ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / LAKSHYA VINAYAK RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

LAKSHYA VINAYAK RESIDENCY

By EXPERT FOUNDATION AND STRUCTURE PVT LTD

RG-MH-01725 · RERA P51500007854 · Last updated on MahaRERA portal: 7 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 54 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 147 documents Report an error

LAKSHYA VINAYAK RESIDENCY is a Residential / Group Housing project by EXPERT FOUNDATION AND STRUCTURE PVT LTD in Aurangabad, Maharashtra, registered with MahaRERA as P51500007854 on 18 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NameLAKSHYA VINAYAK RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Karmad
    • Aurangabad
    • 431007
  • Pincode431007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500007854
  • ReraGenie IDRG-MH-01725

Builder

  • NameEXPERT FOUNDATION AND STRUCTURE PVT LTD
  • Entity typeCompany

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
  • Buildings2 building records
  • Documents filed147 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1 TO 20NA20000
BUILDING 23 TO 28NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

BUILDING 1 TO 2082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING 23 TO 2882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Open Space26
BuildingOpen SpaceTotal
BUILDING 1 TO 202020
BUILDING 23 TO 2866

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,744 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
NITIN DANDGE DESHMUKHAurangabad (M Corp.)Aurangabad
SANGITA SHYAMRAO DESHMUKHAurangabad (M Corp.)Aurangabad
YASHODA DNYESHWAR SHINDEAurangpurAurangabad

Approvals and building plan

Permissible FSI1496.64
Proposed, not sanctioned1,497 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAKASHWANI ABAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC B KULKARNI
EngineerSWAPNIL TAKNE
PartnerRole in project
EXPERT FOUNDATION AND STRUCTURE PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500010511Jun 2021 → Jun 2023

Reason as filed by the promoterThe construction of the project got delayed on account pandemic situation across country due to COVID-19. The construction work at site is completely stopped due to non-availability of labour, we have communicated the same to our customers and they are also understanding the difficulty. The customers have issued their consent for extension of the date of completion of the project. Hence, we request you to allow us extension by 24 months from original date of completion.

EXT51500018551Jun 2021 → Dec 2024

Reason as filed by the promoterThe registered project technically completed in all respect, waiting for occupancy certificate from respective authority.

EXT51500027447Jun 2021 → Dec 2025

Reason as filed by the promoterThe construction and development work of the project was fully completed in September 2024. However, we are unable to obtain the Completion Certificate from AMRDA due to a delay in their online process, which is currently on hold at the authority’s end.Since this delay is purely technical and beyond our control, we kindly request a 12-month extension for the project. The project is 100% complete, and possession has already been handed over to buyers. Therefore, there is no inconvenience or loss to the customers.We request you to grant the extension at the earliest.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed147

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Expert Pvt ltd- form-3 Apr-jun-23_0001.pdf7 Apr 2025
Certificates of CA (Form 3)File: Expert Pvt ltd- form-3 jul-sept-23_0001.pdf7 Apr 2025
Certificates of CA (Form 3)File: Expert Pvt ltd- form-3 Oct-Dec-23_0001.pdf7 Apr 2025
Certificates of CA (Form 3)File: Expert Pvt ltd- form-3 jan-mar-24_0001.pdf7 Apr 2025
Certificates of CA (Form 3)File: Expert Pvt ltd- form-3 Apr-jun-24_0001.pdf7 Apr 2025
Certificates of CA (Form 3)File: Form 3 To Expert found jul sep 24.pdf7 Apr 2025
Declaration in FORM BFile: Form no -B_0001.pdf27 Feb 2025
Certificates of CA (Form 3)File: FORM 3 Dt-30-09-2024_0001.pdf12 Feb 2025
Certificates of CA (Form 3)File: FORM 3 Dt-31-12-2024_0001.pdf12 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form No-5_0001.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 Dt-05-01-2025_0001.pdf25 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form no 2 Dt-05-01-2025.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Book Inventory Dt-30-09-2024_0001.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Book Inventory Dt-31-12-2024.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A Dt-05-10-2024_0001.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A Dt-31-12-2024_0001.pdf25 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no 1 Dt-05-10-2025_0002.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form no 2 Dt-05-10-2025_0001.pdf20 Jan 2025
Declaration in FORM BFile: Form-B New_0001.pdf5 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form- 5 Expert foundation dt 05-06-2024_0001.pdf5 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 04-04-2024 Lakshya Vinayak_0001.pdf30 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 08-07-2024 Lakshya Vinayak_0001_0001.pdf30 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 04-04-2024 Lakshya Vinayak__0001.pdf30 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 08-07-2024 Lakshya Vinayak___0001.pdf30 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A New_0001.pdf30 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A New 08-07-24.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 31-03-23 New_0001.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 30-06-23 New.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 30-09-23 New.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 31-12-23 New_0001.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 31-03-24 New_0001.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Desclosure of Sod -Booked inve 30-06-24 New.pdf30 Jul 2024
Certificates of CA (Form 3)File: FORM 3 Dt-30-06-2024.pdf30 Jul 2024
Certificates of CA (Form 3)File: FORM 3 Dt-30-09-2023.pdf30 Jul 2024
Certificates of CA (Form 3)File: FORM 3 Dt-31-12-2023.pdf30 Jul 2024
Certificates of CA (Form 3)File: FORM 3 Dt-31-03-2024.pdf30 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Dt-04-04-2023_0001.pdf26 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Dt-05-07-2023_0001.pdf26 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Dt-07-10-2023_0001.pdf26 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Dt-04-01-2024_0001.pdf26 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Expert Form 1 date 04-04-2023_0001.pdf24 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Expert Form 1Date 05-07-2023_0001.pdf24 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Expert Form 1 Date 07-10-2023_0001.pdf24 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: expert Form 1 Date 04-01-2024_0001.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Expert Form 2 Date05-04-2023_0001.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Expert Form 2 date 05-07-2023_0001.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Expert Form 2 Date 07-10-2023_0001.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Expert Form 2 Date 06-01-2024_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-30-06-2021_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-30-09-2021_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-31-12-2021_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-31-03-2022_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-30-06-2022_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-30-09-2022_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-31-12-2022_0001.pdf24 Jun 2024
Certificates of CA (Form 3)File: Form-3 Dt-31-03-2023_0001.pdf24 Jun 2024
Building plan approvalFile: BPMS Plot No 1 To 6-Revised Building Permission Drawing (4 files merged).pdf14 Feb 2023
Building Plan Approval (IOD)File: BPMS Plot No 1 To 6-Revised Building Permission Drawing (4 files merged).pdf14 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: BPMS Plot No 1 To 6-Revised Building Permission Order (4 files merged).pdf14 Feb 2023
Declaration about Commencement CertificateFile: Expert pltd declaration farmat-D_0001.pdf14 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf14 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form - 5 - 07-12-2022.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate of expert Dt31-12-2022_0001.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate of expert Dt31-03-2022_0001.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate of expert Dt30-06-2022_0001.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate of expert Dt30-09-2022_0001.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate of expert Dt31-12-2022_0002.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate of expert Dt05-01-2022_0001.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate of expert Dt31-03-2022_0001.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate of expert Dt30-06-2022_0001.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate of expert Dt30-09-2022_0001.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate of expert Dt31-12-2022_0001.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 06-10-2020.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 05-01-2021.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 07-04-2021.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 05-07-2021.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 04-10-2021.pdf28 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2- Expart Date 05-07-2020.pdf28 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2- Expart Date 06-10-2020.pdf28 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2- Expart Date 05-01-2021.pdf28 Jan 2023

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 54 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep LAKSHYA VINAYAK RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karmad1,400+ in Aurangabad

Builder: EXPERT FOUNDATION AND STRUCTURE PVT LTD

EXPERT FOUNDATION AND STRUCTURE PVT LTD has 1 registration on MahaRERA, including LAKSHYA VINAYAK RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that LAKSHYA VINAYAK RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LAKSHYA VINAYAK RESIDENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAKSHYA VINAYAK RESIDENCY?

The registered promoter entity is EXPERT FOUNDATION AND STRUCTURE PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAKSHYA VINAYAK RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAKSHYA VINAYAK RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAKSHYA VINAYAK RESIDENCY?

The professionals named in the filing: Architect: C B KULKARNI; Engineer: SWAPNIL TAKNE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAKSHYA VINAYAK RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAKSHYA VINAYAK RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAKSHYA VINAYAK RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.