Home / Browse projects / Mumbai Suburban, Maharashtra / Mahavir Majesty
Mahavir Majesty
RG-MH-80443 · RERA P51800032166 · Last updated on MahaRERA portal: 29 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mahavir Majesty is a Others project by Mahavir Builders in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032166 on 14 Dec 2021. Possession was promised by 15 Sep 2026 and is now 1 months past that date. The completion date has moved by 9 months from the original filing. 32 of the 121 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.
At a glance
Project
- NameMahavir Majesty
- TypeOthers
- Location
- M G Road
- Kandivali West
- Borivali
- Mumbai Suburban
- 400067
- Pincode400067
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800032166
- ReraGenie IDRG-MH-80443
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Dec 2021
- Promised completion15 Sep 2026
- Revised completionRevised to 15 Sep 2026 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed128 files
Current status
Figures as on 29 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 20 | 4 | 0 | 36 | 36 |
| Wing B | NA | 25 | 15 | 85 | 0 | 85 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
Wing A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed122
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 39 | 39 |
| Wing B | 83 | 83 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Jai Vishwambhari Co-operative Housing Society Ltd | Borivali | Mumbai Suburban |
| New Rakhi Co-operative Housing Society Ltd | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing A | NA | Rs 18.07 cr | Rs 19.63 cr |
| Wing B | NA | Rs 18.07 cr | Rs 19.63 cr |
| - | NA | Rs 1.90 cr | Rs 2.07 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjay B Shah |
| Engineer | SK Consultants & Engineers |
| Engineer | S K Consultants & Engineers |
| Engineer | Arvind Shah |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | Pranav Bhaskaran & Associates |
| Chartered Accountant | Gaurav S Rajpal & Co |
| Partner | Role in project |
|---|---|
| Mahavir Builders | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 03/10/2025 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and the total number of parking. In view of this as the said projesct obtained full OC uploading consents from allottees will not be required. To provide
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 May 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Mar 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Mar 2024
Documents filed128
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 29 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 29 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 29 Jun 2026 |
| Form 2A (FY 2021-2022)File: Form 2A_FY_2021-22.pdf | 29 Jun 2026 |
| Form 2A (FY 2022-2023)File: Form 2A_FY_2022-23.pdf | 29 Jun 2026 |
| Form 2A (FY 2023-2024)File: Form 2A_FY_2023-24.pdf | 29 Jun 2026 |
| Form 2A (FY 2024-2025)File: Form 2A_FY_2024-25.pdf | 29 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate.pdf | 8 Jun 2026 |
| Form 5 (FY 2022-2023)File: Form 5- Mahavir Majesty FY 2022-23.pdf | 11 Mar 2026 |
| Form 5 (FY 2023-2024)File: Form 5- Mahavir Majesty for FY 2023-24.pdf | 11 Mar 2026 |
| Form 5 (FY 2024-2025)File: Form 5- Mahavir Majesty_For FY 2024-25.pdf | 7 Mar 2026 |
| Form 1File: Form 1 - Mahavir Majesty as on June 2025.pdf | 28 Feb 2026 |
| Form 2File: Form 2 - Mahavir Majesty as on June 2025.pdf | 28 Feb 2026 |
| Form 3File: Form 3 - Mahavir Majesty as on June 2025.pdf | 28 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 -Mahavir Majesty as on June 2025.pdf | 28 Feb 2026 |
| Form 1File: Form 1 - Mahavir Majesty as on Sep 2025.pdf | 28 Feb 2026 |
| Form 2File: Form 2 - Mahavir Majesty as on Sept 2025.pdf | 28 Feb 2026 |
| Form 3File: Form 3 - Mahavir Majesty as on Sep 2025.pdf | 28 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Mahavir Majesty as on Sep 2025.pdf | 28 Feb 2026 |
| Form 1File: Form 1 - Mahavir Majesty as on March 2025.pdf | 28 Feb 2026 |
| Form 2File: Form 2 - Mahavir Majesty as on March 2025.pdf | 28 Feb 2026 |
| Form 3File: Form 3 - Mahavir Majesty as on March 2025.pdf | 28 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Mahavir Majesty as on March 2025.pdf | 28 Feb 2026 |
| Details of encumbrancesFile: Encumbrance_Letter_MM.pdf | 16 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_as_on_31-03-2025_compressed.pdf | 16 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory_updation_as_on_31-3-2025_compressed.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 31-12-2024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on 31-12-2024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Mahavir Majesty Sep 2024 (1).pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 30-09-2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on 30-09-2024.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Mahavir Majesty Circular_29_compressed.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on June 2024.pdf | 12 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty 30-06-2024.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on June 2024.pdf | 8 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Mahavir Majesty as on June 2024.pdf | 8 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Redressal_Declaration.pdf | 8 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on March 2024.pdf | 6 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Mahavir Majesty as on March 2024.pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fROM_1_31-03-2024.pdf | 12 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RevisedForm3.pdf | 11 Apr 2024 |
