Lagoona Woods Phase 1
RG-MH-19812 · RERA P52100007392 · Last updated on MahaRERA portal: 26 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 102 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Lagoona Woods Phase 1 is a Others project by Sudarshan Developers in Pune, Maharashtra, registered with MahaRERA as P52100007392 on 17 Aug 2017. Possession is promised by 30 Jun 2028. The completion date has moved by 102 months from the original filing. 19 of the 25 units on this registration are recorded sold or booked, and 21 of 275 construction stages are filed complete.
At a glance
Project
- NameLagoona Woods Phase 1
- TypeOthers
- Location
- Lavharde
- Mulshi
- Pune
- 412115
- Pincode412115
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100007392
- ReraGenie IDRG-MH-19812
Builder
- NameSudarshan Developers
- Entity typePartnership
- PartnersMukta Vivek Saraf, Rahul Premprakash Goyal, Mayank Vinodkumar Goyal, Omprakash Dindayal Agarwal, Akash Premprakash Goyal, Ravindra Shantilal Petty
- Other registrations4 more →
- Completed2 of 5
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Aug 2017
- Promised completion30 Jun 2028
- Revised completionRevised to 30 Jun 2028 (originally 31 Dec 2019)
- Buildings25 building records
- Documents filed96 files
Current status
Figures as on 26 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Unit 1 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 2 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 3 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 4 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 5 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 6 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 7 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 8 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 9 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 10 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 11 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 12 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 13 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 14 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 15 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 16 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 17 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 18 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 19 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 20 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 21 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 22 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 35 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 36 | NA | 2 | 2 | 1 | 0 | 1 |
| Unit 37 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.
21 of 275 construction stages are filed complete across 25 buildings. The stage furthest along is Excavation, at 0%.
Unit 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 664%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 120%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 1364%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 140%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 150%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 160%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 1764%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 180%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 190%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit 200%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 82% |
| Water Supply | Yes | 58% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 26% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 70% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 15% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed50
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Unit 1 | 2 | 2 |
| Unit 2 | 2 | 2 |
| Unit 3 | 2 | 2 |
| Unit 4 | 2 | 2 |
| Unit 5 | 2 | 2 |
| Unit 6 | 2 | 2 |
| Unit 7 | 2 | 2 |
| Unit 8 | 2 | 2 |
| Unit 9 | 2 | 2 |
| Unit 10 | 2 | 2 |
| Unit 11 | 2 | 2 |
| Unit 12 | 2 | 2 |
| Unit 13 | 2 | 2 |
| Unit 14 | 2 | 2 |
| Unit 15 | 2 | 2 |
| Unit 16 | 2 | 2 |
| Unit 17 | 2 | 2 |
| Unit 18 | 2 | 2 |
| Unit 19 | 2 | 2 |
| Unit 20 | 2 | 2 |
| Unit 21 | 2 | 2 |
| Unit 22 | 2 | 2 |
| Unit 35 | 2 | 2 |
| Unit 36 | 2 | 2 |
| Unit 37 | 2 | 2 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 5.14 cr | Rs 5.09 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ravindra Shrikant Kadam |
| Architect | Rohan Ranade |
| Engineer | Aditya mule |
| Chartered Accountant | P R A S S & Associates LLP |
| Chartered Accountant | P T N N & Associates |
| Partner | Role in project |
|---|---|
| Sudarshan Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe re validation of the said project was under process. we received the same on 15/12/2018. Because of the market conditions, we couldn't able to sale the whole/ part against the unsold inventory. because of the funds shortage and, as we done the substantial amount on the common activity till date, we couldn't able to finish the remaining work in said timeline. but we are under process to complete the remaining work in next few months.
Reason as filed by the promoterAt the time of registration of the project with MAHARERA, we had planned for the finance form own contribution/ construction finance. However, we could not arrange funds form financial institutions and advances from customer as expected. We apologize for the same.
Reason as filed by the promoterReasons for delay. After starting development of site in 2015 it was observed that due to hilly terrain there was plenty of obstruction due to landslides during excavation lack of continuous supply of electricity and water supply . Also during 3-4 years of covid there was no sale . As a result we were constantly short of funds to maintain the site. Agencies and labour was not easily available. As we were the only company developing in that area there were disputes in demarcation which had to be solved . Also due to heavy rains development during June to Sept was also not possible. All the abov
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2028
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: March 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: March 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: March 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: March 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: Mar 2026.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: Mar 2026.pdf | 26 May 2026 |
| Form 1File: Sept 2024.pdf | 25 May 2026 |
| Form 2File: Sept 2024.pdf | 25 May 2026 |
| Form 3File: Sept 2024.pdf | 25 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sept 2024.pdf | 25 May 2026 |
| Form 1File: Dec 2024.pdf | 25 May 2026 |
| Form 2File: Dec 2024.pdf | 25 May 2026 |
| Form 3File: Dec 2024.pdf | 25 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Dec 2024.pdf | 25 May 2026 |
| Form 1File: Mar 2025.pdf | 25 May 2026 |
| Form 2File: March 2025.pdf | 25 May 2026 |
| Form 3File: March 2025.pdf | 25 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Mar 2025.pdf | 25 May 2026 |
| Form 1File: March 2022.pdf | 25 Jul 2025 |
| Form 2File: March 2022.pdf | 25 Jul 2025 |
| Form 3File: March 2022.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Mar 2022.pdf | 25 Jul 2025 |
| Form 1File: June 2022.pdf | 25 Jul 2025 |
| Form 2File: June 2022.pdf | 25 Jul 2025 |
| Form 3File: June 2022.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: June 2022.pdf | 25 Jul 2025 |
| Form 1File: Sept 2022.pdf | 25 Jul 2025 |
| Form 2File: Sept 2022.pdf | 25 Jul 2025 |
| Form 3File: Sept 2022.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sept 2022.pdf | 25 Jul 2025 |
| Form 1File: Dec 2022.pdf | 25 Jul 2025 |
| Form 2File: Dec 2022.pdf | 25 Jul 2025 |
| Form 3File: Dec 2022.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Dec 2022.pdf | 25 Jul 2025 |
| Form 1File: March 2023.pdf | 25 Jul 2025 |
| Form 2File: March 2023.pdf | 25 Jul 2025 |
| Form 3File: March 2023.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Mar 2023.pdf | 25 Jul 2025 |
| Form 1File: June 2023.pdf | 25 Jul 2025 |
| Form 2File: June 2023.pdf | 25 Jul 2025 |
| Form 3File: June 2023.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: June 2023.pdf | 25 Jul 2025 |
| Form 1File: Sept 2023.pdf | 25 Jul 2025 |
| Form 2File: Sept 2023.pdf | 25 Jul 2025 |
| Form 3File: Sept 2023.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sept 2023.pdf | 25 Jul 2025 |
| Form 1File: Dec 2023.pdf | 25 Jul 2025 |
| Form 2File: Dec 2023.pdf | 25 Jul 2025 |
| Form 3File: Dec 2023.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Dec 2023.pdf | 25 Jul 2025 |
| Form 1File: March 2024.pdf | 25 Jul 2025 |
| Form 2File: March 2024.pdf | 25 Jul 2025 |
| Form 3File: March 2024.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Mar 2024.pdf | 25 Jul 2025 |
| Form 1File: June 2024.pdf | 25 Jul 2025 |
| Form 2File: June 2024.pdf | 25 Jul 2025 |
| Form 3File: June 2024.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: June 2024.pdf | 25 Jul 2025 |
| Certificates of CA (Form 3)File: FORM3.pdf | 7 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 14 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 6 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 6 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 2020.pdf | 6 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 2021.pdf | 6 Sep 2021 |
| Certificates of CA (Form 3)File: FORM 3 Q4_compressed.pdf | 6 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 17-18.pdf | 6 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 18-19.pdf | 6 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 19-20.pdf | 6 Sep 2021 |
| Declaration in FORM BFile: DECLARATION FORM B.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate phase 1.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Table A Phase 1.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Table B phase 1.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engr Cer lagoonawoods ph 1.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE PHASE I.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Lagoona Woods Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Lavharde13,700+ in Pune
Filed coordinates, straight-line distance. 13 registered projects within 2 km.
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: Sudarshan Developers
Sudarshan Developers has 5 registrations on MahaRERA, including Lagoona Woods Phase 1 and Lagoona Woods Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Lagoona Woods Phase 1 is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Lagoona Woods Phase 1?
The registered promoter entity is Sudarshan Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Lagoona Woods Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Lagoona Woods Phase 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Lagoona Woods Phase 1?
The professionals named in the filing: Architect: Ravindra Shrikant Kadam; Architect: Rohan Ranade; Engineer: Aditya mule; Chartered Accountant: P R A S S & Associates LLP; Chartered Accountant: P T N N & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Lagoona Woods Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback