Home / Browse projects / Raigarh, Maharashtra / KRISHNA RESIDENCY

Completed No litigation declared Residential / Group Housing project

KRISHNA RESIDENCY

By PRATAP BABAJI SHINDE

RG-MH-38548 · RERA P52000034269 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Staircases, 98%
23 of 119Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

KRISHNA RESIDENCY is a Residential / Group Housing project by PRATAP BABAJI SHINDE in Raigarh, Maharashtra, registered with MahaRERA as P52000034269 on 30 Mar 2022. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 6 months from the original filing. 96 of the 119 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • AT TALOJA MAJKUR
    • TALOJA
    • Taloje Majkur
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000034269
  • ReraGenie IDRG-MH-38548

Builder

  • NamePRATAP BABAJI SHINDE
  • Entity typeIndividual
  • Named personSHRI. PRATAP BABAJI SHINDE

Key dates

this monthRegisteredMar 2022First promiseDec 2025Revised toJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on30 Mar 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed94 files

Current status

81%96 of 119 units booked
97.3%Work done, per cost certificate

Figures as on 13 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRISHNA RESIDENCYNA111110316119

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 98%.

KRISHNA RESIDENCY: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes90%

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Closed/Covered33
Open Space97

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,970 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Sep 2025

Approvals and building plan

Sanctioning authorityPanvel Municipal Corporation
Permissible FSI5437.32
Proposed, not sanctioned5,421 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 30 31 32 AND 33 PACHAND HEIGHT SECTOR 9 TALOJA PHASE -1 NAVI MUMBAI
Estimated costRs 12.94 cr
Cost incurredRs 12.59 cr
Work done97.31%
BuildingWingEstimatedIncurred
KRISHNA RESIDENCYNARs 12.28 crRs 11.95 cr
-NARs 66.36 lakhRs 63.71 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDISHA ARCHITECTS AR KAUSHAL JADIA
EngineerADHARSHILA CONSULTANTS MR SAMARTH AGARWAL
Chartered AccountantCA SAGDEO AND CO
Chartered AccountantCA Devyani Shejwal
Chartered AccountantM.s Singh Ranjan & Co
PartnerRole in project
PRATAP BABAJI SHINDE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20012619519Dec 2025 → Jun 2026

Reason as filed by the promoterOur project has been 100% completed, and we are waiting for the Occupancy Certificate.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 30-06-2026.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 30-06-2026.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Pratp Shinde 30-06-26.pdf13 Jul 2026
Occupational CertificateFile: OCCUPANCY CERTIFICATE-TALOJA MAJKUR.pdf21 Jun 2026
Occupational CertificateFile: OC-PLAN-TALOJA MAJKUR01_1.pdf21 Jun 2026
Occupational CertificateFile: OC-PLAN-TALOJA MAJKUR01_2.pdf21 Jun 2026
Occupational CertificateFile: OC-PLAN-TALOJA MAJKUR01_3.pdf21 Jun 2026
Occupational CertificateFile: OC-PLAN-TALOJA MAJKUR01_4.pdf21 Jun 2026
Layout approvalFile: Plan 1.pdf22 May 2026
Layout approvalFile: Plan 2.pdf22 May 2026
Layout approvalFile: Plan 3.pdf22 May 2026
Layout approvalFile: Plan 4.pdf22 May 2026
Building plan approvalFile: Plan 1.pdf22 May 2026
Building plan approvalFile: Plan 2.pdf22 May 2026
Building plan approvalFile: Plan 3.pdf22 May 2026
Building plan approvalFile: Plan 4.pdf22 May 2026
Withdrawal Update Form 1File: Form 1 31-03-2026.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 31-03-2026.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 31-03-2026.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 31-03-2026.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Pratp Shinde 31-03-26.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Pratp Shinde 31-03-26.pdf18 May 2026
Form 2A (FY 2021-2022)File: Form 2A 21-22.pdf9 May 2026
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf9 May 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf9 May 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf9 May 2026
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf9 May 2026
Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf9 May 2026
Form 5 (FY 2023-2024)File: FORM 5 Pratap Shinde 23-24 - converted.pdf9 May 2026
Form 5 (FY 2024-2025)File: FORM 5 Pratap Shinde 24-25.pdf26 Mar 2026
Withdrawal Update Form 1File: FORM-1 ARCHITECT CERTIFICATE_as on31-12-2025.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2 .pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3 Pratp Shinde 31-12-25 Sign.pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1 30-06-25.pdf23 Oct 2025
Withdrawal Update Form 1File: Form 1 30-09-25.pdf23 Oct 2025
Withdrawal Update Form 2File: Form 2 30-06-25.pdf23 Oct 2025
Withdrawal Update Form 2File: Form 2 30-09-25.pdf23 Oct 2025
Withdrawal Update Form 3File: Form 3 SG 30-06-2025.pdf23 Oct 2025
Withdrawal Update Form 3File: Form 3 Pratp Shinde 30-09-25.pdf23 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED - converted.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED - converted.pdf20 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 Pratap Shinde 23-24 - converted.pdf20 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 SIGNED.pdf4 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-12-2023.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-09-2023.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 30-09-2023_1 (3 files merged).pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-09-2023_1 (3 files merged).pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf7 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf13 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf13 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf13 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE_as on 12-01-2023.pdf17 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krishna Residency Majkur EC 13-01-23 with DSC.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _Signed Copy (1).pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf17 Feb 2023
Details of encumbrances concerned to FinanceFile: No encumbrances Pratap Shindhe.pdf10 Feb 2023
Details of encumbrances concerned to LegalFile: No encumbrances Pratap Shindhe.pdf10 Feb 2023
Proforma of Allotment letterFile: allotment and draft sale.pdf20 Apr 2022
Copy of the legal title reportFile: TITLE REPORT.pdf25 Mar 2022
Declaration in FORM BFile: FORM B.pdf25 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI CERT.pdf25 Mar 2022
Layout approvalFile: LAYOUT PLAN.pdf14 Feb 2022
Layout approvalFile: TILR.pdf14 Feb 2022
Building plan approvalFile: 05 BUILDING APPROVAL PLAN_1.pdf14 Feb 2022
Building plan approvalFile: 05 BUILDING APPROVAL PLAN_2.pdf14 Feb 2022
Building plan approvalFile: 05 BUILDING APPROVAL PLAN 3.pdf14 Feb 2022
Building plan approvalFile: 05 BUILDING APPROVAL PLAN_4.pdf14 Feb 2022
PAN CardFile: 01 PAN CARD.pdf14 Feb 2022

How this compares with Raigarh

81%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 6 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALOJA5,900+ in Raigarh

2 kmKRISHNA RESIDENCYCompleted 66Lapsed / revoked 16Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: PRATAP BABAJI SHINDE

PRATAP BABAJI SHINDE has 1 registration on MahaRERA, including KRISHNA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if KRISHNA RESIDENCY is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNA RESIDENCY?

The registered promoter entity is PRATAP BABAJI SHINDE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRISHNA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNA RESIDENCY?

The professionals named in the filing: Architect: DISHA ARCHITECTS AR KAUSHAL JADIA; Engineer: ADHARSHILA CONSULTANTS MR SAMARTH AGARWAL; Chartered Accountant: CA SAGDEO AND CO; Chartered Accountant: CA Devyani Shejwal; Chartered Accountant: M.s Singh Ranjan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.