ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / LOTUS KRISH

Registration approved Residential/Group Housing project

LOTUS KRISH

By SAMPATH KUMAR SHETTY T

RG-KA-10270 · RERA PRM/KA/RERA/1257/334/PR/180516/001712

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 23 documents Report an error

LOTUS KRISH is a Residential/Group Housing project by SAMPATH KUMAR SHETTY T in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180516/001712 on 16 May 2018. Possession is promised by 30 Jun 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameLOTUS KRISH
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/180516/001712
  • ReraGenie IDRG-KA-10270

Builder

  • NameSAMPATH KUMAR SHETTY T
  • Entity typePartnership Firm
  • Authorized SignatorySAMPATH KUMAR SHETTY T
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2018First promiseSep 2020Revised toJun 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 May 2018
  • Promised completion30 Jun 2021
  • Revised completionRevised to 30 Jun 2021 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LOTUS KRISH-----42

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,882 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.82 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2020 → Jun 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed23

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180516/001712 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: REGISTRATION PARTINERSHIP.pdf-
License Copy-
LICENCE PLAN-
LICENCE PLAN-
AGREEMENT FOR SALE-
Sale Deed (1)-
MUDA APPROVAL-
MUDA APPROVAL-
ALLOTEMENT LETTER PDF-
ENCUMBRANCE CERTIFICATE-
Khatha-
Sale Of Deed 1%-
Sale Deed (1)-
Conversion Copy-
Unnamed document-
LICENCE PLAN-
Legal Scrutiny-
AFFIDAVIT-min-
Tower Excel SheetFile: LOTUS KRISH EXCELL.xlsx-
Occupancy CertificateFile: Complition Certificate - Krish.PDF-
Architect certificate for having completed the work(in format no 5)File: Krish Architect Certificate- Q4-2020-21.PDF-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit - Krish.PDF-
Occupancy Certificate received 18.03.2021File: Complition Certificate - Krish.PDF-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep LOTUS KRISH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmLOTUS KRISHOther 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 95 registered projects within 2 km.

Builder: SAMPATH KUMAR SHETTY T

SAMPATH KUMAR SHETTY T has 2 registrations on RERA Karnataka, including SPRING DALE and LOTUS KRISH. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if LOTUS KRISH is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LOTUS KRISH?

The registered promoter entity is SAMPATH KUMAR SHETTY T, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LOTUS KRISH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in LOTUS KRISH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS KRISH. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS KRISH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.