ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / La Mer Regency

Registered No litigation declared Residential / Group Housing project

La Mer Regency

By La Mer Developers Private Limitedd

RG-MH-61072 · RERA P52000034668 · Last updated on MahaRERA portal: 3 May 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
10 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

La Mer Regency is a Residential / Group Housing project by La Mer Developers Private Limitedd in Raigarh, Maharashtra, registered with MahaRERA as P52000034668 on 20 Apr 2022. Possession is promised by 31 Mar 2027.

At a glance

Project

  • NameLa Mer Regency
  • TypeResidential / Group Housing
  • Location
    • Final Plot No 493
    • Market Yard Panvel
    • Distt Raigad
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000034668
  • ReraGenie IDRG-MH-61072

Builder

  • NameLa Mer Developers Private Limitedd
  • Entity typeCompany
  • DirectorsDhanesh Pratap Mehta, Dimple Jiva Parmar

Key dates

this monthRegisteredApr 2022PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Apr 2022
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed110 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA150000
B wingNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

Wing A80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
B wing78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities18

As on 3 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
Tower Puzzle Car ParkingYes0%
Swimming PoolYes0%
GymYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
Wing A11
B wing11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,977 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14525.0
Proposed, not sanctioned10,289 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSMECC Branch, Central Facility Building II, APMC Market II, Sector 19, Vashi, Navi Mumbai 400703

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAdinath Patkar
EngineerYateesh Tare
Chartered AccountantKrishna R. Moondra and Associates LLP
Chartered AccountantDhawan & Co
PartnerRole in project
La Mer Developers Private Limitedd-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Regency-March-2025.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-March-2025.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Regency-March-2025.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discl-Sold-Unsold-Regency-March-2025.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-Dec-2024.pdf28 Feb 2025
Building plan approvalFile: Revised Plan-1.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-2.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-3.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-4 .pdf27 Feb 2025
Building plan approvalFile: Revised Plan-5 .pdf27 Feb 2025
Building plan approvalFile: Revised Plan-6.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-7.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-8 .pdf27 Feb 2025
Building plan approvalFile: Revised Plan-9.pdf27 Feb 2025
Building plan approvalFile: Revised Plan-10 .pdf27 Feb 2025
Building plan approvalFile: Revised Plan-11 .pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-Dec-2024.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Dec-2024.pdf27 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Revised CC-dt-04-02-2025.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-1.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-2.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-3.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-4 .pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-5 .pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-6.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-7.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-8 .pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-9.pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-10 .pdf27 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Plan-11 .pdf27 Feb 2025
Disclosure of sold/ booked inventoryFile: Decl-Sold-Unsold-Regency-Dec-2024.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Sept-2024-Regency.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Discl Sold-Unsold-June-2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Discl-Sold-Umsold-Sep-2024.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5-Regency-2023-24.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-June-2024.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-Regency-Sept-2024.pdf7 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From-3-CA-Cert-June-2024-Regency.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-June-2024.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Sept-2024-Regency.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Discl Sold-Unsold-June-2024.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Discl-Sold-Umsold-Sep-2024.pdf7 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2-Regency-Mar-2023.pdf7 Nov 2024
PAN CardFile: La Mer Developers Limited-Pan Card AAECL6030A.pdf8 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-March-2024.pdf13 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Regency-March-2024.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Regency-Mar-2024.pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Quality-Cert-Regency-March-2024.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: Discl-Sold-Unsold-Regency-March-2024.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-Regency-Dec-2023.pdf21 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Regency-Dec-2023.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold-Dec-2023-Regency.pdf21 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Lamer Regency-Dec-2023.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold-Inventory-Sept-2023.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-June-2023-Regency.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-Sept-2023.pdf1 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5-Regency-2022-23.pdf1 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-Regency-June-2023.pdf26 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Regency-June-2023.pdf26 Aug 2023
Disclosure of sold/ booked inventoryFile: Discl of Sold-Unsold-Regency-June-2023.pdf26 Aug 2023
Proforma of Agreement for saleFile: Agreement for Sale-Regency.pdf26 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Regency-Mar-2023.pdf2 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-Mar-2023.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Regency-Mar-2023.pdf27 Apr 2023
Disclosure of sold/ booked inventoryFile: Discl of Sold Unsold-Mar-2023.pdf27 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory-Sept-2022.pdf16 Nov 2022
Details of encumbrancesFile: Encumbrances-Financial-SBI.pdf8 Aug 2022
CERSAI detailsFile: CERSAI-Lamer.pdf8 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account for Real Estate Project-dt08-08-2022.pdf8 Aug 2022
Copy of the legal title reportFile: Title Report.pdf11 Apr 2022
Proforma of Allotment letterFile: Agreement for Sale-Regency.pdf11 Apr 2022
Proforma of Allotment letterFile: Allotment Letter-Lamer.pdf6 Apr 2022
Details of encumbrancesFile: Encumbrances-dt-01-04-2022.pdf4 Apr 2022
Declaration about Commencement CertificateFile: Decl-Commencement-Cert-Regency.pdf4 Apr 2022
Declaration in FORM BFile: Form-B-Affidavit-Regency.pdf4 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-March-22.pdf4 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Engineer-Cert-Regency-March-2022.pdf4 Apr 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Unsold-01-04-2022.pdf4 Apr 2022
CERSAI detailsFile: Encumbrances-dt-01-04-2022.pdf4 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Regency-March-2022.pdf4 Apr 2022

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep La Mer Regency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Distt Raigad5,900+ in Raigarh

Builder: La Mer Developers Private Limitedd

La Mer Developers Private Limitedd has 1 registration on MahaRERA, including La Mer Regency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if La Mer Regency is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of La Mer Regency?

The registered promoter entity is La Mer Developers Private Limitedd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in La Mer Regency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for La Mer Regency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at La Mer Regency?

The professionals named in the filing: Architect: Adinath Patkar; Engineer: Yateesh Tare; Chartered Accountant: Krishna R. Moondra and Associates LLP; Chartered Accountant: Dhawan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in La Mer Regency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About La Mer Regency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save La Mer Regency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.