Home / Browse projects / Dakshina Kannada, Karnataka / KRISHNA KUMUDA
KRISHNA KUMUDA
By SRI DEVIDAYAL BUILDERS & DEVELOPERS
RG-KA-32003 · RERA PRM/KA/RERA/1257/334/PR/210324/006721 · Last updated on RERA Karnataka portal: 13 Jul 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
KRISHNA KUMUDA is a Mixed Development project by SRI DEVIDAYAL BUILDERS & DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/210324/006721 on 21 Mar 2024. Possession is promised by 31 Dec 2028. 11 of the 16 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.
At a glance
Project
- NameKRISHNA KUMUDA
- TypeMixed Development
- Location
- Mangalore
- Dakshina Kannada
- 574151
- Pincode574151
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/210324/006721
- ReraGenie IDRG-KA-32003
Builder
- NameSRI DEVIDAYAL BUILDERS & DEVELOPERS
- Entity typeProprietorship
- GSTIN29BPPPS6832D1ZC
- Authorized SignatoryDEVIDAYAL SHETTY
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Mar 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed103 files
Current status
Figures as on 13 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KRISHNA KUMUDA | - | - | - | - | - | 16 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 14 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | No | Not applicable |
| Open parking areas | Yes | 100% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| KUMUDA SHETTY | - | - |
| PAVITHRA SHETTY | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.84 cr | Rs 3.32 cr |
| On-site expenditure-Consultants Fees | Rs 7.68 lakh | - |
| On-site expenditure-Site Overhead | Rs 6.96 lakh | - |
| other-contingencies | Rs 1.50 lakh | Rs 16.03 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHALINI SURESH |
| Engineer | SUBRAMANYA |
| Chartered Accountant | GAUTHAM NAYAK M |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed103
As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/210324/006721 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE.pdf | 13 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA Form 4_compressed.pdf | 11 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf | 11 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf | 11 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA certiifcate_compressed.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate.pdf | 15 Jan 2026 |
| EC 2004-2024File: EC 2004-2024.pdf | 13 Mar 2024 |
| Carpet area calculationFile: carpet area statement.pdf | 13 Mar 2024 |
| CDP mapFile: MASTER PLAN.pdf | 13 Mar 2024 |
| VILLAGE MAPFile: Village map-site highlight.pdf | 13 Mar 2024 |
| ARCHITECT COAFile: registration certificate.jpeg | 13 Mar 2024 |
| commencement certificateFile: commencement certificate.pdf | 13 Mar 2024 |
| CLARIFICATIONFile: Rera Clarification.pdf | 13 Mar 2024 |
| architect certificateFile: architect certificate from 2.pdf | 13 Mar 2024 |
| RTC, survey 233/1A2(P) | - |
| Mutation, survey 233/1A2(P) | - |
| Encumbrance Certificate, survey 233/1A2(P) | - |
| Conversion/Alienation Order, survey 233/1A2(P) | - |
| JDA, survey 233/1A2(P) | - |
| Khatha, survey 233/1A2(P) | - |
| Registration CertificateFile: REGISTRATION CERTIFICATE - GST.pdf | - |
| Certificate issued by CA Form 1File: CA Certificate (PR).pdf | - |
| Certificate issued by Architect Form 2File: architect certificate from 2.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit for non litigation on land.pdf | - |
| Certificate from Chartered AccountFile: CA Certificate (PR).pdf | - |
| Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf | - |
| Balance Sheet 2021 - 2022File: BS AY 2022-23.pdf | - |
| Balance Sheet 2020 - 2021File: BS AY 2021-22.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PL AY 2022-23.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL AY 2021-22.pdf | - |
| Cash Flow Statement 2022 - 2023File: IS AY 2023-24.pdf | - |
| Cash Flow Statement 2021 - 2022File: IS AY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf | - |
| Licence Order | - |
| Approved Plan | - |
| Single Site | - |
| Approved Plan | - |
| Approved Plan | - |
| Approved Plan | - |
| Specitication | - |
| Approved Plan | - |
| Single Site | - |
| Structural stability certificate | - |
| search report | - |
| title deed | - |
| Conversion 14 51cents | - |
| Conversion 14 51cents | - |
| JD AGREEMENT | - |
| Proforma AOS | - |
| Proforma allotment letter | - |
| Krishna Kumuda Brochure | - |
| FORM -'B' | - |
| Affidavit3(1) | - |
| Jda affidavit | - |
| MESCOM NOC | - |
| Water NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Zonal Certificate | - |
| Unnamed document | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Sri Devidayal La Grace | SY NO.233/1A2A14, , Padavu Village , Mangalore taluk | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep KRISHNA KUMUDA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 59 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: SRI DEVIDAYAL BUILDERS & DEVELOPERS
SRI DEVIDAYAL BUILDERS & DEVELOPERS has 1 registration on RERA Karnataka, including KRISHNA KUMUDA. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if KRISHNA KUMUDA is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of KRISHNA KUMUDA?
The registered promoter entity is SRI DEVIDAYAL BUILDERS & DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29BPPPS6832D1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in KRISHNA KUMUDA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at KRISHNA KUMUDA?
The professionals named in the filing: Architect: SHALINI SURESH; Engineer: SUBRAMANYA; Chartered Accountant: GAUTHAM NAYAK M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRISHNA KUMUDA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback