LIFE MAXIMA PHASE 1
By Pate Future Constructions LLP
RG-MH-08440 · RERA P52100002203 · Last updated on MahaRERA portal: 6 Apr 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
LIFE MAXIMA PHASE 1 is a Residential / Group Housing project by Pate Future Constructions LLP in Pune, Maharashtra, registered with MahaRERA as P52100002203 on 31 Jul 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 36 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameLIFE MAXIMA PHASE 1
- TypeResidential / Group Housing
- Location
- KIRKATWADI NANDOSHI ROAD
- KIRKATWADI
- Haveli
- Pune
- 411024
- Pincode411024
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100002203
- ReraGenie IDRG-MH-08440
Builder
- NamePate Future Constructions LLP
- Entity typePartnership
- PartnersRAKESHKUMAR AGARWAL, RAMLAKHAN SHUKLA, PRAMOD WANI, NITIN DANGAT, LALIT AJGAONKAR, Amit Anil Jagtap, Sushant Mohan Jadhav
- Other registrations4 more →
- Completed1 of 5
- No longer live4 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Jul 2017
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 29 Jun 2020)
- Buildings3 building records
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LIFE MAXIMA PHASE 1 BLDG C5 | NA | 11 | 0 | 0 | 0 | 0 |
| LIFE MAXIMA PHASE 1 BLDG C6 | NA | 11 | 0 | 0 | 0 | 0 |
| LIFE MAXIMA PHASE 1 BLDG C7 | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 6 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 85%.
LIFE MAXIMA PHASE 1 BLDG C575%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 68% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 69% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 69% |
LIFE MAXIMA PHASE 1 BLDG C649%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 62% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 8% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LIFE MAXIMA PHASE 1 BLDG C743%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 69% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 6 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Two Level Parking | Yes | 0% |
Parking filed68
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| LIFE MAXIMA PHASE 1 BLDG C5 | 22 | 22 |
| LIFE MAXIMA PHASE 1 BLDG C6 | 17 | 17 |
| LIFE MAXIMA PHASE 1 BLDG C7 | 29 | 29 |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAMCHANDRA ALIAS CHANDRAKANT HAGAWANE | KIRKATWADI | Pune |
| BALASAHEB HAGAWANE | KIRKATWADI | Pune |
| RAOSAHEB HAGAWANE | KIRKATWADI | Pune |
| SHEKHAR HAGAWANE | KIRKATWADI | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANKUR ASSOCIATES ARCH PRAKASH KULKARNI |
| Engineer | JW CONSULTANTS ER UMESH JOSHI |
| Partner | Role in project |
|---|---|
| Pate Future Constructions LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere is delay in the completion of the project due to following reasons which are beyond our direct control. 1. After Implementation of GST from July 2017 and repeated changes in the applicable provisions to real estate developers, lot of material orders had to be revised and reworked from time to time e.g. Lift (major long haul item), this has adversely affected the speed of our site work. 2. On the sale side, there is a slowdown in the demand for real estate after the implementation of GST and demonetization, resulting in lower volume of booking and sale for the project. With the revised re
Reason as filed by the promoterThe erstwhile Promoter raised construction finance from PNB Housing Finance Limited. Whereas the erstwhile Promoter was unable to service the loan repayment on time due to slow sales velocity and inadequate working capital due to which Project got stalled for some time. The erstwhile Promoter agreed to transfer majority stake to new incoming Partners. Accordingly, they have obtained customers' consents and submitted the Proposal to MAHA RERA and, therefore, have received approval/permission from Hon. Authority U/sec. 15 on 28/11/2020 for induction of three new members as partners in the Projec
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1752/2014/2014 | PUNE CIVIL SENIOR DIVISION COURT | DEVELOPER NOT PARTY AWAITING SUMMONS |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000228476 | Skyi Property Ventures LLP | Mandar Sharad Bapat | 13/03/2023 |
| CC005000000259289 | Yogesh Bhagwan Mahatme | SUSHNT JADHAV/NILESH PATE | 16/08/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 22 Sep 2022
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: C5.pdf | 6 Apr 2023 |
| Building plan approvalFile: C5-1.pdf | 6 Apr 2023 |
| Building plan approvalFile: C5-2.pdf | 6 Apr 2023 |
| Building plan approvalFile: C5-3.pdf | 6 Apr 2023 |
| Building plan approvalFile: C6.pdf | 6 Apr 2023 |
| Building plan approvalFile: C6-1.pdf | 6 Apr 2023 |
| Building plan approvalFile: C6-2.pdf | 6 Apr 2023 |
| Building plan approvalFile: C6-3.pdf | 6 Apr 2023 |
| Building plan approvalFile: C7.pdf | 6 Apr 2023 |
| Building plan approvalFile: C7-1.pdf | 6 Apr 2023 |
| Building plan approvalFile: C7-3.pdf | 6 Apr 2023 |
| Layout approvalFile: Layout.pdf | 6 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C5.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C5-1.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C5-2.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C5-3.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C6.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C6-1.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C6-2.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C6-3.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C7.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C7-1.pdf | 6 Apr 2023 |
| Building Plan Approval (IOD)File: C7-3.pdf | 6 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter.pdf | 6 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Phase 1-Form 2A.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Phase 1-Sold Declaration.pdf | 6 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3-Life Maxima Ph1.pdf | 6 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Other organisation.pdf | 6 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5.pdf | 6 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf | 6 Apr 2023 |
| Proforma of Agreement for saleFile: Agreement Draft.pdf | 6 Apr 2023 |
| Other - TechnicalFile: Self Declaration.pdf | 6 Apr 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: C5.pdf | 16 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH- FORM 1-LIFE MAXIMA PHASE 1.pdf | 12 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG- FORM 2-LIFE MAXIMA PHASE1.pdf | 12 Nov 2022 |
| Details of encumbrances concerned to LegalFile: Phase 1- encumbrance legal.pdf | 22 Sep 2022 |
| Declaration about Commencement CertificateFile: Phase 1-CC Declaration.pdf | 22 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Phase 1-Quality-19-20.pdf | 22 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Phase 1-Quality-20-21.pdf | 22 Sep 2022 |
| CERSAI detailsFile: CERSAI_Star City.pdf | 22 Sep 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf | 22 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Phase 1-Bank account declaration.pdf | 22 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: Allotment letter deviation.pdf | 22 Sep 2022 |
| Deviation Report with respect to model copy of AgreementFile: Agreement deviation.pdf | 22 Sep 2022 |
| Proforma of Allotment letterFile: Agreement Draft.pdf | 23 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: LIFE MAXIMA-PHASE I P52100002203_31-03-21.pdf | 31 Mar 2022 |
| OtherFile: Change of Name Certificate.pdf | 20 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2018.pdf | 16 Dec 2019 |
| Certificates of CA (Form 5)File: LIFE MAXIMA PHASE 1.pdf | 9 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Life_Maxima NA.pdf | 25 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Maxima Form 1 Phase I 31st Dec 17.pdf | 8 Feb 2018 |
| Copy of the legal title reportFile: LEGAL TITLE.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c5_Engg_Cert.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c6_Engg_Cert.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: life_maxima_-_c7_Cert.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3 MAXIMA I.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: PDF Kirkitwadi rera agr C 5 6 7.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Life Maxima I Arch Letter.pdf | 20 Jul 2017 |
| Declaration in FORM BFile: Life Maxima I Form B.pdf | 18 Jul 2017 |
| Layout approvalFile: Life Maxima Layout.pdf | 4 Jul 2017 |
| Building plan approvalFile: Life Maxima Layout.pdf | 4 Jul 2017 |
| PAN CardFile: PAN Pate Furure Const LLP.pdf | 4 Jul 2017 |
| Details of encumbrancesFile: Encumbrance.pdf | 4 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Life Maxima Layout.pdf | 4 Jul 2017 |
| Building Plan Approval (IOD)File: Life Maxima Layout.pdf | 4 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep LIFE MAXIMA PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KIRKATWADI13,700+ in Pune
SHARADA MYRIA B AND C BUILDING
SHARADA ERECTORS PRIVATE LIMITED
Skyi City Centre
Skyi Property Ventures LLP
CHAITRANGAN PHASE II
DEDGE HOUSING DEVELOPMENT LLP
Mauli Park
MAITRI BUILDCON
Skyi Star City Phase VII
Skyi Property Ventures LLP
Skyi Star City Phase V
Skyi Property Ventures LLP
Builder: Pate Future Constructions LLP
Pate Future Constructions LLP has 5 registrations on MahaRERA, including LIFE MAXIMA PHASE 1 and LIFE MAXIMA PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that LIFE MAXIMA PHASE 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if LIFE MAXIMA PHASE 1 is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of LIFE MAXIMA PHASE 1?
The registered promoter entity is Pate Future Constructions LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in LIFE MAXIMA PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against LIFE MAXIMA PHASE 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for LIFE MAXIMA PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at LIFE MAXIMA PHASE 1?
The professionals named in the filing: Architect: ANKUR ASSOCIATES ARCH PRAKASH KULKARNI; Engineer: JW CONSULTANTS ER UMESH JOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in LIFE MAXIMA PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback