ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / LOTUS RESIDENCY

Registered No litigation declared Residential / Group Housing project

LOTUS RESIDENCY

By VRINDAVAN CONSTRUCTIONS NAGPUR

RG-MH-93557 · RERA P50500056329 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Internal walls, 75%
17 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

LOTUS RESIDENCY is a Residential / Group Housing project by VRINDAVAN CONSTRUCTIONS NAGPUR in Nagpur, Maharashtra, registered with MahaRERA as P50500056329 on 29 May 2024. Possession is promised by 15 Oct 2027. 5 of the 22 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameLOTUS RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • West high Court Road
    • Laxminagar
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440022
  • Pincode440022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500056329
  • ReraGenie IDRG-MH-93557

Builder

  • NameVRINDAVAN CONSTRUCTIONS NAGPUR
  • Entity typeOthers
  • Named personsSIDDHANT SACHIN CHAWARE, VAIBHAV BANSISA MAHAJAN
  • Other registrations3 more →

Key dates

this monthRegisteredMay 2024PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 May 2024
  • Promised completion15 Oct 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed83 files

Current status

23%5 of 22 units booked
23.5%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LOTUS RESIDENCYNA121122022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.

LOTUS RESIDENCY: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes15%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership14

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area780 sq m
Land owned byNot the promoter
Named landowners14
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Aug 2025
LandownerVillageDistrict
Vijar kumar RajuNagpur (M Corp.)Nagpur
Ajay Kumar RajuNagpur (M Corp.)Nagpur
Arvind Devidasji LohiNagpur (M Corp.)Nagpur
Anil Rajpal KedarNagpur (M Corp.)Nagpur
Surendra kumar Bishen SinghNagpur (M Corp.)Nagpur
Anil Manoharrao GirnaleNagpur (M Corp.)Nagpur
Archana Anil GirnaleNagpur (M Corp.)Nagpur
Saee Ajay GhareNagpur (M Corp.)Nagpur
Suresh Gopal PatkiNagpur (M Corp.)Nagpur
Dipak Shankarrao BansodNagpur (M Corp.)Nagpur
Haribhau Isanji RangariNagpur (M Corp.)Nagpur
Pramod Wamanrao JoshiNagpur (M Corp.)Nagpur
Bhushan Govind SagdeoNagpur (M Corp.)Nagpur
Sanjay Kumar RajuNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION (NMC)
Permissible FSI3383.9
Proposed, not sanctioned2,772 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Shubham Appartment, Nazul Plot No.4, Mouza Jaripatka, Talwar Marg, Byramji Town, Nagpur, Maharashtra.440013
Estimated costRs 8.67 cr
Cost incurredRs 2.04 cr
Work done23.5%
BuildingWingEstimatedIncurred
LOTUS RESIDENCYNARs 8.67 crRs 2.04 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR ATHARVA GUPTA
EngineerJW CONSULTANT LLP
EngineerSACHIN MANOJ JAISWAL
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantSUMIT SANTOSH AGRAWAL & ASSOCIATES
PartnerRole in project
VRINDAVAN CONSTRUCTIONS NAGPUR-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Oct 2027

