ReraGenieLog inGet a buyer report

Home / Browse projects / Wardha, Maharashtra / LITTLE EARTH - UNIT 7

Completed No litigation declared Plotted project

LITTLE EARTH - UNIT 7

By VASTU LAND DEVELOPERS AND BUILDERS

RG-MH-30439 · RERA P50400049784 · Last updated on MahaRERA portal: 30 Jan 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
45 of 45Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

LITTLE EARTH - UNIT 7 is a Plotted project by VASTU LAND DEVELOPERS AND BUILDERS in Wardha, Maharashtra, registered with MahaRERA as P50400049784 on 24 Feb 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. 0 of the 45 units on this registration are recorded sold or booked.

At a glance

Project

  • NameLITTLE EARTH - UNIT 7
  • TypePlotted
  • Location
    • SURVEY NO 173
    • MAUJA PAVNAR
    • Pavnar
    • Wardha
    • 442111
  • Pincode442111
  • RERA no.P50400049784
  • ReraGenie IDRG-MH-30439

Builder

  • NameVASTU LAND DEVELOPERS AND BUILDERS
  • Entity typePartnership
  • PartnersSANJAY PUNDLIKRAO MANMODE, MOHAN PUNDLIKRAO MANMODE, SHARAD RANGANATH GAIKWAD, GANESH PARSHURAM ATKAR, ASHISH SHARADRAO DHANDE
  • Other registrations3 more →
  • Completed4 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Feb 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed48 files

Current status

0%0 of 45 units booked

Figures as on 30 Jan 2024, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities18

As on 30 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
OTHERSYes100%
PANNEL GATEYes100%
WALL COMPOUNDYes100%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,671 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VASTU LAND DEVELOPERS AND BUILDERSWardha (M Cl)Wardha

Approvals and building plan

Permissible FSI5670.94

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWARD NO 7 NEW, HOUSE NO 228, NAZUL SHEET NO 50 BALAJI TOWER GANDHI NAGAR ARVI ROAD WARDHA 442001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND KEDAR
EngineerMILIND KEDAR
Chartered AccountantDARSHAN WAKHARIYA
PartnerRole in project
VASTU LAND DEVELOPERS AND BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Oct 2023

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM1 31032023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 FORM 1 30062023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 FORM 1 30092023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form 1 04102023.pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2_31032023.pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2_30062023.pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2_30092023.pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2_04102023.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_06_09_2023.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_08_12_2023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 20012023 compressed.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 300623 compressed.pdf4 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 200123compressed.pdf4 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 300623 compressed.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ 06_09_2023_Little earth unit 7.pdf9 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Little Earth unit 7.pdf9 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_08-09-2023_Little Earth unit 7.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_04102023.pdf4 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_04102023.pdf4 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31032023.pdf4 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_UNIT 7.pdf19 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION_LOCAL AUTHORITY.pdf4 Oct 2023
Copy of the legal title reportFile: FORMAT A _SEARCH.pdf21 Feb 2023
Copy of the legal title reportFile: SEARCH PART 2.pdf21 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest _ ASHISH.pdf15 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest _ Ganesh.pdf15 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest _ Mohan.pdf15 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest _ Sanjay.pdf15 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest,_ Sharad.pdf15 Feb 2023
Layout approvalFile: SANCTIONED MAP.pdf1 Feb 2023
Building plan approval or NA orderFile: NA ORDER COPY.pdf1 Feb 2023
PAN CardFile: PAN CARD_FIRM.PDF1 Feb 2023
Details of encumbrances concerned to FinanceFile: DECLARATION_NO ENCUMBRANCE.pdf1 Feb 2023
Details of encumbrances concerned to LegalFile: DECLARATION_NO ENCUMBRANCE.pdf1 Feb 2023
Copy of Layout Approval (in case of layout)File: SANCTIONED MAP.pdf1 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER COPY.pdf1 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER COPY.pdf1 Feb 2023
Declaration about Commencement CertificateFile: FORMAT D.pdf1 Feb 2023
Declaration in FORM BFile: FORM B.pdf1 Feb 2023
CERSAI detailsFile: DECLARATION_CERSAI.pdf1 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_200259201739_For_Asset_Based_Search_01_02_2023_15_58_46_087.pdf1 Feb 2023
Disclosure of sold/ booked inventoryFile: BOOK SOLD INVENTORY.pdf1 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Feb 2023
Proforma of Agreement for saleFile: AGREEMENT TO SALE.pdf1 Feb 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf1 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION_BANK.pdf1 Feb 2023
Deviation Report with respect to Allotment letterFile: DECLARATION_ NO DEVIATION PROFORMA OF ALLOTMENT LETTER.pdf1 Feb 2023
Deviation Report with respect to model copy of AgreementFile: DECLARATION_NO DEVIATION PROFORMA OF AGREEMENT TO SALE.pdf1 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
VASTU ROYAL PARKSURVEY NO 222 AT SAWANGI MEGHE WARDHACompletedDec 2018Dec 2018

How this compares with Wardha

0%of this project is bookeddistrict median 0%
5%of Wardha projects moved their completion datethis one has not
18%of Wardha registrations have lapsed or been cancelledthis one is completed

Computed across the 290+ Wardha projects on ReraGenie, from their own filings.

Keep LITTLE EARTH - UNIT 7 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SURVEY NO 173, MAUJA PAVNAR290+ in Wardha

Builder: VASTU LAND DEVELOPERS AND BUILDERS

VASTU LAND DEVELOPERS AND BUILDERS has 4 registrations on MahaRERA, including LITTLE EARTH UNIT - 6 and VASTU PARK. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Wardha district page.

Frequently asked questions

What are my rights if LITTLE EARTH - UNIT 7 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LITTLE EARTH - UNIT 7?

The registered promoter entity is VASTU LAND DEVELOPERS AND BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LITTLE EARTH - UNIT 7?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LITTLE EARTH - UNIT 7?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LITTLE EARTH - UNIT 7?

The professionals named in the filing: Architect: MILIND KEDAR; Engineer: MILIND KEDAR; Chartered Accountant: DARSHAN WAKHARIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LITTLE EARTH - UNIT 7?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LITTLE EARTH - UNIT 7. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LITTLE EARTH - UNIT 7 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.