Home / Browse projects / Pune, Maharashtra / LIFE MAXIMA PHASE 1

Registration lapsed No litigation declared Residential / Group Housing project

LIFE MAXIMA PHASE 1

By Pate Future Constructions LLP

RG-MH-08440 · RERA P52100002203 · Last updated on MahaRERA portal: 6 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
12 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 85%
2Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

LIFE MAXIMA PHASE 1 is a Residential / Group Housing project by Pate Future Constructions LLP in Pune, Maharashtra, registered with MahaRERA as P52100002203 on 31 Jul 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 36 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameLIFE MAXIMA PHASE 1
  • TypeResidential / Group Housing
  • Location
    • KIRKATWADI NANDOSHI ROAD
    • KIRKATWADI
    • Haveli
    • Pune
    • 411024
  • Pincode411024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002203
  • ReraGenie IDRG-MH-08440

Builder

  • NamePate Future Constructions LLP
  • Entity typePartnership
  • PartnersRAKESHKUMAR AGARWAL, RAMLAKHAN SHUKLA, PRAMOD WANI, NITIN DANGAT, LALIT AJGAONKAR, Amit Anil Jagtap, Sushant Mohan Jadhav
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live4 lapsed, de-registered or revoked

Key dates

40 months past promisethis monthRegisteredJul 2017First promiseJun 2020Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 29 Jun 2020)
  • Buildings3 building records
  • Documents filed66 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LIFE MAXIMA PHASE 1 BLDG C5NA110000
LIFE MAXIMA PHASE 1 BLDG C6NA110000
LIFE MAXIMA PHASE 1 BLDG C7NA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 6 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 85%.

LIFE MAXIMA PHASE 1 BLDG C575%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises68%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks69%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.69%
LIFE MAXIMA PHASE 1 BLDG C649%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.8%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
LIFE MAXIMA PHASE 1 BLDG C743%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure69%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 6 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes10%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Two Level ParkingYes0%

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered68
BuildingClosed/CoveredTotal
LIFE MAXIMA PHASE 1 BLDG C52222
LIFE MAXIMA PHASE 1 BLDG C61717
LIFE MAXIMA PHASE 1 BLDG C72929

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,015 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
RAMCHANDRA ALIAS CHANDRAKANT HAGAWANEKIRKATWADIPune
BALASAHEB HAGAWANEKIRKATWADIPune
RAOSAHEB HAGAWANEKIRKATWADIPune
SHEKHAR HAGAWANEKIRKATWADIPune

Approvals and building plan

Permissible FSI9614.38
Proposed, not sanctioned9,614 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANKUR ASSOCIATES ARCH PRAKASH KULKARNI
EngineerJW CONSULTANTS ER UMESH JOSHI
PartnerRole in project
Pate Future Constructions LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002006Jun 2020 → Jun 2020

Reason as filed by the promoterThere is delay in the completion of the project due to following reasons which are beyond our direct control. 1. After Implementation of GST from July 2017 and repeated changes in the applicable provisions to real estate developers, lot of material orders had to be revised and reworked from time to time e.g. Lift (major long haul item), this has adversely affected the speed of our site work. 2. On the sale side, there is a slowdown in the demand for real estate after the implementation of GST and demonetization, resulting in lower volume of booking and sale for the project. With the revised re

EXT52100008715Jun 2020 → Dec 2022

Reason as filed by the promoterThe erstwhile Promoter raised construction finance from PNB Housing Finance Limited. Whereas the erstwhile Promoter was unable to service the loan repayment on time due to slow sales velocity and inadequate working capital due to which Project got stalled for some time. The erstwhile Promoter agreed to transfer majority stake to new incoming Partners. Accordingly, they have obtained customers' consents and submitted the Proposal to MAHA RERA and, therefore, have received approval/permission from Hon. Authority U/sec. 15 on 28/11/2020 for induction of three new members as partners in the Projec

Litigation declared1

CaseCourtStatus
1752/2014/2014PUNE CIVIL SENIOR DIVISION COURTDEVELOPER NOT PARTY AWAITING SUMMONS

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000228476Skyi Property Ventures LLPMandar Sharad Bapat13/03/2023
CC005000000259289Yogesh Bhagwan MahatmeSUSHNT JADHAV/NILESH PATE16/08/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Sep 2022

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: C5.pdf6 Apr 2023
Building plan approvalFile: C5-1.pdf6 Apr 2023
Building plan approvalFile: C5-2.pdf6 Apr 2023
Building plan approvalFile: C5-3.pdf6 Apr 2023
Building plan approvalFile: C6.pdf6 Apr 2023
Building plan approvalFile: C6-1.pdf6 Apr 2023
Building plan approvalFile: C6-2.pdf6 Apr 2023
Building plan approvalFile: C6-3.pdf6 Apr 2023
Building plan approvalFile: C7.pdf6 Apr 2023
Building plan approvalFile: C7-1.pdf6 Apr 2023
Building plan approvalFile: C7-3.pdf6 Apr 2023
Layout approvalFile: Layout.pdf6 Apr 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf6 Apr 2023
Building Plan Approval (IOD)File: C5.pdf6 Apr 2023
Building Plan Approval (IOD)File: C5-1.pdf6 Apr 2023
Building Plan Approval (IOD)File: C5-2.pdf6 Apr 2023
Building Plan Approval (IOD)File: C5-3.pdf6 Apr 2023
Building Plan Approval (IOD)File: C6.pdf6 Apr 2023
Building Plan Approval (IOD)File: C6-1.pdf6 Apr 2023
Building Plan Approval (IOD)File: C6-2.pdf6 Apr 2023
Building Plan Approval (IOD)File: C6-3.pdf6 Apr 2023
Building Plan Approval (IOD)File: C7.pdf6 Apr 2023
Building Plan Approval (IOD)File: C7-1.pdf6 Apr 2023
Building Plan Approval (IOD)File: C7-3.pdf6 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter.pdf6 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Phase 1-Form 2A.pdf6 Apr 2023
Disclosure of sold/ booked inventoryFile: Phase 1-Sold Declaration.pdf6 Apr 2023
Certificates of CA (Form 3)File: Form 3-Life Maxima Ph1.pdf6 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Other organisation.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf6 Apr 2023
Proforma of Agreement for saleFile: Agreement Draft.pdf6 Apr 2023
Other - TechnicalFile: Self Declaration.pdf6 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: C5.pdf16 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH- FORM 1-LIFE MAXIMA PHASE 1.pdf12 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG- FORM 2-LIFE MAXIMA PHASE1.pdf12 Nov 2022
Details of encumbrances concerned to LegalFile: Phase 1- encumbrance legal.pdf22 Sep 2022
Declaration about Commencement CertificateFile: Phase 1-CC Declaration.pdf22 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Phase 1-Quality-19-20.pdf22 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Phase 1-Quality-20-21.pdf22 Sep 2022
CERSAI detailsFile: CERSAI_Star City.pdf22 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf22 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Phase 1-Bank account declaration.pdf22 Sep 2022
Deviation Report with respect to Allotment letterFile: Allotment letter deviation.pdf22 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Agreement deviation.pdf22 Sep 2022
Proforma of Allotment letterFile: Agreement Draft.pdf23 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: LIFE MAXIMA-PHASE I P52100002203_31-03-21.pdf31 Mar 2022
OtherFile: Change of Name Certificate.pdf20 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2018.pdf16 Dec 2019
Certificates of CA (Form 5)File: LIFE MAXIMA PHASE 1.pdf9 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: Life_Maxima NA.pdf25 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Maxima Form 1 Phase I 31st Dec 17.pdf8 Feb 2018
Copy of the legal title reportFile: LEGAL TITLE.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c5_Engg_Cert.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c6_Engg_Cert.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c7_Cert.pdf28 Jul 2017
Certificates of CA (Form 3)File: FORM 3 MAXIMA I.pdf28 Jul 2017
Proforma of Allotment letterFile: PDF Kirkitwadi rera agr C 5 6 7.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Life Maxima I Arch Letter.pdf20 Jul 2017
Declaration in FORM BFile: Life Maxima I Form B.pdf18 Jul 2017
Layout approvalFile: Life Maxima Layout.pdf4 Jul 2017
Building plan approvalFile: Life Maxima Layout.pdf4 Jul 2017
PAN CardFile: PAN Pate Furure Const LLP.pdf4 Jul 2017
Details of encumbrancesFile: Encumbrance.pdf4 Jul 2017
Copy of Layout Approval (in case of layout)File: Life Maxima Layout.pdf4 Jul 2017
Building Plan Approval (IOD)File: Life Maxima Layout.pdf4 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LIFE MAXIMA PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIRKATWADI13,700+ in Pune

Builder: Pate Future Constructions LLP

Pate Future Constructions LLP has 5 registrations on MahaRERA, including LIFE MAXIMA PHASE 1 and LIFE MAXIMA PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that LIFE MAXIMA PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LIFE MAXIMA PHASE 1 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LIFE MAXIMA PHASE 1?

The registered promoter entity is Pate Future Constructions LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LIFE MAXIMA PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LIFE MAXIMA PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LIFE MAXIMA PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LIFE MAXIMA PHASE 1?

The professionals named in the filing: Architect: ANKUR ASSOCIATES ARCH PRAKASH KULKARNI; Engineer: JW CONSULTANTS ER UMESH JOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LIFE MAXIMA PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LIFE MAXIMA PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LIFE MAXIMA PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.