Home / Browse projects / Mumbai Suburban, Maharashtra / Mahavir Majesty

Registered No litigation declared Others project

Mahavir Majesty

By Mahavir Builders

RG-MH-80443 · RERA P51800032166 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
89 of 121Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

Mahavir Majesty is a Others project by Mahavir Builders in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032166 on 14 Dec 2021. Possession was promised by 15 Sep 2026 and is now 1 months past that date. The completion date has moved by 9 months from the original filing. 32 of the 121 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.

At a glance

Project

  • NameMahavir Majesty
  • TypeOthers
  • Location
    • M G Road
    • Kandivali West
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800032166
  • ReraGenie IDRG-MH-80443

Builder

  • NameMahavir Builders
  • Entity typePartnership
  • PartnersNikhil Jitendra Mehta, Paras Jitendra Mehta
  • Other registrations2 more →
  • Completed1 of 3
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredDec 2021First promiseDec 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Dec 2021
  • Promised completion15 Sep 2026
  • Revised completionRevised to 15 Sep 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed128 files

Current status

26%32 of 121 units booked
108.6%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA20403636
Wing BNA251585085

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

Wing A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed122

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots122
Closed/Covered122
BuildingClosed/CoveredTotal
Wing A3939
Wing B8383

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,367 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Jai Vishwambhari Co-operative Housing Society LtdBorivaliMumbai Suburban
New Rakhi Co-operative Housing Society LtdBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI7480.43
Proposed, not sanctioned5,197 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS NO 637 637 1 2 NEW CTS NO 637A CHANDA WARKAR ROAD BOREVALI MUMBAI 400092
Estimated costRs 38.05 cr
Cost incurredRs 41.33 cr
Work done108.63%
BuildingWingEstimatedIncurred
Wing ANARs 18.07 crRs 19.63 cr
Wing BNARs 18.07 crRs 19.63 cr
-NARs 1.90 crRs 2.07 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay B Shah
EngineerSK Consultants & Engineers
EngineerS K Consultants & Engineers
EngineerArvind Shah
Chartered AccountantNB Sayed & Associates
Chartered AccountantPranav Bhaskaran & Associates
Chartered AccountantGaurav S Rajpal & Co
PartnerRole in project
Mahavir Builders-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11062621313Dec 2025 → Sep 2026

Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 03/10/2025 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and the total number of parking. In view of this as the said projesct obtained full OC uploading consents from allottees will not be required. To provide

