Home / Browse projects / Aurangabad, Maharashtra / PMAY U Sundarwadi 10
PMAY U Sundarwadi 10
RG-MH-31552 · RERA P51500079887 · Last updated on MahaRERA portal: 12 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 60 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PMAY U Sundarwadi 10 is a Residential / Group Housing project by Aurathrone Infra in Aurangabad, Maharashtra, registered with MahaRERA as P51500079887 on 28 Mar 2025. Possession is promised by 31 Dec 2030. The completion date has moved by 60 months from the original filing. 0 of the 2,112 units on this registration are recorded sold or booked, and 19 of 209 construction stages are filed complete.
At a glance
Project
- NamePMAY U Sundarwadi 10
- TypeResidential / Group Housing
- Location
- Gut no. 10
- Mauje Sunderwadi
- Sundarwadi
- Aurangabad
- 431007
- Pincode431007
- RERA no.P51500079887
- ReraGenie IDRG-MH-31552
Builder
- NameAurathrone Infra
- Entity typePartnership
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Mar 2025
- Promised completion31 Dec 2030
- Revised completionRevised to 31 Dec 2030 (originally 31 Dec 2025)
- Buildings19 building records
- Documents filed52 files
Current status
Figures as on 12 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A9-A10 | NA | 8 | 8 | 112 | 0 | 112 |
| A11-A12 | NA | 8 | 8 | 112 | 0 | 112 |
| A13-A14 | NA | 8 | 8 | 112 | 0 | 112 |
| A15-A16 | NA | 8 | 8 | 112 | 0 | 112 |
| A17-A18 | NA | 8 | 8 | 112 | 0 | 112 |
| A19-A20 | NA | 8 | 8 | 112 | 0 | 112 |
| A21-A22 | NA | 8 | 8 | 112 | 0 | 112 |
| A23-A24 | NA | 8 | 8 | 112 | 0 | 112 |
| A25-A26 | NA | 8 | 8 | 112 | 0 | 112 |
| A27-A28 | NA | 8 | 8 | 112 | 0 | 112 |
| A29-A30 | NA | 8 | 8 | 112 | 0 | 112 |
| A31-A32 | NA | 8 | 8 | 112 | 0 | 112 |
| A33-A34 | NA | 8 | 8 | 112 | 0 | 112 |
| A35-A36 | NA | 8 | 8 | 112 | 0 | 112 |
| A37-A38 | NA | 7 | 7 | 96 | 0 | 96 |
| A1-A2 | NA | 8 | 8 | 112 | 0 | 112 |
| A3-A4 | NA | 8 | 8 | 112 | 0 | 112 |
| A5-A6 | NA | 8 | 8 | 112 | 0 | 112 |
| A7-A8 | NA | 8 | 8 | 112 | 0 | 112 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building19
As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 209 construction stages are filed complete across 19 buildings. The stage furthest along is Plinth, at 15%.
A9-A109%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A11-A129%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A13-A149%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A15-A169%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A17-A189%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A19-A209%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A21-A229%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A23-A249%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A25-A269%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A27-A289%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A29-A309%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A31-A329%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A33-A349%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A35-A369%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A37-A389%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A1-A210%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 15% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A3-A410%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 15% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A5-A69%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A7-A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1553
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| A9-A10 | 82 | 82 |
| A11-A12 | 82 | 82 |
| A13-A14 | 82 | 82 |
| A15-A16 | 82 | 82 |
| A17-A18 | 82 | 82 |
| A19-A20 | 82 | 82 |
| A21-A22 | 82 | 82 |
| A23-A24 | 82 | 82 |
| A25-A26 | 82 | 82 |
| A27-A28 | 82 | 82 |
| A29-A30 | 82 | 82 |
| A31-A32 | 82 | 82 |
| A33-A34 | 82 | 82 |
| A35-A36 | 82 | 82 |
| A37-A38 | 77 | 77 |
| A1-A2 | 82 | 82 |
| A3-A4 | 82 | 82 |
| A5-A6 | 82 | 82 |
| A7-A8 | 82 | 82 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Chhatrapati Samabhajinagar Municipal Corporation | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 10.85 cr | - |
| A9-A10 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A11-A12 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A13-A14 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A15-A16 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A17-A18 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A19-A20 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A21-A22 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A23-A24 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A25-A26 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A27-A28 | NA | Rs 9.73 cr | Rs 14.10 lakh |
| A29-A30 | NA | Rs 9.73 cr | Rs 14.10 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Swapnil Shroff |
| Engineer | Surve Samarth Chandrakant |
| Chartered Accountant | CA Yash Nagar |
| Partner | Role in project |
|---|---|
| Aurathrone Infra | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe request an extension of the project timeline as per RERA due to the delay in receiving the official work order from the concerned government authorities, despite our continuous follow-ups. As the work order is essential to begin and progress the project, we seek additional time to ensure successful completion once the order is issued. We appreciate your consideration.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Mar 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Sundarwadi 10 AI Form 1 Signed.PDF | 12 May 2026 |
| Withdrawal Update Form 2File: Sundarwadi 10 AI Form 2 Signed.PDF | 12 May 2026 |
| Withdrawal Update Form 3File: Sundarwadi 10.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Sundarwadi Gut No 10 Form 1_.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Sundarwadi Gut No 10 Form 2.PDF | 21 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Sundarwadi 10 2025-26 Q3_.pdf | 21 Jan 2026 |
| Withdrawal Update Form 1File: Sundarwadi Gut No 10 Form 1_.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Sundarwadi Gut No 10 Form 2.PDF | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Sundarwadi 10 2025-26 Q3_.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Aurathrone Infra - Sundarwadi Gut No10 - Form 1.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Aurathrone Infra - Sundarwadi Gut No 10 - Form 2.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: form 3_Final.pdf | 27 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Sundarwadi Gut 10.PDF | 8 Aug 2025 |
| Withdrawal Update Form 1File: Form 1 Sundarwadi 10.pdf | 23 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 Sundarwadi 10.pdf | 23 Jul 2025 |
| Withdrawal Update Form 3File: Sundarwadi Gut 10 Form 3 Upload.pdf | 23 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SUNDARWADI 10_compressed.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SUNDARWADI 10_compressed.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SUNDARWADI 10_compressed.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Sunderwadi 10 Upload 31-03-25.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sunderwadi 10 Form 3 Signed_1.pdf | 28 Mar 2025 |
| Copy of the legal title reportFile: RERA SEARCH REPORT GUT NO 10 Sunderwadi_latest_upload.pdf | 25 Mar 2025 |
| Other - FinanceFile: Final Form 3 Declaration Sundarwadi 10.pdf | 25 Mar 2025 |
| Other - FinanceFile: Workorder Sundarwadi 9 and 10 (1).pdf | 25 Mar 2025 |
| Proforma of Allotment letterFile: Allotment letter Sundarwadi 10.pdf | 20 Mar 2025 |
| Other - LegalFile: Sundarwadi Gut 10 7_12.pdf | 20 Mar 2025 |
| Other - LegalFile: Online Certificate AURATHRONE INFRA ROF.pdf | 20 Mar 2025 |
| Other - LegalFile: Partnership Deed Aurathrone_1.pdf | 20 Mar 2025 |
| Proforma of Agreement for saleFile: Agreement to Sale Sundarwadi 10.pdf | 20 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Declaration Format B.pdf | 20 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrances Merged.pdf | 13 Mar 2025 |
| Declaration in FORM BFile: FORM B - Developer New Revised Upload.pdf | 13 Mar 2025 |
| Other - LegalFile: Annexure A.PDF | 13 Mar 2025 |
| Declaration about Commencement CertificateFile: Decleration of CC.PDF | 13 Mar 2025 |
| CERSAI detailsFile: Cersai Declaration.PDF | 13 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about RERA Designated Bank Accounts for real estate projects.pdf | 13 Mar 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.PDF | 13 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrances Merged.pdf | 13 Mar 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.PDF | 13 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Merged.pdf | 13 Mar 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for securedunsecured finance availed for the project.PDF | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Sunderwadi 10 Upload.pdf | 12 Mar 2025 |
| CERSAI detailsFile: Sundarwadi 10 Upload.pdf | 12 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aurathrone Sundarwadi 10.PDF | 10 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Gmail - 76 08 SANTION BP POROPSAL 05032025 PMAY.pdf | 10 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Upload.pdf | 7 Mar 2025 |
| Layout approvalFile: Layout.pdf | 5 Mar 2025 |
| Building plan approvalFile: Building Plan.pdf | 5 Mar 2025 |
| PAN CardFile: PAN Aurathrone Infra.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 5 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Upload.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf | 5 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 52 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PMAY U Sundarwadi 10 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mauje Sunderwadi1,400+ in Aurangabad
PMAY U Sundarwadi 9
Aurathrone Infra
SECTOR 41
MANISH RAMNIRANJAN AGRAWAL AND AMITABH CHA
AURA SQUARE - KALYAN HEIGHTS
KALYAN HEIGHTS
URBAN AMBITION
MANISH RAMNIRANJAN AGRAWAL
Hrim Ssky City Phase V
Ashok Baheti
DISHA VRUNDAVAN
Everest Realtors
See every Aurangabad project, with the district possession charts
Builder: Aurathrone Infra
Aurathrone Infra has 2 registrations on MahaRERA, including PMAY U Sundarwadi 10 and PMAY U Sundarwadi 9. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if PMAY U Sundarwadi 10 is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PMAY U Sundarwadi 10?
The registered promoter entity is Aurathrone Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PMAY U Sundarwadi 10?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PMAY U Sundarwadi 10?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PMAY U Sundarwadi 10?
The professionals named in the filing: Architect: Ar. Swapnil Shroff; Engineer: Surve Samarth Chandrakant; Chartered Accountant: CA Yash Nagar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PMAY U Sundarwadi 10?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.