 of the 20 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameMajestic Krishna
  • TypeResidential / Group Housing
  • Location
    • Plot No 37
    • Sector 6
    • Pushpak Nagar
    • Dapoli
    • Panvel
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000053799
  • ReraGenie IDRG-MH-06809

Builder

  • NameKrishna Builders and Developers
  • Entity typePartnership
  • PartnersGanesh Bechar Patel, Vijay Ganesh Patel
  • PartnerCHANDRESH GANESH PATEL
  • Other registrations1 more →

Key dates

this monthRegisteredNov 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Nov 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed96 files

Current status

100%20 of 20 units booked
100.0%Work done, per cost certificate

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Majestic KrishnaNA4420020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 83%.

Majestic Krishna: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.83%

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area320 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jun 2025

Approvals and building plan

Sanctioning authorityCIDCO Ltd
Permissible FSI730.76
Proposed, not sanctioned731 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 10 and 11 Plot No 29 Radha Krishna CHSL Sector 11 Kharghar Navi Mumbai 410210
Estimated costRs 1.50 cr
Cost incurredRs 1.50 cr
Work done100.0%
BuildingWingEstimatedIncurred
Majestic KrishnaNARs 1.38 crRs 1.38 cr
-NARs 12.00 lakhRs 12.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel Architects
EngineerS R Consultants
EngineerSumit Maruti Adkhale
Chartered AccountantSachin Maheshwari and Co
Chartered AccountantG D Shah & Associates
PartnerRole in project
Krishna Builders and Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q4Form1.pdf19 May 2026
Withdrawal Update Form 2File: Q4Form2.pdf19 May 2026
Withdrawal Update Form 3File: Q4Form3.pdf19 May 2026
Withdrawal Update Form 1File: Q3Form1.pdf26 Feb 2026
Withdrawal Update Form 2File: Q3Form2.pdf26 Feb 2026
Withdrawal Update Form 3File: Q3Form3.pdf26 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A New Format.pdf23 Feb 2026
Withdrawal Update Form 1File: Q2Form1.pdf22 Feb 2026
Withdrawal Update Form 2File: Q2Form2.pdf22 Feb 2026
Withdrawal Update Form 3File: Q2Form3.pdf22 Feb 2026
Form 2A (FY 2024-2025)File: Form2A.pdf19 Feb 2026
Form 5 (FY 2023-2024)File: Form 5.pdf18 Feb 2026
Form 5 (FY 2024-2025)File: Form5.pdf18 Feb 2026
Form 1File: Q3Form1.pdf15 Aug 2025
Form 2File: Q3Form2.pdf15 Aug 2025
Form 3File: Q3Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q3Soldunsold.pdf15 Aug 2025
Form 1File: Q4Form1.pdf15 Aug 2025
Form 2File: Q4Form2.pdf15 Aug 2025
Form 3File: Q4Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: SoldUnsold.pdf15 Aug 2025
Form 1File: Q1Form1.pdf15 Aug 2025
Form 2File: Q1Form2.pdf15 Aug 2025
Form 3File: Q1Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf15 Aug 2025
Form 1File: Q2Form1.pdf15 Aug 2025
Form 2File: Q2Form2.pdf15 Aug 2025
Form 3File: Q2Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf15 Aug 2025
Form 1File: Q3Form1.pdf15 Aug 2025
Form 2File: Q3Form2.pdf15 Aug 2025
Form 3File: Q3Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf15 Aug 2025
Form 1File: Q4Form1.pdf15 Aug 2025
Form 2File: Q4Form2.pdf15 Aug 2025
Form 3File: Q4Form3.pdf15 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf15 Aug 2025
Withdrawal Update Form 1File: Q1Form1.pdf13 Aug 2025
Withdrawal Update Form 2File: Q1Form2.pdf13 Aug 2025
Withdrawal Update Form 3File: Q1Form3.pdf13 Aug 2025
Withdrawal Update Form 1File: Q1Form1.pdf11 Aug 2025
Withdrawal Update Form 2File: Q1Form2.pdf11 Aug 2025
Withdrawal Update Form 3File: Q1Form3.pdf11 Aug 2025
Withdrawal Update Form 1File: Q1Form1.pdf5 Aug 2025
Withdrawal Update Form 2File: Q1Form2.pdf5 Aug 2025
Withdrawal Update Form 3File: Q1Form3.pdf5 Aug 2025
Withdrawal Update Form 1File: Q1Form1.pdf1 Aug 2025
Withdrawal Update Form 2File: Q1Form2.pdf1 Aug 2025
Withdrawal Update Form 3File: Q1Form3.pdf1 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q4Form3.pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4Form2.pdf12 May 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4Form1.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3Form3.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3Form2.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3Form1.pdf22 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q2Form3.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2Form2.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2Form1.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1Form1.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1Form3.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1Form2.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: SoldUnsold.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q4Form3.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4Form2.pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4Form1.pdf5 Apr 2024
Disclosure of sold/ booked inventoryFile: Q3Soldunsold.pdf11 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3Form3.pdf11 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3Form1.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3Form2.pdf25 Jan 2024
Declaration about Commencement CertificateFile: 06 Format D.pdf21 Nov 2023
Copy of the legal title reportFile: 02 Title Certificate.pdf2 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 36 Sepreate Bank Account.pdf28 Oct 2023
Other - LegalFile: 32 Tripartite Agreement.pdf27 Oct 2023
CERSAI detailsFile: 17 CERSAI.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 18 Form 3.pdf7 Oct 2023

How this compares with Raigarh

100%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Majestic Krishna on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pushpak Nagar5,900+ in Raigarh

2 kmMajestic KrishnaCompleted 5Lapsed / revoked 3Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 109 registered projects within 2 km.

Builder: Krishna Builders and Developers

Krishna Builders and Developers has 2 registrations on MahaRERA, including Majestic Krishna and KRISHNA CORNER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Majestic Krishna is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Majestic Krishna?

The registered promoter entity is Krishna Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Majestic Krishna?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Majestic Krishna?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Majestic Krishna?

The professionals named in the filing: Architect: Atul Patel Architects; Engineer: S R Consultants; Engineer: Sumit Maruti Adkhale; Chartered Accountant: Sachin Maheshwari and Co; Chartered Accountant: G D Shah & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Majestic Krishna?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Majestic Krishna. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Majestic Krishna to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.