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Mar 2024

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf29 Jun 2026
Form 2A (FY 2021-2022)File: Form 2A_FY_2021-22.pdf29 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A_FY_2022-23.pdf29 Jun 2026
Form 2A (FY 2023-2024)File: Form 2A_FY_2023-24.pdf29 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A_FY_2024-25.pdf29 Jun 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf8 Jun 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf8 Jun 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf8 Jun 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf8 Jun 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf8 Jun 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf8 Jun 2026
Form 5 (FY 2022-2023)File: Form 5- Mahavir Majesty FY 2022-23.pdf11 Mar 2026
Form 5 (FY 2023-2024)File: Form 5- Mahavir Majesty for FY 2023-24.pdf11 Mar 2026
Form 5 (FY 2024-2025)File: Form 5- Mahavir Majesty_For FY 2024-25.pdf7 Mar 2026
Form 1File: Form 1 - Mahavir Majesty as on June 2025.pdf28 Feb 2026
Form 2File: Form 2 - Mahavir Majesty as on June 2025.pdf28 Feb 2026
Form 3File: Form 3 - Mahavir Majesty as on June 2025.pdf28 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 -Mahavir Majesty as on June 2025.pdf28 Feb 2026
Form 1File: Form 1 - Mahavir Majesty as on Sep 2025.pdf28 Feb 2026
Form 2File: Form 2 - Mahavir Majesty as on Sept 2025.pdf28 Feb 2026
Form 3File: Form 3 - Mahavir Majesty as on Sep 2025.pdf28 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Mahavir Majesty as on Sep 2025.pdf28 Feb 2026
Form 1File: Form 1 - Mahavir Majesty as on March 2025.pdf28 Feb 2026
Form 2File: Form 2 - Mahavir Majesty as on March 2025.pdf28 Feb 2026
Form 3File: Form 3 - Mahavir Majesty as on March 2025.pdf28 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Mahavir Majesty as on March 2025.pdf28 Feb 2026
Details of encumbrancesFile: Encumbrance_Letter_MM.pdf16 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_as_on_31-03-2025_compressed.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory_updation_as_on_31-3-2025_compressed.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 31-12-2024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on 31-12-2024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Mahavir Majesty Sep 2024 (1).pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 30-09-2024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on 30-09-2024.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Mahavir Majesty Circular_29_compressed.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on June 2024.pdf12 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 30-06-2024.pdf12 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on June 2024.pdf8 Jul 2024
Disclosure of sold/ booked inventoryFile: Circular 29 - Mahavir Majesty as on June 2024.pdf8 Jul 2024
Home Buyer /Allottee Grievance Redressal CellFile: Redressal_Declaration.pdf8 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on March 2024.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Mahavir Majesty as on March 2024.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fROM_1_31-03-2024.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RevisedForm3.pdf11 Apr 2024
Declaration about Commencement CertificateFile: Declaration_about_CC_Fromate_D.pdf22 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2023.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_11zon.pdf18 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format_A.pdf18 Mar 2024
Building plan approvalFile: Drawing_20th_Floor_compressed.pdf12 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing_20th_Floor_compressed.pdf12 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - Mahavir Majesty.pdf7 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold_Inventory_31-12-2023_compressed.pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - Mahavir Majesty.pdf9 Feb 2024
Proforma of Agreement for saleFile: 1_SALE_DEED_-_COMMERCIAL_RERA_SUBMISSION.pdf18 Jan 2024
Proforma of Agreement for saleFile: 1_AFS_AU_SMALL_-_RESI_Mahavir_Builders-2.pdf18 Jan 2024
Declaration about Commencement CertificateFile: Format D.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on Dec 2023.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_31-012-2023_11zon.pdf17 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 2372455_FurtherCC_signed.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on Dec 2023.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty Dec 2023.pdf16 Jan 2024
Proforma of Agreement for saleFile: SALE_DEED_-_RESI_RERA_SUBMISSION.pdf16 Jan 2024
Proforma of Agreement for saleFile: SALE_DEED_-_COMMERCIAL_RERA_SUBMISSION.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed (2).pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A_2021-2022.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A_2022_-_2023.pdf19 Dec 2023
Disclosure of sold/ booked inventoryFile: Circular_29_compressed.pdf19 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed (9).pdf19 Dec 2023
Details of encumbrancesFile: Rera_Encumbrance.pdf14 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Mahavir Majesty One as on June 2023.pdf9 Nov 2023
Building plan approvalFile: Layout- Mahavir Majesty_compressed.pdf31 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Layout- Mahavir Majesty_compressed.pdf31 Oct 2023
Building plan approvalFile: Mahavir Majesty- Layout_compressed.pdf30 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Mahavir Majesty- Layout_compressed.pdf30 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on Sep 2023.pdf27 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty Sept 2023.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on Sep 2023.pdf10 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Mahavir Majesty FY 2022-23.pdf22 Sep 2023

How this compares with Mumbai Suburban

26%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 9 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahavir Majesty on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali West6,700+ in Mumbai Suburban

2 kmMahavir MajestyCompleted 121Lapsed / revoked 67Other 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 332 registered projects within 2 km.

Builder: Mahavir Builders

Mahavir Builders has 3 registrations on MahaRERA, including Mahavir Majesty and Mahavir Santoshika. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Mahavir Majesty is delayed beyond 15 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahavir Majesty?

The registered promoter entity is Mahavir Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahavir Majesty?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mahavir Majesty?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahavir Majesty?

The professionals named in the filing: Architect: Sanjay B Shah; Engineer: SK Consultants & Engineers; Engineer: S K Consultants & Engineers; Engineer: Arvind Shah; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahavir Majesty?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahavir Majesty. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahavir Majesty to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.