Home / Browse projects / Nagpur, Maharashtra / MAHENDRA SKYLARK

Registered No litigation declared Residential / Group Housing project

MAHENDRA SKYLARK

By MAHENDRA INFRA HEIGHTS PRIVATE LIMITED

RG-MH-03658 · RERA P50500029870 · Last updated on MahaRERA portal: 8 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 43 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 43 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
15 of 28Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 155 documents Report an error

MAHENDRA SKYLARK is a Residential / Group Housing project by MAHENDRA INFRA HEIGHTS PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500029870 on 12 Jul 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 43 months from the original filing. 13 of the 28 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAHENDRA SKYLARK
  • TypeResidential / Group Housing
  • Location
    • SOUTH AMBAZARI
    • DONGRE LAYOUT
    • OPP ABHAYNAKAR NAGAR GARDEN
    • SHADHANANDPETH
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440010
  • Pincode440010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500029870
  • ReraGenie IDRG-MH-03658

Builder

  • NameMAHENDRA INFRA HEIGHTS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorMAHENDRA SHYAMRAO TAYWADE
  • DirectorsMALHAR MAHENDRA TAYWADE, DINESH DAULATRAO TAYWADE

Key dates

this monthRegisteredJul 2021First promiseMay 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Jul 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 May 2024)
  • Buildings1 building record
  • Documents filed155 files

Current status

46%13 of 28 units booked
91.9%Work done, per cost certificate

Figures as on 8 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAHENDRA SKYLARKNA9728028

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

MAHENDRA SKYLARK: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,490 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
JEEVAN VIHAR CO-OP HOUSING APT SOCIETY LTDNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Municipal Corporation
Permissible FSI2906.0
Proposed, not sanctioned2,744 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSOUTH AMBAZARI , DONGRE LAYOUT , OPP ABHAYNAKAR NAGAR GARDEN
Estimated costRs 17.47 cr
Cost incurredRs 16.06 cr
Work done91.91%
BuildingWingEstimatedIncurred
MAHENDRA SKYLARKNARs 17.47 crRs 16.06 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGN CELL
EngineerP S PATANKAR AND ASSOCIATES
EngineerSurendra K Deshpande
Chartered AccountantSANJAY CHINDALIYA AND CO
Chartered AccountantMJM Associates
PartnerRole in project
MAHENDRA INFRA HEIGHTS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500022964May 2024 → May 2025

Reason as filed by the promoterThe Project could not not completed in due time as there was shortage of sand and raw material in the area for few months,

EA19022619901May 2024 → Dec 2027

Reason as filed by the promoterDue delay in obtaining the necessary sanctions from the local authority-which involved multiple rounds of clarification and the resolution of certain technical and procedural discrepancies-we were unable to complete the project within the scheduled timeline

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC004000000030491Muskaan NayyarMahendra Shaymrao Taywade01/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed155

