Home / Browse projects / MAARIA ANNEXE

Registered Litigation declared Mixed project

MAARIA ANNEXE

By LAKADAWALA DEVELOPERS PVT LTD

RG-MH-20825 · RERA P51900007782 · Last updated on MahaRERA portal: 12 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 107 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2029Possession promisedmoved 107 months from the original
0 of 11Construction stages doneacross 2 buildings; furthest along: Excavation, 85%
87 of 160Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

MAARIA ANNEXE is a Mixed project by LAKADAWALA DEVELOPERS PVT LTD in 400037, registered with MahaRERA as P51900007782 on 18 Aug 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 107 months from the original filing. 73 of the 160 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAARIA ANNEXE
  • TypeMixed
  • Location
    • JK BHASIN ROAD & AMBEDKAR ROAD
    • 400037
  • Pincode400037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007782
  • ReraGenie IDRG-MH-20825

Builder

  • NameLAKADAWALA DEVELOPERS PVT LTD
  • Entity typeCompany
  • Managing DirectorMUSA ISMAIL LAKDAWALA
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJan 2021Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed126 files

Current status

46%73 of 160 units booked
57.1%Work done, per cost certificate

Figures as on 12 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAARIANA161614613159

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 12 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 85%.

MAARIA60%
ActivityProgress
Excavation85%
Basement (if any)0%
Podiums (if any)55%
Plinth85%
Stilt Floor85%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 12 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,513 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Dec 2025

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY(SRA)
Permissible FSI12957.5
Proposed, not sanctioned3,062 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAZGAON MUMBAI 400010
Estimated costRs 40.00 cr
Cost incurredRs 22.86 cr
Work done57.14%
BuildingWingEstimatedIncurred
MAARIANARs 38.00 crRs 22.23 cr
-NARs 2.00 crRs 62.73 lakh

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM K RAO
ArchitectM.K.Rao & Associates
ArchitectEdifice Consultant
EngineerB Yusuf Amin
EngineerN D Rathod & Associates
Chartered AccountantISHAQ LAKKADGHAT & CO.
Chartered AccountantLAKKADGHAT & CO
Chartered AccountantH P Jadeja & Associates
Chartered AccountantPratik Makwana & Associates
Chartered AccountantAnita A Yadav & Associates
PartnerRole in project
LAKADAWALA DEVELOPERS PVT. LTD.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900009558Jan 2021 → Dec 2024

Reason as filed by the promoterAs you are aware that last year was very tough phase for every person especially for Land Developers and Builders all work was halted due to pandemic since working labour to material supplier and all the department / Authorities who are related with this activity were shut down for near about 1 whole year. Our proposal file was put up for concessions and further approvals as per DCPR 2034 to Hon. C.E.O. (SRA) but due to some issues and policy matters the same was on hold till 2018. Last year 2020 we again processed the proposal file to Hon. C.E.O. (SRA) for approvals as per DCPR 2034 and got t

EA04122518531Jan 2021 → Dec 2029

Reason as filed by the promoterDue to the delay in the Environment, Aviation and other permissions from the competent Authority for the Sale Building, further construction was stopped. Permission was expected in due course, hence the extension of the project is required.

Litigation declared4

CaseCourtStatus
531/2016STATE CONSUMERPENDING
729/2015STATE CONSUMERPENDING
276/2013NCBRC NEW DELHIPENDING
729/2015STATE CONSUMEROngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000001275PAWANKUMAR GUPTALAKADWALA DEVELOPERS PVT LTD07/11/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Q2 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 1File: FORM 1 Q3 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 1File: FORM 1 Q4 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 1File: FORM 1 Q1 26-27 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 2File: Form 2 Q2 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 2File: FORM 2 Q3 25-26 Maaria Annexe New.pdf12 Aug 2026
Withdrawal Update Form 2File: FORM 2 Q4 25-26 Maaria Annexe New.pdf12 Aug 2026
Withdrawal Update Form 2File: FORM 2 Q1 26-27 Maaria Annexe New.pdf12 Aug 2026
Withdrawal Update Form 3File: FORM 3 Q2 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 3File: FORM 3 Q3 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 3File: FORM 3 Q4 25-26 Maaria Annexe.pdf12 Aug 2026
Withdrawal Update Form 3File: FORM 3 Q1 26-27 Maaria Annexe.pdf12 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A 25-26 Maaria Annexe.pdf12 Aug 2026
Form 2A (FY 2020-2021)File: FORM-2A FY-2020-21.pdf20 Nov 2025
Form 2A (FY 2021-2022)File: FORM-2A FY-2021-22.pdf20 Nov 2025
Form 2A (FY 2022-2023)File: FORM-2A FY-2022-23.pdf20 Nov 2025
Form 2A (FY 2023-2024)File: FORM-2A FY-2023-24.pdf20 Nov 2025
Form 1File: Form 1 Q4 20-21.pdf19 Nov 2025
Form 2File: Form 2 Q4 20-21 new.pdf19 Nov 2025
Form 3File: Form 3 Q4 20-21.pdf19 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 20-21.pdf19 Nov 2025
Form 1File: Form 1 Q1 24-25.pdf18 Nov 2025
Form 2File: Form 2 Q1 24-25.pdf18 Nov 2025
Form 3File: Form 3 Q1 FY 24-25.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q1 24-25.pdf18 Nov 2025
Form 1File: Form 1 Q2 24-25.pdf18 Nov 2025
Form 2File: Form 2 Q2 24-25.pdf18 Nov 2025
Form 3File: Form 3 Q2 FY 24-25.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q2 24-25.pdf18 Nov 2025
Form 1File: Form 1 Q3 24-25.pdf18 Nov 2025
Form 2File: Form 2 Q3 24-25.pdf18 Nov 2025
Form 3File: Form 3 Q3 FY 24-25.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q3 24-25.pdf18 Nov 2025
Form 1File: Form 1 Q4 24-25.pdf18 Nov 2025
Form 2File: Form 2 Q4 24-25.pdf18 Nov 2025
Form 3File: Form 3 Q4 FY 24-25.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q4 24-25.pdf18 Nov 2025
Form 1File: Form 1 Q1 25-26.pdf18 Nov 2025
Form 2File: Form 2 Q1 25-26.pdf18 Nov 2025
Form 3File: Form 3 Q1 25-26.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q1 25-26.pdf18 Nov 2025
Form 1File: Form 1 Q4 23-24.pdf18 Nov 2025
Form 2File: Form 2 Q4 23-24.pdf18 Nov 2025
Form 3File: Form 3 Q4 23-24.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 23-24.pdf18 Nov 2025
Form 1File: Form 1 Q4 22-23.pdf18 Nov 2025
Form 2File: Form 2 Q4 22-23.pdf18 Nov 2025
Form 3File: Form 3 Q4 22-23.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 22-23.pdf18 Nov 2025
Form 1File: Form 1 Q4 21-22.pdf18 Nov 2025
Form 2File: Form 2 Q4 21-22.pdf18 Nov 2025
Form 3File: Form 3 Q4 FY 21-22.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 21-22.pdf18 Nov 2025
Form 1File: Form 1 Q1 23-24.pdf18 Nov 2025
Form 2File: Form 2 Q1 23-24.pdf18 Nov 2025
Form 3File: Form 3 Q1 23-24.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q1 23-24.pdf18 Nov 2025
Form 1File: Form 1 Q2 23-24.pdf18 Nov 2025
Form 2File: Form 2 Q2 23-24.pdf18 Nov 2025
Form 3File: Form 3 Q2 23-24.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q2 23-24.pdf18 Nov 2025
Form 1File: Form 1 Q3 23-24.pdf18 Nov 2025
Form 2File: Form 2 Q3 23-24.pdf18 Nov 2025
Form 3File: Form 3 Q3 23-24.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q3 23-24.pdf18 Nov 2025
Form 1File: Form 1 Q4 17-18.pdf18 Nov 2025
Form 2File: Form 2 Q4 17-18.pdf18 Nov 2025
Form 3File: Form 3 Q4 17-18.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 17-18.pdf18 Nov 2025
Form 1File: Form 1 Q4 18-19.pdf18 Nov 2025
Form 2File: Form 2 Q4 18-19.pdf18 Nov 2025
Form 3File: Form 3 Q4 18-19.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 18-19.pdf18 Nov 2025
Form 1File: Form 1 Q4 19-20.pdf18 Nov 2025
Form 2File: Form 2 Q4 19-20.pdf18 Nov 2025
Form 3File: Form 3 Q4 19-20.pdf18 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory -Q4 19-20.pdf18 Nov 2025
Form 2A (FY 2024-2025)File: Form-2A -2024-25-Promoter.pdf18 Nov 2025
Form 2A (FY 2019-2020)File: Form-2A-2019-20 Promoter.pdf18 Nov 2025
Form 5 (FY 2017-2018)File: Form 5-FY-1718.pdf18 Nov 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MAARIAM APARTMENTISMAIL CURTLEY ROAD GHOGHARI MOHALLA MUMBAI 400003112CompletedFeb 2004Late, Feb 2005

Keep MAARIA ANNEXE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmMAARIA ANNEXECompleted 6Lapsed / revoked 12Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: LAKADAWALA DEVELOPERS PVT LTD

LAKADAWALA DEVELOPERS PVT LTD has 4 registrations on MahaRERA, including LAKADAWALA SOLITAIRE and MAARIA ANNEXE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if MAARIA ANNEXE is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAARIA ANNEXE?

The registered promoter entity is LAKADAWALA DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAARIA ANNEXE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAARIA ANNEXE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAARIA ANNEXE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAARIA ANNEXE?

The professionals named in the filing: Architect: M K RAO; Architect: M.K.Rao & Associates; Architect: Edifice Consultant; Engineer: B Yusuf Amin; Engineer: N D Rathod & Associates; Chartered Accountant: ISHAQ LAKKADGHAT & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAARIA ANNEXE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAARIA ANNEXE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAARIA ANNEXE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.