Home / Browse projects / Nashik, Maharashtra / Laxmi Heights Apartment

Registered No litigation declared Residential / Group Housing project

Laxmi Heights Apartment

By Gopi Kanayalal Allthakkar

RG-MH-70554 · RERA P51600051504 · Last updated on MahaRERA portal: 12 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
8 of 11Construction stages donefurthest along: Installation of Lifts, 50%
27 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Laxmi Heights Apartment is a Residential / Group Housing project by Gopi Kanayalal Allthakkar in Nashik, Maharashtra, registered with MahaRERA as P51600051504 on 23 Jun 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 2 of the 29 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameLaxmi Heights Apartment
  • TypeResidential / Group Housing
  • Location
    • Near Shree Gajanan Estate
    • Bankar Mala
    • CHEHEDI BK
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600051504
  • ReraGenie IDRG-MH-70554

Builder

  • NameGopi Kanayalal Allthakkar
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jun 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed73 files

Current status

7%2 of 29 units booked
96.0%Work done, per cost certificate

Figures as on 12 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Laxmi Heights ApartmentNA6529029

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 50%.

Laxmi Heights Apartment: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed85

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots85
Closed/Covered14
Open Space71

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area850 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jun 2025
LandownerVillageDistrict
Shrikant Shashikant BankarCHEHEDI BKNashik
Hirabai Shashikant BankarCHEHEDI BKNashik
Sandeep Shashikant BankarCHEHEDI BKNashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI2186.22
Proposed, not sanctioned2,186 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNashik Road Deolali Vyapari Sahakari Bank Ltd, Subhash Road Branch, Jawahar Market, Nashik Road, Nas
Estimated costRs 3.75 cr
Cost incurredRs 3.60 cr
Work done96.0%
BuildingWingEstimatedIncurred
Laxmi Heights ApartmentNARs 3.75 crRs 3.60 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshok Senghani
EngineerYogesh Thatte
Chartered AccountantJain Chhajed & Associates
Chartered AccountantKapil Ramesh Khivansara
PartnerRole in project
Gopi Kanayalal Allthakkar-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA09022619773Dec 2025 → Dec 2026

Reason as filed by the promoterThere are inadequate bookings from the customer, and the construction work is in progress at slow pace. Accordingly, we will require additional time to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Laxmi Heights - Mar 2026.pdf12 May 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate - Mar 2026.pdf12 May 2026
Withdrawal Update Form 3File: Form 3 - Laxmi Heights - Mar 2026.pdf12 May 2026
Form 2A (FY 2024-2025)File: Form 2A - Laxmi Heights - March 2025.pdf24 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A - Laxmi Heights - Mar 2024.pdf24 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 - Laxmi Heights Apartment.pdf24 Feb 2026
Form 1File: Form 1 Architect Certificate.pdf9 Feb 2026
Form 2File: Form 2 Engineer Certificate Sept 2025.pdf9 Feb 2026
Form 3File: Form 3 Laxmi Heights Sept 2025.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory Sep 2025.pdf9 Feb 2026
Form 1File: Form 1 Architect Certificate Dec 2025.pdf9 Feb 2026
Form 2File: Form 2 Engineer Certificate Dec 2025.pdf9 Feb 2026
Form 3File: Form 3 Laxmi Heights Dec 2025.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory Dec 2025.pdf9 Feb 2026
Form 1File: Form 1- Architect Certificate - June 2025.pdf1 Aug 2025
Form 2File: Form 2 - Engineer Certificate - June 2025.pdf1 Aug 2025
Form 3File: Form 3 - Laxmi Heights - June 2025.pdf1 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory June 2025.pdf1 Aug 2025
Form 1File: Form 2 - Engineer Certificate - Mar 2025.pdf21 May 2025
Form 2File: Form 1 - Engineer Certificate - Mar 2025.pdf21 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmi Heights - Mar 2025.pdf1 May 2025
Other - FinanceFile: Self Declaration - Penalty Payment.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect Certificate - Sept 2023.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form 1 - Architect Certificate - Dec 2023.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form 1 - Architect Certificate - March 2024.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form 1 - Architect Certificate - June 2024.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Form 1 - Architect Certificate - Sept 2024.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - Signed.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - Dec 2024.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - Dec 2024.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmi Heights - Dec 2024.pdf25 Jan 2025
Other - FinanceFile: 3 Self Declaration - Update for June 2023.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Laxmi Heights Apartment.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Booked Inventory.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - June 2024.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - Sept 2024.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmi Heights - Sept 2024.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmi Heights - June 2024.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - June 2024.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - Sept 2024.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - March 2024.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Laxmi Heights - March 2024.pdf30 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - March 2024.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Laxmi Heights - Mar 2024.pdf30 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect Certificate.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer's Certificate.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate.pdf20 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Laxmi Heights - Sept 2023.pdf20 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Laxmi Heights- Dec 2023.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Plinth Certificate.pdf1 Jun 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance Certificate.pdf24 Apr 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance Certificate.pdf24 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Seperate Bank Account.pdf24 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Updated.pdf21 Apr 2023
CERSAI detailsFile: CERSAI Search Report.pdf25 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate.pdf25 Mar 2023
Layout approvalFile: Approved Building Plan.pdf21 Mar 2023
Building plan approvalFile: Approved Building Plan.pdf21 Mar 2023
PAN CardFile: PAN - Gopi Althakkar.pdf21 Mar 2023
Copy of the legal title reportFile: Format A - Legal Title Report.pdf21 Mar 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance Certificate.pdf21 Mar 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance Certificate.pdf21 Mar 2023
Copy of Layout Approval (in case of layout)File: Approved Building Plan.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Approved Building Plan.pdf21 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf21 Mar 2023
Declaration about Commencement CertificateFile: Declaration - Commencement Certificate.pdf21 Mar 2023
Declaration in FORM BFile: Form B - Developer.pdf21 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf21 Mar 2023
Proforma of Agreement for saleFile: Draft Agreement of Sale.pdf21 Mar 2023
Proforma of Allotment letterFile: Draft Letter of Allotment.pdf21 Mar 2023
Deviation Report with respect to Allotment letterFile: No Deviation in allotment letter.pdf21 Mar 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Certificate - Agreement.pdf21 Mar 2023

How this compares with Nashik

7%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 12 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Laxmi Heights Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bankar Mala4,100+ in Nashik

Builder: Gopi Kanayalal Allthakkar

Gopi Kanayalal Allthakkar has 1 registration on MahaRERA, including Laxmi Heights Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Laxmi Heights Apartment is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Laxmi Heights Apartment?

The registered promoter entity is Gopi Kanayalal Allthakkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Laxmi Heights Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Laxmi Heights Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Laxmi Heights Apartment?

The professionals named in the filing: Architect: Ashok Senghani; Engineer: Yogesh Thatte; Chartered Accountant: Jain Chhajed & Associates; Chartered Accountant: Kapil Ramesh Khivansara. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Laxmi Heights Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Laxmi Heights Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Laxmi Heights Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.