Home / Browse projects / Nagpur, Maharashtra / MADHUBAN II
MADHUBAN II
By R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED
RG-MH-58564 · RERA P50500077221 · Last updated on MahaRERA portal: 30 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MADHUBAN II is a Residential / Group Housing project by R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500077221 on 31 Jul 2024. Possession is promised by 31 Mar 2028.
At a glance
Project
- NameMADHUBAN II
- TypeResidential / Group Housing
- Location
- DEWAPUR ROAD
- GRAMPANCHAYAT TAKALGHAT
- Dewapur
- Hingna
- Nagpur
- 441122
- Pincode441122
- RERA no.P50500077221
- ReraGenie IDRG-MH-58564
Builder
- NameR A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED
- Entity typeCompany
- DirectorJOY BAHL
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Jul 2024
- Promised completion31 Mar 2028
- Revised completionNone
- Buildings28 building records
- Documents filed44 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 A | NA | 5 | 0 | 0 | 0 | 0 |
| 1 B | NA | 5 | 0 | 0 | 0 | 0 |
| 1 C | NA | 5 | 0 | 0 | 0 | 0 |
| 1 D | NA | 5 | 0 | 0 | 0 | 0 |
| 1 E | NA | 5 | 0 | 0 | 0 | 0 |
| 1 F | NA | 5 | 0 | 0 | 0 | 0 |
| 2 A | NA | 5 | 0 | 0 | 0 | 0 |
| 2 B | NA | 5 | 0 | 0 | 0 | 0 |
| 2 C | NA | 5 | 0 | 0 | 0 | 0 |
| 3 A | NA | 5 | 0 | 0 | 0 | 0 |
| 3 B | NA | 5 | 0 | 0 | 0 | 0 |
| 3 C | NA | 5 | 0 | 0 | 0 | 0 |
| 3 D | NA | 5 | 0 | 0 | 0 | 0 |
| 3 E | NA | 5 | 0 | 0 | 0 | 0 |
| 3 F | NA | 5 | 0 | 0 | 0 | 0 |
| 3 G | NA | 5 | 0 | 0 | 0 | 0 |
| 3 H | NA | 5 | 0 | 0 | 0 | 0 |
| 3 I | NA | 5 | 0 | 0 | 0 | 0 |
| 3 J | NA | 5 | 0 | 0 | 0 | 0 |
| 3 K | NA | 5 | 0 | 0 | 0 | 0 |
| 3 Q | NA | 5 | 0 | 0 | 0 | 0 |
| 3 R | NA | 5 | 0 | 0 | 0 | 0 |
| 3 S | NA | 5 | 0 | 0 | 0 | 0 |
| 3 T | NA | 5 | 0 | 0 | 0 | 0 |
| 4 A | NA | 9 | 0 | 0 | 0 | 0 |
| 4 B | NA | 9 | 0 | 0 | 0 | 0 |
| 4 C | NA | 9 | 0 | 0 | 0 | 0 |
| 4 D | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 30 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 28 buildings; the table lists the first 20.
120 of 308 construction stages are filed complete across 28 buildings. The stage furthest along is Slabs of Super Structure, at 0%.
