Home / Browse projects / Ahmednagar, Maharashtra / MADHUBAN APARTMENT
MADHUBAN APARTMENT
RG-MH-00659 · RERA P52200003164 · Last updated on MahaRERA portal: 8 Apr 2022
Source: official MahaRERA filing
Red flags
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MADHUBAN APARTMENT is a Others project by LUNIYA MUNOT AND COMPANY in Ahmednagar, Maharashtra, registered with MahaRERA as P52200003164 on 4 Aug 2017. The registration is recorded completed; possession was promised by 30 Apr 2023. The completion date has moved by 30 months from the original filing.
At a glance
Project
- NameMADHUBAN APARTMENT
- TypeOthers
- Location
- Ahmadnagar (M Corp.)
- Nagar
- Ahmednagar
- 414001
- Pincode414001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52200003164
- ReraGenie IDRG-MH-00659
Builder
- NameLUNIYA MUNOT AND COMPANY
- Entity typePartnership
- PartnerRAJENDRA SHANTILAL MUNOT
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 Aug 2017
- Promised completion30 Apr 2023
- Revised completionRevised to 30 Apr 2023 (originally 31 Oct 2020)
- Buildings1 building record
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MADHUBAN | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
MADHUBAN: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed52
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANJAY VINYAK SOWANI |
| Engineer | P S KULKARNI |
| Partner | Role in project |
|---|---|
| LUNIYA MUNOT AND COMPANY | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1)DUE TO COVID-19 LOSSES OF VARIOUS AGENCY MEMBERS OF OUR TEAM, 2)LOCKDOWN WAS DECLARED BY HON. COLLECTOR OF AHMEDNAGAR CITY , 3)HEALTH ISSUES OF KEY PERSON OF OUR FIRM , 4)SHORTAGE OF FUNDS FOR COMPLETION OF PROJECT.
Reason as filed by the promoterRespected Authority, Due to Covid lockdown we could not sell flats on time and due to that we have shortage of funds and availability of labour. We will be completing project on time to all flat holders. The new completion date will be 30th April 2023. So we request you to kindly review our application and approve us the new completion date for the above mentioned project. Thank you.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Jul 2021
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form_4_-_Architects_Letter.pdf | 8 Apr 2022 |
| Status of ConveyanceFile: Declaration_undertaking_-_MadhubanApt.pdf | 7 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form_5_-_2017-18.pdf | 13 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form_5_-_2018-19.pdf | 13 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form_5_-_2019-20.pdf | 13 Oct 2021 |
| Declaration about Commencement CertificateFile: Form_D_-_Declaration.pdf | 25 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_-_Engineers_certificate.pdf | 25 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form_2A_-_31032019-c.pdf | 25 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form_2A_-_2019-20.pdf | 25 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form_2A-_2017-18.pdf | 25 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form_2A_-_31032019-c.pdf | 25 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form_2A_-_2020-21.pdf | 25 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Certificates of CA (Form 5).pdf | 25 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Discolsure of Sold Inventory.PDF | 15 Aug 2021 |
| Certificates of CA (Form 3)File: Chartered Accountants Form 5 (UT).PDF | 15 Aug 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect's Certificate Form 4.PDF | 15 Aug 2021 |
| Declaration about Commencement CertificateFile: download.pdf | 17 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert.pdf | 17 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Cert.pdf | 17 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SOWANI CERTIFICATE RERA.PDF | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KAKDE CERTIFICATE RERA.PDF | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.PDF | 29 Jul 2017 |
| Proforma of Allotment letterFile: MADHUBAN AGG.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.PDF | 29 Jul 2017 |
| Layout approvalFile: LAYOUT.pdf | 15 Jul 2017 |
| Building plan approvalFile: FINAL PLAN2.pdf | 15 Jul 2017 |
| Building plan approvalFile: FINAL PLAN1.pdf | 15 Jul 2017 |
| Building plan approvalFile: FINAL PLAN1.pdf | 15 Jul 2017 |
| PAN CardFile: New Doc 2017-07-15_1.pdf | 15 Jul 2017 |
| Copy of the legal title reportFile: CERTIFICATE.pdf | 15 Jul 2017 |
| Details of encumbrancesFile: SEARCH REPORT.PDF | 15 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 15 Jul 2017 |
| Building Plan Approval (IOD)File: FINAL PLAN2.pdf | 15 Jul 2017 |
| Building Plan Approval (IOD)File: FINAL PLAN1.pdf | 15 Jul 2017 |
| Building Plan Approval (IOD)File: FINAL PLAN1.pdf | 15 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT.PDF | 15 Jul 2017 |
| Declaration in FORM BFile: FORM B.PDF | 15 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHANTI NAGAR | VINAYAK NAGAR PUNE NAGAR ROAD AHMEDNAGAR | 20 | Completed | Mar 2014 | Dec 2013 |
| YASH APARTMENT | SARAS NAGAR BEHIND MARKET YARD AHMEDNAGAR | 31 | Completed | Jun 2011 | Apr 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmednagar
Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
Keep MADHUBAN APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ahmadnagar (M Corp.)490+ in Ahmednagar
CROWN PLAZA
MAHAVIR INFRA PLUS LLP
PLATINUM PLAZA
SPY DEVELOPERS BUILDERS AND SUPPLIERS
Sandal Suites Shirdi
Sandal Lands Private Limited
REGENT
RISELIFE SPACES
YUVRAJ RESIDENCY
ASHOK LALCHAND DESARDA
Arabella
Marc Developers
See every Ahmednagar project, with the district possession charts
Builder: LUNIYA MUNOT AND COMPANY
LUNIYA MUNOT AND COMPANY has 1 registration on MahaRERA, including MADHUBAN APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ahmednagar district page.
Frequently asked questions
What are my rights if MADHUBAN APARTMENT is delayed beyond 30 Apr 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MADHUBAN APARTMENT?
The registered promoter entity is LUNIYA MUNOT AND COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MADHUBAN APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MADHUBAN APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MADHUBAN APARTMENT?
The professionals named in the filing: Architect: SANJAY VINYAK SOWANI; Engineer: P S KULKARNI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MADHUBAN APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.