| Declaration about Commencement CertificateFile: Declaration_about_CC_Fromate_D.pdf | 22 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2023.pdf | 18 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_11zon.pdf | 18 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format_A.pdf | 18 Mar 2024 |
| Building plan approvalFile: Drawing_20th_Floor_compressed.pdf | 12 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing_20th_Floor_compressed.pdf | 12 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - Mahavir Majesty.pdf | 7 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold_Inventory_31-12-2023_compressed.pdf | 26 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - Mahavir Majesty.pdf | 9 Feb 2024 |
| Proforma of Agreement for saleFile: 1_SALE_DEED_-_COMMERCIAL_RERA_SUBMISSION.pdf | 18 Jan 2024 |
| Proforma of Agreement for saleFile: 1_AFS_AU_SMALL_-_RESI_Mahavir_Builders-2.pdf | 18 Jan 2024 |
| Declaration about Commencement CertificateFile: Format D.pdf | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on Dec 2023.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_31-012-2023_11zon.pdf | 17 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 2372455_FurtherCC_signed.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on Dec 2023.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty Dec 2023.pdf | 16 Jan 2024 |
| Proforma of Agreement for saleFile: SALE_DEED_-_RESI_RERA_SUBMISSION.pdf | 16 Jan 2024 |
| Proforma of Agreement for saleFile: SALE_DEED_-_COMMERCIAL_RERA_SUBMISSION.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed (2).pdf | 19 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A_2021-2022.pdf | 19 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A_2022_-_2023.pdf | 19 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Circular_29_compressed.pdf | 19 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed (9).pdf | 19 Dec 2023 |
| Details of encumbrancesFile: Rera_Encumbrance.pdf | 14 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Mahavir Majesty One as on June 2023.pdf | 9 Nov 2023 |
| Building plan approvalFile: Layout- Mahavir Majesty_compressed.pdf | 31 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout- Mahavir Majesty_compressed.pdf | 31 Oct 2023 |
| Building plan approvalFile: Mahavir Majesty- Layout_compressed.pdf | 30 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Mahavir Majesty- Layout_compressed.pdf | 30 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mahavir Majesty as on Sep 2023.pdf | 27 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Mahavir Majesty Sept 2023.pdf | 16 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mahavir Majesty as on Sep 2023.pdf | 10 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Mahavir Majesty FY 2022-23.pdf | 22 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 128 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mahavir Majesty on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kandivali West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 332 registered projects within 2 km.
Ruparel Optima Ph I
Ruparel Infra & Realty Pvt Ltd
"SALE BLDG NO. 6 (A & B) WING KNOWN AS NORTHER
N.ROSE DEVELOPERS PVT LTD
JP Commerz
Metallica Industries Limited
Ruparel Skygreens I
Shree Siddhivinayak Infrastructure & Realt
ShreejiAikyam
Rushabh Developers
Shiv Vardaan
NAVKARMIK HOMES LLP, URVI CONSTRUCTION
See every Mumbai Suburban project, with the district possession charts
Builder: Mahavir Builders
Mahavir Builders has 3 registrations on MahaRERA, including Mahavir Majesty and Mahavir Santoshika. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Mahavir Majesty is delayed beyond 15 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mahavir Majesty?
The registered promoter entity is Mahavir Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mahavir Majesty?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mahavir Majesty?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mahavir Majesty?
The professionals named in the filing: Architect: Sanjay B Shah; Engineer: SK Consultants & Engineers; Engineer: S K Consultants & Engineers; Engineer: Arvind Shah; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mahavir Majesty?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback