ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / KRISHNA PRABHA

Registered No litigation declared Residential / Group Housing project

KRISHNA PRABHA

By OMKARA BUILDCON

RG-MH-50017 · RERA P50500054300 · Last updated on MahaRERA portal: 19 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Internal walls, 88%
4 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

KRISHNA PRABHA is a Residential / Group Housing project by OMKARA BUILDCON in Nagpur, Maharashtra, registered with MahaRERA as P50500054300 on 15 Jan 2024. Possession is promised by 31 Dec 2026. 10 of the 14 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA PRABHA
  • TypeResidential / Group Housing
  • Location
    • AJANI ROAD
    • MOUJE AJANI
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440010
  • Pincode440010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500054300
  • ReraGenie IDRG-MH-50017

Builder

  • NameOMKARA BUILDCON
  • Entity typePartnership
  • PartnersRAVINDRA SEWAKRAM SONKUSARE, SADANAND MADHAVRAO KOKATE, VITTHAL RAMCHANDRA BAJIRAO
  • Other registrations5 more →
  • Completed2 of 6
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jan 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed74 files

Current status

71%10 of 14 units booked
77.0%Work done, per cost certificate

Figures as on 19 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRISHNA PRABHANA8714014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 88%.

KRISHNA PRABHA: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Sanitary Fittings within the flats / premises74%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks81%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.49%

Progress on shared amenities15

As on 19 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes78%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes89%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes83%
Energy managemcntYes52%
Fire protection and fire safety requirementsYes71%
Electrical meter room, sub-station, receiving stationYes51%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered13

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area766 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
RAMCHANDRA KRISHNRAO BADKASNagpur (M Corp.)Nagpur
NARAYAN KRISHNARAO BADKASNagpur (M Corp.)Nagpur
BHARTI JAYANT BADKASNagpur (M Corp.)Nagpur
ABHIJEET JAYANT BADKASNagpur (M Corp.)Nagpur
BHAGYASHREE WAKHARENagpur (M Corp.)Nagpur
PRITI RAMESH GHONGENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION (NMC)
Permissible FSI2736.17
Proposed, not sanctioned2,680 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA1 YASH HEIGHTS, PLOT NO 140, NEAR JAIN MANDIR, RAMDASPETH, NAGPUR, MAHARASHTRA-440010
Estimated costRs 5.12 cr
Cost incurredRs 3.94 cr
Work done77.0%
BuildingWingEstimatedIncurred
KRISHNA PRABHANARs 5.12 crRs 3.94 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAVINDRA SONKUSARE
EngineerKAMAL SHAHU
EngineerEr GOPAL PANDHARE
Chartered AccountantANKIT TALREJA
PartnerRole in project
OMKARA BUILDCON-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 DEC-2025.pdf19 Apr 2026
Withdrawal Update Form 2File: FORM-2 DEC-2025.pdf19 Apr 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025.pdf19 Apr 2026
Withdrawal Update Form 1File: FORM-1 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 1File: FORM-1 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 1File: FORM-1 DEC-2025.pdf18 Mar 2026
Withdrawal Update Form 1File: FORM-1 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 1File: FORM-1 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 1File: FORM-1 DEC-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 DEC-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 2File: FORM-2 DEC-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 JUN-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 SEP-2025.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025.pdf18 Mar 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krishna Prabha_Form-1- Architect Certificate_Dec-24.pdf1 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krishna Prabha_Form-1- Architect Certificate_Sep-24.pdf26 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form -2.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-24.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold_June-24.pdf3 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krishna Prabha_june-24.pdf3 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krishna Prabha Form 1.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Omkara Buildcon March 2024.pdf7 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Omkara Buildcon.pdf7 May 2024
Other - TechnicalFile: mail.pdf10 Jan 2024
Other - LegalFile: Partnership Deed.pdf21 Dec 2023
Other - FinanceFile: Partnership Deed.pdf21 Dec 2023
Other - TechnicalFile: Partnership Deed.pdf21 Dec 2023
Declaration in FORM BFile: FORM-B_Land Owner.pdf20 Dec 2023
CERSAI detailsFile: CERSAI_Search_Report_200290331530_For_Asset_Based_Search_16_12_2023_20_10_48_609 (1).pdf20 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Sonkusre_UPDATE.pdf20 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration_Co-Promoter.pdf20 Dec 2023
Other - LegalFile: Badkas POA.pdf20 Dec 2023
Other - LegalFile: Badkas Agreement-1-20.pdf20 Dec 2023
Other - LegalFile: Badkas Agreement-21-40.pdf20 Dec 2023
Other - TechnicalFile: Badkas POA.pdf20 Dec 2023
Other - TechnicalFile: Badkas Agreement-1-20.pdf20 Dec 2023
Other - TechnicalFile: Badkas Agreement-21-40.pdf20 Dec 2023
Details of encumbrances concerned to FinanceFile: ENCUM_FINANCE_Prepared_Krishna Prabha (1).pdf18 Dec 2023
Details of encumbrances concerned to FinanceFile: ENCUM_LEGAL_Prepared_Krishna Prabha (1) -.pdf18 Dec 2023
Details of encumbrances concerned to LegalFile: ENCUM_FINANCE_Prepared_Krishna Prabha (1).pdf18 Dec 2023
Details of encumbrances concerned to LegalFile: ENCUM_LEGAL_Prepared_Krishna Prabha (1) -.pdf18 Dec 2023
Declaration about Commencement CertificateFile: form d (2)_Krishna Prabha (1).pdf18 Dec 2023
Declaration in FORM BFile: FORM-B_PROMOTER.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf18 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Kokate (1).pdf18 Dec 2023
Proforma of Allotment letterFile: Allotment Letter _Krishna Prabha (1).pdf18 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Disclosure_Krishna Prabha.pdf18 Dec 2023
Deviation Report with respect to Allotment letterFile: Deviation Report - ALLOTMENT LETTER _Krishna Prabha (1).pdf18 Dec 2023
Deviation Report with respect to model copy of AgreementFile: ATS DEVIATION REPORT -KRISHNA PRABHa (1) (1).pdf18 Dec 2023
Building plan approvalFile: Sanctioned Drawing.pdf16 Dec 2023
Layout approvalFile: Sanctioned Drawing.pdf16 Dec 2023
PAN CardFile: OMKARA PAN.pdf16 Dec 2023
Copy of the legal title reportFile: Search Report-OMKARA BUILDCON.pdf16 Dec 2023
Copy of Layout Approval (in case of layout)File: Sanctioned Drawing.pdf16 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Drawing.pdf16 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Building Permit.pdf16 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Vitthal Bajirao.pdf16 Dec 2023
Proforma of Agreement for saleFile: ATS-omkara.pdf16 Dec 2023

How this compares with Nagpur

71%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNA PRABHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUJE AJANI2,800+ in Nagpur

2 kmKRISHNA PRABHACompleted 22Lapsed / revoked 11Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 56 registered projects within 2 km.

Builder: OMKARA BUILDCON

OMKARA BUILDCON has 6 registrations on MahaRERA, including OMKARA PARK WING A and OMKARA PARK WING B. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if KRISHNA PRABHA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNA PRABHA?

The registered promoter entity is OMKARA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNA PRABHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRISHNA PRABHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNA PRABHA?

The professionals named in the filing: Architect: RAVINDRA SONKUSARE; Engineer: KAMAL SHAHU; Engineer: Er GOPAL PANDHARE; Chartered Accountant: ANKIT TALREJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA PRABHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA PRABHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA PRABHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.