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 skyalrk.pdf8 Sep 2026
Withdrawal Update Form 2File: Form 2 skylark.pdf8 Sep 2026
Withdrawal Update Form 3File: Form 3 skylark.pdf8 Sep 2026
Withdrawal Update Form 1File: Mahendra Skylark Form 1 JAN TO MARCH.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 skylark.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 skylark.pdf21 Aug 2026
Form 2A (FY 2025-2026)File: Mahendra Skylark Form 2A.pdf30 Jul 2026
Withdrawal Update Form 1File: Mahendra Skylark Form 1 JAN TO MARCH.pdf20 Jul 2026
Withdrawal Update Form 2File: Mahendra Skylark Form 2 JAN TO MARCH.pdf20 Jul 2026
Withdrawal Update Form 3File: Mahendra Infra form 3 oct to dec 25 skylark.pdf20 Jul 2026
Withdrawal Update Form 1File: Mahendra Skylark Form 1 july to spet.pdf18 Apr 2026
Withdrawal Update Form 1File: Form 1_Oct-Dec 25.pdf18 Apr 2026
Withdrawal Update Form 1File: Mahendra Skylark Form 1 JAN TO MARCH.pdf18 Apr 2026
Withdrawal Update Form 2File: Mahendra Skylark Form 2 july to spet.pdf18 Apr 2026
Withdrawal Update Form 2File: Mahendra Skylark Form 2 oct to dec.pdf18 Apr 2026
Withdrawal Update Form 2File: Mahendra Skylark Form 2 JAN TO MARCH.pdf18 Apr 2026
Withdrawal Update Form 3File: Mahendra Infra form 3 july to sep 25 skylark.pdf18 Apr 2026
Withdrawal Update Form 3File: Mahendra Infra form 3 oct to dec 25 skylark.pdf18 Apr 2026
Withdrawal Update Form 3File: Mahendra Infra form 3 oct to dec 25 skylark.pdf18 Apr 2026
Form 1File: Form 1 july to sept 24 skylark.pdf12 Feb 2026
Form 2File: Form 2 july to sept 24 skyalrk.pdf12 Feb 2026
Form 3File: Form 3 - Jul to Sep 2024 skylark.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: DSBI Jul-Sept 24 skylark.pdf12 Feb 2026
Form 1File: skylark Form 1_Oct-Dec 24.pdf12 Feb 2026
Form 2File: skylark Form 2 Oct-Dec 24.pdf12 Feb 2026
Form 3File: skyalrk Form 3 - Oct to Dec 2024.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: skylark DSBI Oct-Dec 24.pdf12 Feb 2026
Form 1File: Form 1 jan to march 25.pdf12 Feb 2026
Form 2File: skylark Form 2 Oct-Dec 25.pdf12 Feb 2026
Form 3File: skylark Form 3 - Jan to Mar 2025.pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: skylark DSBI Jan-Mar 25.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 april to june 25 skylark.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 april to june 2025 skylark.pdf12 Feb 2026
Withdrawal Update Form 3File: Mahendra Infra Form 3 apr to jun 25 skylark_compressed.pdf12 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A (12).pdf12 Feb 2026
Form 2A (FY 2021-2022)File: Form 2A 22.pdf22 Jan 2026
Form 2A (FY 2022-2023)File: Form 2A 23.pdf22 Jan 2026
Form 2A (FY 2023-2024)File: Form 2A 24.pdf22 Jan 2026
Form 1File: july to sept 2021 form 1 skylark.pdf27 Nov 2025
Form 2File: july to sept 2021 form 2 skylark.pdf27 Nov 2025
Form 3File: july to sept 2021 form 3.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: july to sept 2021 dsbii.pdf27 Nov 2025
Form 1File: form 1 oct 2021.pdf27 Nov 2025
Form 2File: form 2 oct 2021.pdf27 Nov 2025
Form 3File: form 3 oct 2021.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi oct 2021.pdf27 Nov 2025
Form 1File: form 1 jan 2022.pdf27 Nov 2025
Form 2File: form 2 jan 2022.pdf27 Nov 2025
Form 3File: form 3 jan 2022.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi jan 2022.pdf27 Nov 2025
Form 1File: form 1 april 2022.pdf27 Nov 2025
Form 2File: form 2 april 2022.pdf27 Nov 2025
Form 3File: form 3 april 2022.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi april 2022.pdf27 Nov 2025
Form 1File: form 1 july 2022.pdf27 Nov 2025
Form 2File: form 2 july 2022.pdf27 Nov 2025
Form 3File: form 3 july 2023.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi july 2022.pdf27 Nov 2025
Form 1File: form 1 oct 2022.pdf27 Nov 2025
Form 2File: form 2 oct 2022.pdf27 Nov 2025
Form 3File: form 3 oct 2022.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi oct 2022.pdf27 Nov 2025
Form 1File: form 1 jan 2023.pdf27 Nov 2025
Form 2File: form 2 jan 2023.pdf27 Nov 2025
Form 3File: form 3 jan 2023.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi jan 2023.pdf27 Nov 2025
Form 1File: form 1 april 2023.pdf27 Nov 2025
Form 2File: form 2 april 2023.pdf27 Nov 2025
Form 3File: form 3 april 2023.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi april 2023.pdf27 Nov 2025
Form 1File: form 1 july 2023.pdf27 Nov 2025
Form 2File: form 2 july 2023.pdf27 Nov 2025
Form 3File: form 3 july 2023.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi july 2023.pdf27 Nov 2025
Form 1File: form 1 oct 2023.pdf27 Nov 2025
Form 2File: form 2 oct 2023.pdf27 Nov 2025
Form 3File: form 3 oct 2023.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: dsbi oct 2023.pdf27 Nov 2025
Form 1File: form 1 jan 2024.pdf27 Nov 2025
Form 2File: form 2 jan 2024.pdf27 Nov 2025

How this compares with Nagpur

46%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 43 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHENDRA SKYLARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHADHANANDPETH2,800+ in Nagpur

2 kmMAHENDRA SKYLARKCompleted 16Lapsed / revoked 4Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: MAHENDRA INFRA HEIGHTS PRIVATE LIMITED

MAHENDRA INFRA HEIGHTS PRIVATE LIMITED has 1 registration on MahaRERA, including MAHENDRA SKYLARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if MAHENDRA SKYLARK is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHENDRA SKYLARK?

The registered promoter entity is MAHENDRA INFRA HEIGHTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHENDRA SKYLARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHENDRA SKYLARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAHENDRA SKYLARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHENDRA SKYLARK?

The professionals named in the filing: Architect: DESIGN CELL; Engineer: P S PATANKAR AND ASSOCIATES; Engineer: Surendra K Deshpande; Chartered Accountant: SANJAY CHINDALIYA AND CO; Chartered Accountant: MJM Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHENDRA SKYLARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHENDRA SKYLARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHENDRA SKYLARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.