Home / Browse projects / Mumbai Suburban, Maharashtra / Kurla Kadam Scoiety Phase 1

Registration lapsed Litigation declared Others project

Kurla Kadam Scoiety Phase 1

By Pramod Pandurang Pisal

RG-MH-26272 · RERA P51800006382 · Last updated on MahaRERA portal: 18 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Litigation declared, 3 cases
  • 60 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
40 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 88%
60Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Kurla Kadam Scoiety Phase 1 is a Others project by Pramod Pandurang Pisal in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006382 on 14 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 30 months from the original filing. 60 complaints are on record with the regulator.

At a glance

Project

  • NameKurla Kadam Scoiety Phase 1
  • TypeOthers
  • Location
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006382
  • ReraGenie IDRG-MH-26272

Builder

  • NamePramod Pandurang Pisal
  • Entity typeIndividual
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live3 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2022)
  • Buildings4 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rehab Building No 1NA80000
M M ResidencyNA170000
Rehab Building 2NA130000
Rehab Building 3NA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 88%.

Rehab Building No 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
M M Residency93%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Rehab Building 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Rehab Building 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Closed/Covered52

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,549 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
M M DevelopersKurlaMumbai Suburban
Spenta Infrastructure and Development Pvt LtdMumbai CityMumbai City

Approvals and building plan

Permissible FSI20945.69
Proposed, not sanctioned20,946 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBuilding No 10 Samrat CHS Near Kedarnath Temple Nehru Nagar Kurla East Mumbai 400024

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVert Arch
Engineeraaryaa reality
Chartered Accountantssk bansal& co
PartnerRole in project
Unity Land Consultancy-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019074Jun 2022 → Dec 2024

Reason as filed by the promoterCC was pending. Now Received Full CC. And RCC construction is complete. Finishing in progress

EXT51800012143Jun 2022 → Jun 2023

Reason as filed by the promoterThe following project is developed under the Slum Rehabilitation Scheme. Promoter no.1 is the LOI holder of the project. Promoter 1 further appointed Promoter 2 and Promoter 3 for development of said scheme. Litigations arised between the Promoter 2 and Promoter 3. Thereafter, promoter 3 had filed various legal complaints in various courts. Promoter 1 settled with promoter 3 all the complaints and issues regarding the said project and promoter 3 has withdrawn all the rights from the said project before Hon’ble Bombay High Court, Mumbai. And Promoter 1 started the pending work in 2021. The prom

Litigation declared3

CaseCourtStatus
123/2016City Civil CourtPending
NA/2016ArbitrationProcreeding in progress
NA/2016ArbitrationClosed

Complaints filed with MahaRERA60

Case no.ComplainantRespondentFiled
CC006000000000203Abdul RahimPramod Pandurang Pisal19/08/2017
CC006000000000205Altaf Ishaq BangiPramod Pandurang Pisal19/08/2017
CC006000000000214Shahbuddin SiddiquePramod Pandurang Pisal19/08/2017
CC006000000000300BADRUDDIN KUTBUDDIN THAKURPRAMOD PANDURANG PISAL30/08/2017
CC006000000000495Jagdish S. ShindePramod P. Pisal (Unity Land Consultancy) & M M Developers24/09/2017
CC006000000000813Qais Ayyub DaberPramod P. Pisal (Promoter of Unity Land Consultancy) & M M Developers24/09/2017
CC006000000000984Sarla Vasudev Patil Jointly with Vasudev Supadu PatilPramod P. Pisal (Uniti Land Consultancy) & M M Developers05/10/2017
CC006000000001016Rupali Vasudev Patil jointly with Vasudev Supadu PatilPramod P. Pisal (Unity Land Consultancy) & M. M. Developers05/10/2017
CC006000000001104Mohamad Masroor ShaikhUnity land Consultancy05/10/2017
CC006000000001328FEROZ RASHID KHANPRAMOD PANDURANG PISAL12/11/2017
CC006000000001388Imran Hasan KaziPramod P. Pisal (Unity Land Consultancy)24/10/2017
CC006000000001351Mr. Vasant Nivruti Bobade jointly with Mrs. Kamal Vasant BobadePromod P. Pisal (Unity Land Consultancy25/12/2017
CC006000000012630Abdullah Mohd. Firoz KhanUnity Land Consultancy27/12/2017
CC006000000012687Pradeep ShindeUnity Land Consultancy01/01/2018
CC006000000012660Shirish Dinkar KulkarniUnity Land Consultancy29/12/2017
CC006000000012675Vanita Sanjay ShindeUnity Land Consultancy01/01/2018
CC006000000012796Sanjay Prakash MetriUnity Land Consultancy08/01/2018
CC006000000022859Arif Haroon ShaikhUnity Land Consultancy20/01/2018
CC006000000022857Shivani Shashikant ShelarUnity Land Consultancy17/01/2018
CC006000000022852Shabanu Shaukatali SayedUnity Land Consultancy20/01/2018
CC006000000022890Krishna Laxman TekeUnity Land Consultancy18/01/2018
CC006000000022892Nilesh Dattatreya TekeUnity Land Consultancy18/01/2018
CC006000000022982USMAN NOOR MOHAMMED DARIYAPRAMOD PANDURANG PISAL25/01/2018
CC006000000023085MOHAMMED ABID MOMINPRAMOD PANDURANG PISAL25/01/2018
CC006000000023009Benny Elizabeth TitusUnity Land Consultancy15/04/2018
CC006000000023012Selva Ganapathy SelvarajUnity Land Consultancy03/03/2018
CC006000000023094NANDLAL KISHORE BINDPRAMOD PANDURANG PISAL25/01/2018
CC006000000022996IMROZ A BAIGPRAMOD PANDURANG PISAL25/01/2018
CC006000000023083NAEEM KHANPRAMOD PANDURANG PISAL25/01/2018
CC006000000023005Sadikali Sabirali ShaikhUnity Land Consultancy19/01/2018
CC006000000023084PRAMOD GAJANAN SHINGAREPRAMOD PANDURANG PISAL25/01/2018
CC006000000022995ABDUL REHMAN SULEMAN KALWETARPRAMOD PANDURANG PISAL25/01/2018
CC006000000022994Parvez Amir Mohammed KhanPRAMOD PANDURANG PISAL25/01/2018
CC006000000023023TUFAIL AHMED ABDUL QUDDUS. PRAMOD PANDURANG PISAL.2. M M DEVELOPERS 3. SPENTA INFRASTRUCTURE AND DEVELOPMENT PVT. LTD.23/01/2018
CC006000000023058Shaikh LutfuddinUnity Land Consultancy03/03/2018
CC006000000023059Nijam F. PathanUnity Land Consultancy03/03/2018
CC006000000054604Tabrez MandviwalaUnity Land Consultancy23/05/2018
CC006000000055859Pravin KadamUnity Land Consultancy20/08/2018
CC006000000023590Nuruddin Mohd. Hussain ShaikhUnity Land Consultancy09/03/2018
CC006000000023413DEVDATT CHANDRAKANT MANJREKARPRAMOD PANDURANG PISAL27/02/2018
CC006000000023663Ajita Oswald RodriguesUnity Land Consultancy09/03/2018
CC006000000023666Bharat Bhupendra ParmarUnity Land Consultancy16/04/2018
CC006000000023755JANHAVI SIDDHESH WADKARPRAMOD PANDURANG PISAL24/03/2018
CC006000000044040SIRAJ AHMED SHAIKHPRAMOD PANDURANG PISAL17/05/2018
CC006000000044129SANJAY RAMCHANDRA GAJBHIYEPRAMOD PANDURANG PISAL17/05/2018
CC006000000044192Mahesh K. PolUnity Land Consultancy30/04/2018
CC006000000044348Leena Vilas KulkarniUnity Land Consultancy30/04/2018
CC006000000044351Mahe Alam Imtiyaz AhmedUnity Land Consultancy30/04/2018
CC006000000054583Parveen Aminullah Shah SyedUnity Land Consultancy21/05/2018
CC006000000055582Rizwan S. AnsariUnity Land Consultancy17/08/2018
CC006000000056223Tabrez MandviwalaUnity Land Consultancy16/09/2018
CC006000000056869Sanjay ChaubeUnity Land Consultancy10/11/2018
CC006000000057485RAJU MAHADEORAO TAYADEPRAMOD PANDURANG PISAL30/12/2018
CC006000000078181VALMIK BHIMRAO NIKAMMOHAMMED MASROORSHAIKH09/03/2019
CC006000000195847SIDDHARTH LAXMAN SHINDEUNITY LAND CONSULTANCY (PRAMOD P PISAL)06/02/2021
CC006000000333969Aslam Abubakar PawaskarPramod Pandurang Pisal23/02/2023
CC006000000354448sakina mohammad khanPramod Pisal14/03/2023
CC006000000354460Mohommad Nizam KhanM/s. Unity Land Consultancy Private Limited23/02/2023
CC006000000580930zafer syedPramod Pandurang Pisal26/06/2024
CC12503220PRASHANT BHIMRAO BANGALEPramod Pandurang Pisal12/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure of sold Booked Inventory.pdf18 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 17-18.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 18-19.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 22-23.pdf1 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: aryaa reality.pdf31 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer certificate (1).pdf31 May 2024
Building plan approvalFile: MM Residency Layout Plan.pdf29 May 2024
Building Plan Approval (IOD)File: MM Residency Layout Plan.pdf29 May 2024
Building plan approvalFile: MM Residency IOA and Plans_compressed.pdf13 May 2024
Building Plan Approval (IOD)File: MM Residency IOA and Plans_compressed.pdf13 May 2024
Declaration in FORM BFile: Form Kurla.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 FY 22-23.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GetUserDocumentFileContent (15).pdf13 May 2024
Disclosure of sold/ booked inventoryFile: DocScanner 14-May-2024 4-18 am_compressed.pdf13 May 2024
Certificates of CA (Form 3)File: DocScanner 14-May-2024 3-42 am_compressed.pdf13 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf13 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf13 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DocScanner May 13, 2024 1-20 PM.pdf13 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 22.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 23.pdf9 May 2024
CERSAI detailsFile: CERSAI_Search_Report_200306253929_For_Asset_Based_Search_09_05_2024_23_28_38_257.pdf9 May 2024
CERSAI detailsFile: DocScanner 9 May 2024 11-55 pm.pdf9 May 2024
Certificates of CA (Form 3)File: Form 3 Scanned.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Real Real Estate.pdf9 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DocScanner 9 May 2024 11-55 pm.pdf9 May 2024
Layout approvalFile: MM Residency Layout Plan.pdf29 Apr 2024
Copy of Layout Approval (in case of layout)File: MM Residency Layout Plan.pdf29 Apr 2024
Building plan approvalFile: MM-Residency-IOA Compressed.pdf14 Nov 2022
Building Plan Approval (IOD)File: MM-Residency-IOA Compressed.pdf14 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: MM-Residency-CC.pdf14 Nov 2022
Declaration about Commencement CertificateFile: Scanned Circular 32.pdf6 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Scanned Form 2A 2020_compressed.pdf6 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Scanned Form 2A 2021_compressed.pdf6 Jul 2022
Disclosure of sold/ booked inventoryFile: Scanned Circular 29 _compressed (1).pdf6 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Scanned Form 5 2017-18_compressed.pdf6 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Scanned Form 5 2018-19.pdf6 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Scanned Form 5 2019-20.pdf6 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Scanned Form 5 2020-21.pdf6 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200241488271_For_Asset_Based_Search_05_07_2022_14_36_35_334.pdf5 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: kk.pdf27 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 123Architect Letter MahaRERA Letter .pdf21 Jun 2018
Certificates of CA (Form 3)File: Unity Land Project Kurla Kadam Phase 1 CA Certificate-31072017.pdf31 Jul 2017
Layout approvalFile: Unity Land Consultancy- non Apllcability-29-7-17.pdf29 Jul 2017
Building plan approvalFile: Download File (5).pdf29 Jul 2017
Building plan approvalFile: Download File (6).pdf29 Jul 2017
Building plan approvalFile: Download File (7).pdf29 Jul 2017
PAN CardFile: Pan Card Pramod Pisal.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Jul 2017
Details of encumbrancesFile: Download File (16).pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Unity Land Consultancy- non Apllcability-29-7-17.pdf29 Jul 2017
Building Plan Approval (IOD)File: Download File (6).pdf29 Jul 2017
Building Plan Approval (IOD)File: Download File (5).pdf29 Jul 2017
Building Plan Approval (IOD)File: Download File (7).pdf29 Jul 2017
Declaration in FORM BFile: Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VERTAECH-Certificate-29-7-17.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C Form 2 Unity land Kurla Phase 1.pdf29 Jul 2017
Proforma of Allotment letterFile: ARTICLES OF AGREEMENT FORMAT.pdf29 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kurla Kadam Scoiety Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmKurla Kadam Scoiety PhasCompleted 112Lapsed / revoked 112Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 366 registered projects within 2 km.

Builder: Pramod Pandurang Pisal

Pramod Pandurang Pisal has 5 registrations on MahaRERA, including Kurla Kadam Scoiety Phase 1 and Highway View Phase 1. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Kurla Kadam Scoiety Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Kurla Kadam Scoiety Phase 1 is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kurla Kadam Scoiety Phase 1?

The registered promoter entity is Pramod Pandurang Pisal, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kurla Kadam Scoiety Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kurla Kadam Scoiety Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kurla Kadam Scoiety Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kurla Kadam Scoiety Phase 1?

The professionals named in the filing: Architect: Vert Arch; Engineer: aaryaa reality; Chartered Accountant: ssk bansal& co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kurla Kadam Scoiety Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kurla Kadam Scoiety Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kurla Kadam Scoiety Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.