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 LOTUS RESIDENCY JUN-2026.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM-1 LOTUS RESIDENCY JUN-2026.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 LR March 26.pdf18 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A MARCH 2026.pdf12 May 2026
Withdrawal Update Form 1File: Form 1 LR 31-3-26.pdf19 Apr 2026
Withdrawal Update Form 2File: FORM 2 LOTUS RESIDENCY MARCH 2026.pdf19 Apr 2026
Withdrawal Update Form 3File: Form 3 LR March 26.pdf19 Apr 2026
Withdrawal Update Form 1File: Form-1 DEC-25 lotus residency.pdf18 Jan 2026
Withdrawal Update Form 2File: FORM-2 LOTUS RESIDENCY.pdf18 Jan 2026
Withdrawal Update Form 3File: FORM-3 DEC-25 LOTUS RESIDENCY.pdf18 Jan 2026
Withdrawal Update Form 1File: form 1 Lotus Residency sept 25.pdf13 Oct 2025
Withdrawal Update Form 2File: form 2 lotus residency sept 25.pdf13 Oct 2025
Withdrawal Update Form 3File: form 3 Lotus residency sep 2025.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Lotus Residency (24-25).pdf12 Oct 2025
Withdrawal Update Form 1File: FORM-1.pdf21 Aug 2025
Withdrawal Update Form 2File: FORM-2.pdf21 Aug 2025
Withdrawal Update Form 3File: FORM-3.pdf21 Aug 2025
Form 1File: FORM-1 JUN-24.pdf20 Aug 2025
Form 2File: FORM-2 JUN-24.pdf20 Aug 2025
Form 3File: FORM-3 JUN-24.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD JUN-24.pdf20 Aug 2025
Form 1File: FORM-1 SEPT-24.pdf20 Aug 2025
Form 2File: FORM-2 SEPT-24.pdf20 Aug 2025
Form 3File: FORM-3 SEPT-24.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD SEPT-24.pdf20 Aug 2025
Form 1File: FORM-1 DEC-24.pdf20 Aug 2025
Form 2File: FORM-2 DEC-24.pdf20 Aug 2025
Form 3File: FORM-3 DEC-24.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-24.pdf20 Aug 2025
Withdrawal Update Form 1File: FORM-1.pdf20 Aug 2025
Withdrawal Update Form 2File: FORM-2.pdf20 Aug 2025
Withdrawal Update Form 3File: FORM-3.pdf20 Aug 2025
Form 1File: FORM-1 MAR-25.pdf16 Jul 2025
Form 2File: FORM-2 MAR-25.pdf16 Jul 2025
Form 3File: FORM-3 MAR-25.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MAR-25.pdf16 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Lotus Residency_March-25.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_LOTUS RESIDENCY_MAR 25.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_INVENTORY_P50500056329_LOTUS RESIDENCY 31-3-25.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Lotus Residency_Dec-2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Lotus Residency_Dec-2024.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Lotus Residency_Dec-2024.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventery Details of LOTUS RESIDENCY_SEP_2024.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 LOTUS RESIDENCY_SEP_2024.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 LOTUS RESIDENCY_SEP_2024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 LOTUS RESIDENCY_SEP_2024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Lotus Residency Form 2 June 2024.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Lotus Residency June 2024.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LOTUS RESIDECY_FORM-3_JUNE-24.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lotus Residency Form 1 June 2024.pdf13 Jul 2024
Building plan approvalFile: SANCTION MAPV1.pdf20 May 2024
Layout approvalFile: SANCTION MAPV1.pdf20 May 2024
Copy of Layout Approval (in case of layout)File: SANCTION MAPV1.pdf20 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SANCTION MAPV1.pdf20 May 2024
Proforma of Agreement for saleFile: ATS- LOTUS RESIDENCY.pdf20 May 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Agreement to Sale.pdf20 May 2024
Declaration in FORM BFile: Lotus Residency_Form-B_Promoter.pdf10 May 2024
Declaration in FORM BFile: Lotus Residency_Form-B_Land Owner.pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3_lotus.pdf10 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Vrindavan Format A.pdf10 May 2024
PAN CardFile: 1 PAN Card (22).pdf9 May 2024
Copy of the legal title reportFile: TITLE_REPORT-RERA LOTUS RESIDENCY (1)_compressed.pdf9 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate Finance.pdf9 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate Legal.pdf9 May 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate Finance.pdf9 May 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate Legal.pdf9 May 2024
Commencement Certificates / NA Order for plotted developmentFile: pERMIT.pdf9 May 2024
Declaration about Commencement CertificateFile: Decleration about Commencemnt Certificate.pdf9 May 2024
CERSAI detailsFile: Cersai Declaration_Lotus Residency.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Vaibhav.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Rashi.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Siddhant.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Co promoter.pdf9 May 2024
Proforma of Allotment letterFile: Allotment letter (3).pdf9 May 2024
Deviation Report with respect to Allotment letterFile: Deviation report Allotment Letter.pdf9 May 2024
Other - LegalFile: harshada redevelopment agreement registered.pdf9 May 2024
Other - LegalFile: harshada POA registered.pdf9 May 2024
Other - FinanceFile: harshada POA registered.pdf9 May 2024

How this compares with Nagpur

23%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LOTUS RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Laxminagar2,800+ in Nagpur

2 kmLOTUS RESIDENCYCompleted 44Lapsed / revoked 22Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 121 registered projects within 2 km.

Builder: VRINDAVAN CONSTRUCTIONS NAGPUR

VRINDAVAN CONSTRUCTIONS NAGPUR has 4 registrations on MahaRERA, including LE GRANDE ROYALE and ROYALE REGENCY-KALIDAS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if LOTUS RESIDENCY is delayed beyond 15 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LOTUS RESIDENCY?

The registered promoter entity is VRINDAVAN CONSTRUCTIONS NAGPUR, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LOTUS RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LOTUS RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LOTUS RESIDENCY?

The professionals named in the filing: Architect: AR ATHARVA GUPTA; Engineer: JW CONSULTANT LLP; Engineer: SACHIN MANOJ JAISWAL; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: SUMIT SANTOSH AGRAWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LOTUS RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.