1 A45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1 B45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1 C45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1 D45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1 E45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
1 F45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
2 A45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
2 B45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
2 C45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 A45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 B45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 C45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 D45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 E45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 F45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 G45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 H45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 I45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 J45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
3 K45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2715
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| 1 A | 21 | 21 |
| 1 B | 21 | 21 |
| 1 C | 21 | 21 |
| 1 D | 21 | 21 |
| 1 E | 21 | 21 |
| 1 F | 21 | 21 |
| 2 A | 74 | 74 |
| 2 B | 74 | 74 |
| 2 C | 74 | 74 |
| 3 A | 129 | 129 |
| 3 B | 129 | 129 |
| 3 C | 129 | 129 |
| 3 D | 129 | 129 |
| 3 E | 129 | 129 |
| 3 F | 129 | 129 |
| 3 G | 129 | 129 |
| 3 H | 129 | 129 |
| 3 I | 129 | 129 |
| 3 J | 129 | 129 |
| 3 K | 129 | 129 |
| 3 Q | 129 | 129 |
| 3 R | 129 | 129 |
| 3 S | 129 | 129 |
| 3 T | 129 | 129 |
| 4 A | 108 | 108 |
| 4 B | 108 | 108 |
| 4 C | 108 | 108 |
| 4 D | 108 | 108 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| LANDMARK BUILDERS AND DEVELOPERS | Nagpur (M Corp.) | Nagpur |
| RAJ KRISHNA CONSTRUCTION COMPANY PVT LTD | - | South |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH SHRIKRISHNA RAJANKAR |
| Engineer | Birendra Kumar Pal |
| Chartered Accountant | Mahesh Bidichandani |
| Partner | Role in project |
|---|---|
| R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: BUILDING PLAN APPROVAL FINAL.pdf | 30 Jul 2024 |
| Layout approvalFile: LAYOUT PLAN MARKED FINAL.pdf | 30 Jul 2024 |
| Layout approvalFile: LAYOUT APPROVAL FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BUILDING PLAN 1 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BUILDING PLAN 2 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BUILDING PLAN 3 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BUILDING PLAN 4 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BLDG ELEVATION 1,2 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: BLDG ELEVATION 3,4 FINAL.pdf | 30 Jul 2024 |
| Building plan approvalFile: PARKING LAYOUT FINAL.pdf | 30 Jul 2024 |
| Layout approvalFile: LAYOUT APPROVAL LETTER.pdf | 30 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN MARKED FINAL.pdf | 30 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL FINAL.pdf | 30 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL LETTER.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN APPROVAL FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 1 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 2 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 3 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 4 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG ELEVATION 1,2 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG ELEVATION 3,4 FINAL.pdf | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: PARKING LAYOUT FINAL.pdf | 30 Jul 2024 |
| Declaration in FORM BFile: FORM B.pdf | 10 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: ilovepdf_merged.pdf | 21 May 2024 |
| Details of encumbrances concerned to LegalFile: ilovepdf_merged.pdf | 21 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GetUserDocumentFileContent.pdf | 21 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Order 34 For Separate Bank Account.pdf | 21 May 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report- Allotment Letter.pdf | 21 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report- Agreement To Sale.pdf | 21 May 2024 |
| Other - LegalFile: Sale Deed 44 A Dewapur_compressed.pdf | 21 May 2024 |
| Other - LegalFile: sale deed 44 B_compressed.pdf | 21 May 2024 |
| Other - TechnicalFile: 6 Other - Technical.pdf | 21 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Project NEW.pdf | 6 Oct 2023 |
| Other - TechnicalFile: BR000.pdf | 28 Sep 2023 |
| Declaration in FORM BFile: Affidavit.pdf | 13 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: FINANCE AND LEGAL MERGED.pdf | 8 Aug 2023 |
| Details of encumbrances concerned to LegalFile: FINANCE AND LEGAL MERGED.pdf | 8 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-Plinth_28Bldg.pdf | 8 Aug 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 8 Aug 2023 |
| CERSAI detailsFile: Undertaking of No Security Interest.pdf | 8 Aug 2023 |
| Proforma of Agreement for saleFile: 2 Proforma of Agreement for sale.pdf | 8 Aug 2023 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment Letter.pdf | 8 Aug 2023 |
| PAN CardFile: 1 PAN Card.pdf | 5 Aug 2023 |
| Copy of the legal title reportFile: SEARCH REPORT COMPRESSED.pdf | 5 Aug 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MADHUBAN II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GRAMPANCHAYAT TAKALGHAT2,800+ in Nagpur
Rivershore Estate
Godrej Skyline Developers Ltd
Godrej Forest Estate
Dream World Landmarks LLP
Vrindavan Phase-3
Radha Madhav Developers
Kalpataru Ardene
Azure Tree Enviro Farms Private Limited
MAHALAXMI NAGAR-10
PADMALAXMI INFRTECH
VRINDAVAN PARK
TIRUPATI DEVELOPERS
See every Nagpur project, with the district possession charts
Builder: R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED
R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED has 2 registrations on MahaRERA, including MADHUBAN and MADHUBAN II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if MADHUBAN II is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MADHUBAN II?
The registered promoter entity is R A J KRISHNA CONSTRUCTION COMPANY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MADHUBAN II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MADHUBAN II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MADHUBAN II?
The professionals named in the filing: Architect: RAJESH SHRIKRISHNA RAJANKAR; Engineer: Birendra Kumar Pal; Chartered Accountant: Mahesh Bidichandani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MADHUBAN II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback