ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / LOTUS LEGACY

Registration approved No litigation declared Residential/Group Housing project

LOTUS LEGACY

By ATHARVA BUILDERS AND DEVELOPERS

RG-KA-18331 · RERA PRM/KA/RERA/1257/334/PR/150725/007929 · Last updated on RERA Karnataka portal: 1 Jul 2025

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2030Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 66 documents Report an error

LOTUS LEGACY is a Residential/Group Housing project by ATHARVA BUILDERS AND DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/150725/007929 on 15 Jul 2025. Possession is promised by 30 Aug 2030.

At a glance

Project

  • NameLOTUS LEGACY
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575003
  • Pincode575003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/150725/007929
  • ReraGenie IDRG-KA-18331

Builder

  • NameATHARVA BUILDERS AND DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ABRFA5785G1ZR
  • Authorized SignatoryDHANRAJ KUMAR
  • Other registrations6 more →
  • Declared earlier projects10 →

Key dates

this monthRegisteredJul 2025PromisedAug 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Jul 2025
  • Promised completion30 Aug 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LOTUS LEGACY---22022

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 1 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 1 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasYes-
Water and SanitationYes-
Air ConditioningYes-
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area779 sq m
Named landowners5
LandownerVillageDistrict
DHANRAJ KUMAR--
SAMPATH KUMAR SHETTY T--
JITHENDRA S KOTTARY--
RAJINI JENNIFER PATRAO--
VIJAYALAXMI ARAVIND SHENOY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.46 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 12.24 cr-
Payment of taxesRs 1.02 cr-
On-site expenditure-Consultants FeesRs 10.00 lakh-
On-site expenditure-Site OverheadRs 5.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRIYANKA GANESH SUVARNA
EngineerDHANRAJ
Chartered AccountantSRINIVAS UDUPA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed66

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/150725/007929 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
renewed Engineer license certificate with self attestedFile: ENGINEER dhanraj license.pdf1 Jul 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: BALANCE SHEET merged.pdf17 Jun 2025
sources of fund to complete the projectFile: Sources of Fund.pdf17 Jun 2025
MR showing flow of titles in favor of landownerFile: MR LEGACY.pdf17 Jun 2025
EC from 17/3/2024 to till dateFile: ECC-11062025-2318863.pdf17 Jun 2025
title deedFile: SALE DEED NON AGRICULTURAL PROPRTY.pdf17 Jun 2025
Layout/Development/single plan approved letterFile: single site (2).pdf17 Jun 2025
Layout/Development/ single approval planFile: single site (2).pdf17 Jun 2025
Building plan Blue printFile: PLAN.pdf17 Jun 2025
Extract of Master Plan proposed area with consent authority seal and signatureFile: PLAN.pdf17 Jun 2025
Village MapFile: village map_merged.pdf17 Jun 2025
Extract of ZR copy with consent authority seal and signatureFile: Zonal.pdf17 Jun 2025
Each floor plan and section planFile: FLOOR PLANS_merged.pdf17 Jun 2025
KSPCB NOCFile: STP mandatory notification by GoK.pdf17 Jun 2025
Common Area Allotted to Association detailsFile: COMMON AREA AMENITIES.pdf17 Jun 2025
renewed Engineer license certificateFile: engineer license.pdf17 Jun 2025
brief estimated cost of construction, certified by the registered Civil EngineerFile: ABSTRACT ESTIMATE Lotus legacy (2).pdf17 Jun 2025
project section 3(1) notarised affidavitFile: NOTARIZED AFFIDAVIT AFT RERA LEGACY.pdf17 Jun 2025
STP/Septic Tank, Soak pit, and sewer line drawing certified by the EngineerFile: STP mandatory notification by GoK.pdf17 Jun 2025
e Land cost calculation sheet as per the guidance valueFile: LAND COST guidance value.pdf17 Jun 2025
the source of water supply to the projectFile: WELL POINT.pdf17 Jun 2025
RTC, survey 117/1A , 117/1A-
Mutation, survey 117/1A , 117/1A-
Encumbrance Certificate, survey 117/1A , 117/1A-
Conversion/Alienation Order, survey 117/1A , 117/1A-
Sale/Title/Gift Deed, survey 117/1A , 117/1A-
Khatha, survey 117/1A , 117/1A-
Registration CertificateFile: Form C FIRM REG NO.pdf-
GST CertificateFile: GST Certificate 1.pdf-
Partnership DeedFile: Partership Deed - Atharva.PDF-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM 1 CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: Form-2, Architect certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3, Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: AFFIDAVIT CUM DECLARATION.pdf-
Balance Sheet 2023 - 2024File: P&L BALANCE SHEET_23-24.pdf-
Balance Sheet 2022 - 2023File: P&L BALANCE SHEET_22-23.pdf-
Balance Sheet 2021 - 2022File: P&L BALANCE SHEET 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: P&L BALANCE SHEET_23-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P&L BALANCE SHEET_22-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L BALANCE SHEET 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ACK_2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ACK_2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ACK 21-22.pdf-
LICENSE (1)-
PLAN-
FLOOR PLANS_merged-
STRUCTURAL STABILITY LEGACY-
SPECIFICATIONS (2)-
BROCHURE_11zon-
GIFT DEED DANAPATRA LEGACY (1)-
New Agreement -(Rera)LEGACY-
ALLOTMENT LETTER LEGACY-
FORM B-
AFFIDAVIT CUM DECLARATION-
JOINT AFFIDAVIT CUM DECLARATION-
ADVOCATE SEARCH REPORT - LEGACY-
MESCOM NOC-
WATER NOC legacy-
FIRE NOC-

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date3 under way, not due yet2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
ATHARVA KRISHVIMANGALORE THOTA Village of Mangalore Taluk, within JEPPU Ward of Mangalore City Corporation and within the registration Sub-District of Mangalore CityOngoingDec 2027Not due yet
ATHARVA AIKYADerebail Village of Mangalore Taluk within limits of Mangalore City Corporation, and within registration Sub District of Mangalore CityOngoingNov 2027Not due yet
ATHARVA KANISHKABEJAI, KAPIKAD, MANGALOREOngoingDec 2026Not due yet
ATHARVA PADMA KUSHABOLOOR 'B' VILLAGE URWA MARIGUDI MAIN ROAD OF MANGALORE TALUK WITHIN AND WITHIN NO. 26 DEREBAIL WARD OF MANGALORE CITY CORPORATION, WITHIN THE REGISTRATION SUB DISTRICT OF MANGALORE CITY, DAKSHINA KANNADA DISTRICTOngoingJul 2025Not delivered
ATHARVA KRISHNI87 B KADRI VILAAGE, ANEGUNDI BEJAI, MANGALORE 575004Completed-No date filed
ATHARVA GLORYATTAVARA VILLAGE PANDESHWARA WARD OF MANGALORE CITY CORPORATION WITHIN REGISTRATION SUB DISTRICT OF MANGALORE CITYCompleted-No date filed

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep LOTUS LEGACY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmLOTUS LEGACYOther 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: ATHARVA BUILDERS AND DEVELOPERS

Atharva builders and developers has 7 registrations on RERA Karnataka, including Atharva Kanishka and Atharva Krishvi. Its filings declare 10 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if LOTUS LEGACY is delayed beyond 30 Aug 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LOTUS LEGACY?

The registered promoter entity is ATHARVA BUILDERS AND DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ABRFA5785G1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LOTUS LEGACY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LOTUS LEGACY?

The professionals named in the filing: Architect: PRIYANKA GANESH SUVARNA; Engineer: DHANRAJ; Chartered Accountant: SRINIVAS UDUPA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LOTUS LEGACY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS LEGACY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS LEGACY to a free account