Home / Browse projects / Mumbai Suburban, Maharashtra / LALANIBUSINESSPARK

Registration lapsed No litigation declared Commercial project

LALANIBUSINESSPARK

By LALANI CONSTRUCTIONS PRIVATE LIMITED

RG-MH-49196 · RERA P51800033063 · Last updated on MahaRERA portal: 25 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
1 of 11Construction stages donefurthest along: Staircases, 15%
22 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

LALANIBUSINESSPARK is a Commercial project by LALANI CONSTRUCTIONS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800033063 on 3 Feb 2022. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 24 months from the original filing. 0 of the 22 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameLALANIBUSINESSPARK
  • TypeCommercial
  • Location
    • CTS F/73A F P NO 613A TPS-III JUNCTION OF P D HINDUJA ROAD AND 15TH ROAD
    • KHAR WEST MUMBAI
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800033063
  • ReraGenie IDRG-MH-49196

Builder

  • NameLALANI CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredFeb 2022First promiseMar 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Feb 2022
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed98 files

Current status

0%0 of 22 units booked

Figures as on 25 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LALANIBUSINESSPARKNA211802222

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 15%.

LALANIBUSINESSPARK: 11% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)2%
Podiums (if any)0%
Plinth2%
Stilt Floor0%
Slabs of Super Structure2%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.1%

Progress on shared amenities15

As on 25 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area498 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBrihan Mumbai Mahanagarpalika
Permissible FSI2578.5
Proposed, not sanctioned2,578 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Shelter Gr and 1st Floor, 32nd Road, Opp National College

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSOHIL HAJIANI
EngineerSACPL MR NIKHIL SHANGVI
Chartered AccountantMR MANISH FOFARIA & CO
PartnerRole in project
LALANI CONSTRUCTIONS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019163Mar 2024 → Mar 2026

Reason as filed by the promoterOur actual execution started on 01/03/2022 at site. The project consists of 2 nos. of basements+ ground + service floor+16thupper floors+17thpart floor with existing buildings on 2 sides and approachable roads on 2 sides, therefore to safeguard the Roads and compound wall of the existing bldgs., 152 piling was required to be done as suggested by our structural consultant. Piling along with the pile cap completed in 2 months; contractor took 1month for mobilisation and start the excavation work; Excavation was required to be done in 3 phases. Phase -1: excavation up to first basement level (-4.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert-31-03-2025 LBP.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE 31-03-25.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FORM 2 31-03-25.pdf5 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEERS QUALITY ASSURANCE CERTIFICATE L b p- 31-03-25.pdf5 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration about RERA Designated Account.pdf10 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Opening RERA Designated Bank Account.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 31-12-24.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate form-1 31-12-24.pdf13 Jan 2025
Proforma of Allotment letterFile: LBPRevisedAllotment letter08012025.pdf8 Jan 2025
Proforma of Agreement for saleFile: LBPAgreement08012025.pdf8 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: LBP SBI.pdf8 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: LBP Bajaj Mortgage .pdf8 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (31-12-24).pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 (31-12-24).pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A (31-12-24).pdf2 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate form-1 30-09-24.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate-LBP-30-09-2024.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FORM 2 30-09-24.pdf24 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEERS QUALITY ASSURANCE CERTIFICATE FORM 2A 30-09-24.pdf24 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certificate LBP-31-03-2024.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert LBP 30-06-2024.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEERS CERTIFICATE LBP 30-06-24.pdf16 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE LBP 30-06-24.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 LBP ARCHITECTS CERTIFICATE 30-06-24.pdf15 Jul 2024
Disclosure of sold/ booked inventoryFile: LBPUnsold unit.pdf25 Apr 2024
Declaration in FORM BFile: LBP FORM B.pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: lalani business park rera certificate march 2024 31-04-24.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 31-04-24.pdf24 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE 31-04-24.pdf24 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA certificate-31-03-2024 LBP.pdf24 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Form 3-CA certificate-31-03-2024 LBP.pdf24 Apr 2024
OtherFile: FORM B SUBMITTED.pdf23 Apr 2024
OtherFile: sold unsold inventory.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate-LCPL-31-12-2023.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: lbp form 2 31-12-23.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: lbp form 2a 31-12-23.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate form-1 lalani business park 31-12-23.pdf4 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 2400226_FurtherCC_signed KADRI MANZIL LALANI BUSINESS PARK.pdf5 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LBP form 1 23-10-23.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate form-2 lalani business park 30-09-23.pdf25 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: quality assurance certificate 2a lalani business park 30-09-23.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate LCPL-30-09-2023.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate-LCPL-30-06-2023.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate lalani business park 30-06-23.pdf4 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: lalani business park form-2 engineers certificate 30-06-23.pdf3 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: lalani business park form 2a quality assurance certificate 30-06-23.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA Certificate-LCPL-31-03-2023.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 lalani business park 31-03-2023.pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LBP Annexure B Form - 2.pdf31 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: LBP Annexure -C Form 2a.pdf31 Mar 2023
Building plan approvalFile: Amended plan approval letter (signed) 23-05-2022.pdf4 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Amended plan approval letter (signed) 23-05-2022.pdf4 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: 1244401073NoteSheet_16646_signed cc revalidation.pdf4 Feb 2023
Building plan approvalFile: 1.pdf3 Feb 2023
Building plan approvalFile: 2.pdf3 Feb 2023
Building plan approvalFile: 3.pdf3 Feb 2023
Building plan approvalFile: 4.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf3 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A Lalani business park (25-01-23).pdf25 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3LCPL.pdf25 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: manisha madam form-1 lalani business park.pdf21 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Lalani busines Park form-2 nasib bhai (21-01-23).pdf21 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5LCPL22.pdf29 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5LCPL22.pdf29 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LBP Ar Manisha ltr 310322.pdf22 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LBP Ar Manisha ltr 300622.pdf22 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LBP Er Naisb bhulani ltr 300322.pdf22 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LBP Er Nasib bhulani ltr 300622.pdf22 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3CACertificateLBP.pdf22 Jul 2022
Layout approvalFile: Page 1.pdf18 Jan 2022
Building plan approvalFile: Page 3.pdf18 Jan 2022
Building plan approvalFile: Page 4.pdf18 Jan 2022
Building plan approvalFile: Page 1.pdf18 Jan 2022
Building plan approvalFile: Page 2.pdf18 Jan 2022
Copy of Layout Approval (in case of layout)File: Page 1.pdf18 Jan 2022

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LALANIBUSINESSPARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHAR WEST MUMBAI6,700+ in Mumbai Suburban

2 kmLALANIBUSINESSPARKCompleted 119Lapsed / revoked 53Other 150Dot size: filed unitsN

Filed coordinates, straight-line distance. 322 registered projects within 2 km.

Builder: LALANI CONSTRUCTIONS PRIVATE LIMITED

LALANI CONSTRUCTIONS PRIVATE LIMITED has 3 registrations on MahaRERA, including LALANIBUSINESSPARK and Lalani Goodwill Building No 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that LALANIBUSINESSPARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LALANIBUSINESSPARK is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LALANIBUSINESSPARK?

The registered promoter entity is LALANI CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LALANIBUSINESSPARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LALANIBUSINESSPARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LALANIBUSINESSPARK?

The professionals named in the filing: Architect: SOHIL HAJIANI; Engineer: SACPL MR NIKHIL SHANGVI; Chartered Accountant: MR MANISH FOFARIA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LALANIBUSINESSPARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LALANIBUSINESSPARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LALANIBUSINESSPARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.