Home / Browse projects / Raigarh, Maharashtra / LAKE CITY PHASE-2

Completed No litigation declared Others project

LAKE CITY PHASE-2

By SADANAND LAXMANRAO PATIL

RG-MH-42931 · RERA P52000017801 · Last updated on MahaRERA portal: 18 Apr 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
238 of 374Construction stages doneacross 34 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

LAKE CITY PHASE-2 is a Others project by SADANAND LAXMANRAO PATIL in Raigarh, Maharashtra, registered with MahaRERA as P52000017801 on 17 Sep 2018. The registration is recorded completed; possession was promised by 30 Jun 2022.

At a glance

Project

  • NameLAKE CITY PHASE-2
  • TypeOthers
  • Location
    • KHOPOLI PALI ROAD
    • PALI SUDHAGAD
    • Bhilpada (khuravale)
    • Sudhagad
    • Raigarh
    • 410205
  • Pincode410205
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000017801
  • ReraGenie IDRG-MH-42931

Builder

  • NameSADANAND LAXMANRAO PATIL
  • Entity typeIndividual
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2018PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Sep 2018
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings34 building records
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C1NA10000
C2 AND C3NA10000
C4 AND C5NA10000
C6 AND C7NA10000
C8 AND C9NA10000
C10 AND C11NA10000
C12 AND C13NA10000
C14 AND C15NA10000
C16 AND C17NA10000
C18 AND C19NA10000
C20 AND C21NA10000
C22 AND C23NA10000
C27NA10000
C28NA10000
C29NA10000
C30NA10000
C31NA10000
C32NA10000
C33NA10000
C34NA10000
B14 AND B15NA20000
B16 AND B17NA20000
B18 AND B19NA20000
B20NA20000
B29 AND B30NA20000
B31 AND B32NA20000
B33 AND B34NA20000
B35 AND B36NA20000
B37 AND B38NA20000
B39 AND B40NA20000
B41 AND B42NA20000
B43 AND B44NA20000
B45 AND B46NA20000
B47 AND B48NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 18 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 34 buildings; the table lists the first 20.

238 of 374 construction stages are filed complete across 34 buildings. The stage furthest along is Podiums (if any), at 0%.

C164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C2 AND C364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C4 AND C564%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C6 AND C764%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C8 AND C964%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C10 AND C1164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C12 AND C1364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C14 AND C1564%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C16 AND C1764%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C18 AND C1964%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C20 AND C2164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C22 AND C2364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C2764%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C2864%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C2964%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C3064%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C3164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C3264%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C3364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C3464%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed58

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots58
Open Space58
BuildingOpen SpaceTotal
C111
C2 AND C322
C4 AND C522
C6 AND C722
C8 AND C922
C10 AND C1122
C12 AND C1322
C14 AND C1522
C16 AND C1722
C18 AND C1922
C20 AND C2111
C22 AND C2322
C2711
C2811
C2911
C3011
C3111
C3211
C3311
C3411
B14 AND B1522
B16 AND B1722
B18 AND B1922
B2022
B29 AND B3022
B31 AND B3222
B33 AND B3422
B35 AND B3622
B37 AND B3822
B39 AND B4022
B41 AND B4222
B43 AND B4422
B45 AND B4622
B47 AND B4822

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,570 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
GAJANAN UTTAMRAO MANTEBanerPune

Approvals and building plan

Permissible FSI18582.41
Proposed, not sanctioned18,582 sq m
Buildings approved34
Buildings sanctioned34

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 2 Atria Sai Prestige Baner Road Pune Maharashtra 411045

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJIT MOHITE
ArchitectADITYA JESWAL
EngineerSATISH MARATHE
EngineerK P Badgujar Consultants Pvt Ltd
EngineerSANKET DARAMWAR
Chartered AccountantS P MUDALIAR & ASSOCIATES
PartnerRole in project
SADANAND LAXMANRAO PATIL-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Oct 2022

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: LC ph2 Registration Certificate.pdf18 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Phase-2.pdf12 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2018-19.pdf30 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-20.pdf30 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance 29022020.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 30112018.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 28022019.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 31052019.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 31082019.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 30112019.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 29022020.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 31052020.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 31082020.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICTAE 30112020.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 28022021.pdf17 Feb 2023
Certificates of CA (Form 3)File: CA CERTIFICATE 31052021.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 31082021.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 30112021.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 28022022.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 28022022.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE 30062022.pdf17 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 29022020.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 31082020.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 30112020.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 280221.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect's Certificate 31082021.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate 30112021.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 280222.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Cert 31052022 C.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGG CERTIFICATE 30112018.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 28022019.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 31052019.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 31082019.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CER 29022020.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CER 31052020.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENG CER 31082020.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 301120.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 28022021.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 31082021.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 28022022.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert 30062022.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 30112018.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 28022019.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 31082019.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 30112019.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 2 ENGINEER CER 29022020.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 2 ENG CER 31082020.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 310521.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGR CERT 30112021.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A SITE ENGINEER'S CERTIFICATE 280222.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CER 31052020.pdf30 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCH CER 31052021.pdf30 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Cert 31052022 C.pdf30 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Self Declaration Society Formation.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert 300622.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 ANNUAL REPORT.pdf1 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: LC Ph2 OC.pdf6 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200228211424_For_Asset_Based_Search_17_01_2022_13_58_25_896.pdf19 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf27 Sep 2021
Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY 28-02-21.pdf19 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate For Ouality Assurance.pdf29 Apr 2021
Details of Restarting of Construction work post lockdownFile: Details of Restarting Construction Post Lockdown.pdf29 Jun 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE .pdf11 Jan 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate .pdf11 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QA certificate (30-11-19).pdf11 Jan 2020
Certificates of CA (Form 3)File: RERA CA CERTIFICATE .pdf11 Jan 2020
Layout approvalFile: REVISED LAYOUT PLAN.pdf12 Oct 2019
Building plan approvalFile: REVISED BUILDING PLAN 1.pdf12 Oct 2019
Building plan approvalFile: REVISED BUILDING PLAN 2.pdf12 Oct 2019
Building plan approvalFile: REVISED BUILDING PLAN 3.pdf12 Oct 2019
Copy of Layout Approval (in case of layout)File: REVISED LAYOUT PLAN.pdf12 Oct 2019
Building Plan Approval (IOD)File: REVISED BUILDING PLAN 1.pdf12 Oct 2019
Building Plan Approval (IOD)File: REVISED BUILDING PLAN 2.pdf12 Oct 2019
Building Plan Approval (IOD)File: REVISED BUILDING PLAN 3.pdf12 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: NEW NA ORDER .pdf12 Oct 2019
Certificates of CA (Form 3)File: CA RERA FORM 3.pdf4 Sep 2018
Proforma of Allotment letterFile: 7) ALLOTMENT LETTER.pdf3 Sep 2018
Proforma of Allotment letterFile: 7) Agreement for Sale.pdf3 Sep 2018
Building plan approvalFile: 3) BUILDING PLAN 1.pdf1 Sep 2018
Building plan approvalFile: 3) BUILDING PLAN 2.pdf1 Sep 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Lake City Phase-4Chive Khopoli Pali Road Sudhagad Pali Dist. Raigad 410205-CompletedJun 2022Jun 2022
Lake City Phase-2Bhilpada Khopoli Pali Road Sudhagad Pali Dist. Raigad 41020558CompletedJun 2022Jun 2022
LAKE CITY PHASE-1Bhilpada Khopoli Pali Road Sudhagad Pali Dist. Raigad 41020592CompletedJun 2019Jun 2019

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LAKE CITY PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALI SUDHAGAD5,900+ in Raigarh

Builder: SADANAND LAXMANRAO PATIL

SADANAND LAXMANRAO PATIL has 5 registrations on MahaRERA, including LAKE CITY PHASE-1 and LAKE CITY PHASE-2. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if LAKE CITY PHASE-2 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAKE CITY PHASE-2?

The registered promoter entity is SADANAND LAXMANRAO PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAKE CITY PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAKE CITY PHASE-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAKE CITY PHASE-2?

The professionals named in the filing: Architect: ABHIJIT MOHITE; Architect: ADITYA JESWAL; Engineer: SATISH MARATHE; Engineer: K P Badgujar Consultants Pvt Ltd; Engineer: SANKET DARAMWAR; Chartered Accountant: S P MUDALIAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAKE CITY PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAKE CITY PHASE-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAKE CITY PHASE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.