LA PROMENADE BAYWALK
RG-MH-09609 · RERA P51700003336 · Last updated on MahaRERA portal: 22 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Litigation declared, 1 case
- 5 complaints at MahaRERA
- Completion date moved by 84 months
- 5 extensions taken
Clear
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
LA PROMENADE BAYWALK is a Residential / Group Housing project by AADI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700003336 on 5 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 84 months from the original filing. 97 of the 140 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameLA PROMENADE BAYWALK
- TypeResidential / Group Housing
- Location
- KALYAN
- Kalyan-Dombivali (M Corp.)
- Thane
- 421102
- Pincode421102
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700003336
- ReraGenie IDRG-MH-09609
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2019)
- Buildings1 building record
- Documents filed141 files
Current status
Figures as on 22 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BAYWALK | NA | 14 | 12 | 140 | 0 | 140 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.
BAYWALK: 77% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Progress on shared amenities15
As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed73
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BAYWALK | NA | Rs 24.70 cr | Rs 17.50 cr |
| - | NA | Rs 1.30 cr | Rs 13.00 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Paarth Architectural Consultants |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | PRANAV BHASKARAN & ASSOCIATES |
| Chartered Accountant | Vikas Abhang & Associates |
| Chartered Accountant | NB Sayed & Associates |
| Partner | Role in project |
|---|---|
| AADI DEVELOPERS | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees. The project is has completed 90% of the work, we require extension for smooth functioning of the project.
Reason as filed by the promoterThe work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 12 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of completion
Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already completed 80% of the construction work before Lockdown and are hopeful that once we receive project extension of only one year, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for an extension of our project u/s 7(3). The project was delayed for reasons beyond our control on account of various reasons and more particularly on the account of the pandemic of Covid-19. We have the consent of 51.85% of allottees for purpose of extension of the RERA registration period of the said project.
Reason as filed by the promoterThe reason for this extension request is to account for unforeseen delays in construction, which have impacted our timeline, as well as the time needed to finalize regulatory approvals. Also, we are yet to apply for the Occupancy Certificate (OC), and based on the current progress, we expect to receive the OC by March 2026. To accommodate these delays and ensure full compliance with all MahaRERA requirements, we are requesting this extension as a buffer period, allowing us to complete all formalities in a timely and orderly manner.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 605/2023 | District Consumer Disputes Redressal Commission | Ongoing |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000199257 | Mr. Gaurav Raikar and Mrs. Janhvi Raikar | AADI Developers | 05/12/2021 |
| CC006000000261985 | MR.MUKESH CHANDRA MENARIA | AADI DEVELOPER | 20/07/2022 |
| CC12500260 | Ishwar Narayandas Keswani | AADI DEVELOPERS | 25/01/2025 |
| CC12504510 | AADI DEVELOPERS | Ketan Bharat Panchmatia | 17/12/2025 |
| CC12504520 | AADI DEVELOPERS | Ketan Bharat Panchmatia | 18/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed141
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate-Baywalk-till June 2026.pdf | 22 Jul 2026 |
| Withdrawal Update Form 2File: La_Promenade_Baywalk_Form2_Q1_2026-27_22-07-2026_10-56.pdf | 22 Jul 2026 |
| Withdrawal Update Form 3File: La_Promenade_Baywalk_Form3_Q1_2026-27_20-07-2026_12-41_doc1.pdf | 22 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form 5-FY-2023-2024.pdf | 6 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5-FY-2024-2025.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - La Promenade Baywalk as on March 2026.pdf | 1 May 2026 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on March 2026.pdf | 1 May 2026 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on March 2026.pdf | 1 May 2026 |
| Withdrawal Update Form 1File: Form 1-Architect Certificate-Signed-Dec-2025.pdf | 20 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on Dec 2025.pdf | 20 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on Dec 2025.pdf | 20 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - La Promenade Baywalk as on Sep 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 - La Promenade Baywalk as on Sep 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on Sep 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on Sep 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on Sept 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on Sept 2025.pdf | 28 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 - La Promenade Baywalk as on Sep 2025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on Sep 2025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on Sept 2025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 - La Promenade Baywalk as on Sep 2025.pdf | 25 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on Sep 2025.pdf | 25 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on Sept 2025.pdf | 25 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - La Promenade Baywalk as on June 2025 (SIGNED).pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - La Promenade Baywalk as on June 2025.pdf | 18 Oct 2025 |
| Form 1File: Form 1 - La Promenade Baywalk as on March 2025.pdf | 25 Sep 2025 |
| Form 2File: Form 2 - La Promenade Baywalk as on March 2025.pdf | 25 Sep 2025 |
| Form 3File: Form 3 - La Promenade Baywalk as on March 2025.pdf | 25 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - La Promenade Baywalk as on March 2025.pdf | 25 Sep 2025 |
| Certificates of CA (Form 3)File: Form 3-CA certificate-Aadi Developers-Signed copy-March 2025.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineers Certificate-Aadi Developers-Signed copy-March 2025.pdf | 11 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - La Promenade Baywalk as on March 2025.pdf | 8 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - La Promenade Baywalk as on Dec 2024.pdf | 5 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 - La Promenade Baywalk as on Dec 2024.pdf | 27 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - La Promenade Baywalk as on Dec 2024.pdf | 17 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - La Promenade Baywalk as on Sept 2024.pdf | 11 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 10 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Circular-29-La Promenade-Baywalk.pdf | 10 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 La Promenade Baywalk Sept 2024.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 of La Promenade Baywalk as on 30th September 2024.pdf | 20 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 La Promenade Baywalk Sept 2024.pdf | 14 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Aadi Developers-Engineers Certificate.pdf | 26 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3-Aadi Developers-CA certificate-signed.pdf | 26 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 of La Promenade as on 30th June 2024.pdf | 19 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - La Promanade baywalk as on June 2024.pdf | 3 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Declaration-La Promenade.pdf | 1 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Aadi Developers- Signed Copy.pdf | 27 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - La Promenade Baywalk as on March 2024.pdf | 15 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - La Promenade Baywalk as on March 2024.pdf | 10 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- La Promenade Baywalk -March 2024-Aadi Develoeprs.pdf | 10 Apr 2024 |
| Proforma of Agreement for saleFile: Baywalk-Draft RERA Agrmnt-2024.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29-Baywalk-December-2023.pdf | 20 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 of La Promenade as on 31st December 2023.pdf | 30 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - La Promenade Baywalk as on Dec 2023.pdf | 29 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - La Promenade Baywalk as on Dec 2023.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 - La Promenade Baywalk as on Dec 2023.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- La Promenade Baywalk as on September 2023.pdf | 29 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certificate-Sept 2023.pdf | 18 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certificate.pdf | 8 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineers Certificate.pdf | 8 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3-CA certificate-Sept 2023_compressed.pdf | 8 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (1)_compressed.pdf | 8 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: La Promenade Baywalk Sept 23 - Form 2.pdf | 2 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 of La Promenade as on 30th September 2023.pdf | 21 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 as on Sep 2023.pdf | 9 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf | 3 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report 2021-2022.pdf | 20 Sep 2023 |
| Declaration in FORM BFile: Form B.pdf | 18 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 18 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3_11zon.pdf | 18 Sep 2023 |
| Certificates of CA (Form 5)File: Form 5 Annual Report 2017-2018_11zon.pdf | 18 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Annual Report 2018-2019.pdf | 18 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Annual Report 2019-2020.pdf | 18 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Annual Report 2020-2021.pdf | 18 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Quality Assurance.pdf | 8 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 5 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Aadi Developers-Circular 29 Aug2023.pdf | 26 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Letter-Aadi Developers-June 2023.pdf | 21 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- La Promenade Baywalk as on June 2023.pdf | 21 Jul 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| LA PROMENADE BOARDWALK | SURVEY NO-31 VILLAGE MOHILI AMBIVALI KALYAN THANE-421102 | 140 | Completed | Feb 2016 | Late, Jan 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 141 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep LA PROMENADE BAYWALK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KALYAN7,600+ in Thane
Filed coordinates, straight-line distance. 31 registered projects within 2 km.
Godrej Riviera Phase 1
GODREJ PROPERTIES LIMITED
MOHANKHEDA GARDENS
MOHANKHEDA HERITAGE
Ramrajya - Neptune Ekansh D
Neptune Developers Limited
Ramrajya - Neptune Jal Tarang D
Neptune Developers Limited
Ramrajya - Neptune Jal Tarang E
Neptune Developers Limited
Ramrajya - Neptune Udaan B
Neptune Developers Limited
See every Thane project, with the district possession charts
Builder: AADI DEVELOPERS
AADI DEVELOPERS has 2 registrations on MahaRERA, including LA PROMENADE BAYWALK and Shridhar Residency. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that LA PROMENADE BAYWALK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if LA PROMENADE BAYWALK is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of LA PROMENADE BAYWALK?
The registered promoter entity is AADI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in LA PROMENADE BAYWALK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against LA PROMENADE BAYWALK?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for LA PROMENADE BAYWALK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at LA PROMENADE BAYWALK?
The professionals named in the filing: Architect: Paarth Architectural Consultants; Engineer: SK Consultants & Engineers; Chartered Accountant: PRANAV BHASKARAN & ASSOCIATES; Chartered Accountant: Vikas Abhang & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in LA PROMENADE BAYWALK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback