Registration approved No litigation declared Residential/Group Housing project

LAND LINKS ANANTHA NAGAR TOWNSHIP

By LAND LINKS

RG-KA-50678 · RERA PRM/KA/RERA/1257/334/PR/271123/006438 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
4 of 14Construction stages donefurthest along: RCC or MS Framed structure, 90%
23 of 54Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 135 documents Report an error

LAND LINKS ANANTHA NAGAR TOWNSHIP is a Residential/Group Housing project by LAND LINKS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/271123/006438 on 27 Nov 2023. Possession is promised by 10 Dec 2026. 31 of the 54 units on this registration are recorded sold or booked, and 4 of 14 construction stages are filed complete.

At a glance

Project

  • NameLAND LINKS ANANTHA NAGAR TOWNSHIP
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/271123/006438
  • ReraGenie IDRG-KA-50678

Builder

  • NameLAND LINKS
  • Entity typeProprietorship
  • GSTIN29ACZPP0444NIZO
  • Authorized SignatoryJ KRISHNA PALEMAR
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on27 Nov 2023
  • Promised completion10 Dec 2026
  • Revised completionNone
  • Buildings6 building records
  • Documents filed135 files

Current status

57%31 of 54 units booked
3.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1 A---808
1B---808
2A---10010
2B---808
5A---10010
5B---10010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 14 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 93% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure90%
Masonry Construction90%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification90%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing90%
Electrification, Water supply and Sanitary Finishing90%
Painting90%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work90%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes90%
Sewage and Drainage SystemYes90%
Water conservation/rain water harvesting/recharge of ground waterYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes90%
Electricity supply transformer and substationYes90%
Storm water drainsYes90%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes90%
Parks & Tree plantingYes90%
Street LightingYes90%
ElectricityYes90%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes90%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes90%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes90%
BasementNoNot applicable
TerraceYes90%
Outer WallYes90%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
J KRISHNA--
J KRISHNA--
J KRISHNA--
J KRISHNA PALEMAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.68 cr
Cost incurredRs 23.10 lakh
Spent of the estimate3.46%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.60 crRs 20.93 lakh
On-site expenditure-Consultants FeesRs 2.75 lakh-
On-site expenditure-Site OverheadRs 2.75 lakh-
Payment of taxesRs 1.90 lakh-
On-site expenditure-Salaries of workers-Rs 2.17 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG YOGISH PAI
EngineerRAGHAVENDRA S
Chartered AccountantKESHAVA N BALLUKARAYA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed135

As listed on the registration, under the names the promoter filed them with; the newest 80 of 135 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/271123/006438 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Landlinks form 4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q2 26-27_compressed.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Landlinks Anantha township form 4.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5Q1 26-27-1.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q1 26-27-1.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Landlinks Form 4 Qtr 4_compressed.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5_compressed.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6_compressed.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 landlinks anatha township dec 25_compressed.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Kudupu Rera Form 5 Q3_compressed.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Kudupu Rera Form 6 Q3_compressed.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
previous project quarterly updateFile: Plot Quarterly Update Land links layout.pdf27 Nov 2023
Development PlanFile: Development plan.pdf27 Nov 2023
Development Plan OrderFile: Development plan order.pdf27 Nov 2023
Architects certificate with valid COA number.File: COA CERTIFICATE.pdf27 Nov 2023
Form 2File: Form 2 Landlinks.pdf27 Nov 2023
form 5File: Form 5 Landlinks.pdf27 Nov 2023
Phasewise demarcation drawingFile: DEMARCATION.pdf27 Nov 2023
Amenities and Common area certified by engineerFile: Certified amenties area.pdf27 Nov 2023
self-attested copy of the Engineer license certificateFile: Self attetested Engineer License.pdf27 Nov 2023
STP design drawing certified by the EngineerFile: STP certitied by engineer.pdf27 Nov 2023
Land cost calculation sheet as per the guidance value(Self-attested copy)File: GUIDANCE VALUE.pdf27 Nov 2023
clarificationFile: clarification.pdf27 Nov 2023
RTC, survey 109/6-
Mutation, survey 109/6-
Encumbrance Certificate, survey 109/6-
Conversion/Alienation Order, survey 109/6-
Sale/Title/Gift Deed, survey 109/6-
Khatha, survey 109/6-
RTC, survey 109/4-
Mutation, survey 109/4-
Encumbrance Certificate, survey 109/4-
Conversion/Alienation Order, survey 109/4-
Sale/Title/Gift Deed, survey 109/4-
Khatha, survey 109/4-
RTC, survey 109/5-
Mutation, survey 109/5-
Encumbrance Certificate, survey 109/5-
Conversion/Alienation Order, survey 109/5-
Sale/Title/Gift Deed, survey 109/5-
Khatha, survey 109/5-
RTC, survey 109/7-
Mutation, survey 109/7-
Encumbrance Certificate, survey 109/7-
Conversion/Alienation Order, survey 109/7-
Sale/Title/Gift Deed, survey 109/7-
Khatha, survey 109/7-
Registration CertificateFile: gst certificate.jpg-
Certificate issued by CA Form 1File: Form 1 landlinks.pdf-
Certificate issued by Architect Form 2File: Form 2 Landlinks.pdf-
Certificate issued by Engineer Form 3File: Form no 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 landlinks.pdf-
Balance Sheet 2022 - 2023File: BS with Sch 22.pdf-
Balance Sheet 2021 - 2022File: BS with Sch 21.pdf-
Balance Sheet 2020 - 2021File: BS with Sch 20.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL with Sch 22.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL with Sch 21.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL with Sch 20.pdf-
Auditor's Report 2022 - 2023File: audit report 22.pdf-
Auditor's Report 2021 - 2022File: audit report 21.pdf-
Auditor's Report 2020 - 2021File: audit report 20.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR 22.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 21.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 20.pdf-
Building license all-
MESCOM Noc-
Water NOC-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
LAND LINKS ANANTHA NAGAR LAYOUTRS NO.109-5(P)146-1B2(P)109-4(P)109-5(P)146-1B2(P)109-4(P)109-4(P)109-3(P)109-6(P)109-3(P)109-7(P) , KUDUPU VILLAGE MANGALORE , KUDUPU MANGALOREOngoingJun 2024Not delivered

How this compares with Dakshina Kannada

57%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep LAND LINKS ANANTHA NAGAR TOWNSHIP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: LAND LINKS

LAND LINKS has 1 registration on RERA Karnataka, including LAND LINKS ANANTHA NAGAR TOWNSHIP. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if LAND LINKS ANANTHA NAGAR TOWNSHIP is delayed beyond 10 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LAND LINKS ANANTHA NAGAR TOWNSHIP?

The registered promoter entity is LAND LINKS, a proprietorship as per the filing. Its GSTIN 29ACZPP0444NIZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LAND LINKS ANANTHA NAGAR TOWNSHIP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LAND LINKS ANANTHA NAGAR TOWNSHIP?

The professionals named in the filing: Architect: G YOGISH PAI; Engineer: RAGHAVENDRA S; Chartered Accountant: KESHAVA N BALLUKARAYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAND LINKS ANANTHA NAGAR TOWNSHIP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAND LINKS ANANTHA NAGAR TOWNSHIP. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAND LINKS ANANTHA NAGAR TOWNSHIP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.