Home / Browse projects / Dakshina Kannada, Karnataka / KRISHNA KUMUDA

Registration approved No litigation declared Mixed Development project

KRISHNA KUMUDA

By SRI DEVIDAYAL BUILDERS & DEVELOPERS

RG-KA-32003 · RERA PRM/KA/RERA/1257/334/PR/210324/006721 · Last updated on RERA Karnataka portal: 13 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
14 of 14Construction stages doneevery applicable stage filed complete
5 of 16Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 103 documents Report an error

KRISHNA KUMUDA is a Mixed Development project by SRI DEVIDAYAL BUILDERS & DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/210324/006721 on 21 Mar 2024. Possession is promised by 31 Dec 2028. 11 of the 16 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA KUMUDA
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
    • 574151
  • Pincode574151
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/210324/006721
  • ReraGenie IDRG-KA-32003

Builder

  • NameSRI DEVIDAYAL BUILDERS & DEVELOPERS
  • Entity typeProprietorship
  • GSTIN29BPPPS6832D1ZC
  • Authorized SignatoryDEVIDAYAL SHETTY
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Mar 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed103 files

Current status

69%11 of 16 units booked
87.0%Of the estimated cost spent so far

Figures as on 13 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRISHNA KUMUDA-----16

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 14 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area566 sq m
Named landowners2
LandownerVillageDistrict
KUMUDA SHETTY--
PAVITHRA SHETTY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.00 cr
Cost incurredRs 3.48 cr
Spent of the estimate86.96%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.84 crRs 3.32 cr
On-site expenditure-Consultants FeesRs 7.68 lakh-
On-site expenditure-Site OverheadRs 6.96 lakh-
other-contingenciesRs 1.50 lakhRs 16.03 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHALINI SURESH
EngineerSUBRAMANYA
Chartered AccountantGAUTHAM NAYAK M

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed103

As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/210324/006721 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE.pdf13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA Form 4_compressed.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA certiifcate_compressed.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate.pdf15 Jan 2026
EC 2004-2024File: EC 2004-2024.pdf13 Mar 2024
Carpet area calculationFile: carpet area statement.pdf13 Mar 2024
CDP mapFile: MASTER PLAN.pdf13 Mar 2024
VILLAGE MAPFile: Village map-site highlight.pdf13 Mar 2024
ARCHITECT COAFile: registration certificate.jpeg13 Mar 2024
commencement certificateFile: commencement certificate.pdf13 Mar 2024
CLARIFICATIONFile: Rera Clarification.pdf13 Mar 2024
architect certificateFile: architect certificate from 2.pdf13 Mar 2024
RTC, survey 233/1A2(P)-
Mutation, survey 233/1A2(P)-
Encumbrance Certificate, survey 233/1A2(P)-
Conversion/Alienation Order, survey 233/1A2(P)-
JDA, survey 233/1A2(P)-
Khatha, survey 233/1A2(P)-
Registration CertificateFile: REGISTRATION CERTIFICATE - GST.pdf-
Certificate issued by CA Form 1File: CA Certificate (PR).pdf-
Certificate issued by Architect Form 2File: architect certificate from 2.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for non litigation on land.pdf-
Certificate from Chartered AccountFile: CA Certificate (PR).pdf-
Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf-
Balance Sheet 2021 - 2022File: BS AY 2022-23.pdf-
Balance Sheet 2020 - 2021File: BS AY 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL AY 2022-23.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL AY 2021-22.pdf-
Cash Flow Statement 2022 - 2023File: IS AY 2023-24.pdf-
Cash Flow Statement 2021 - 2022File: IS AY 2022-23.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf-
Licence Order-
Approved Plan-
Single Site-
Approved Plan-
Approved Plan-
Approved Plan-
Specitication-
Approved Plan-
Single Site-
Structural stability certificate-
search report-
title deed-
Conversion 14 51cents-
Conversion 14 51cents-
JD AGREEMENT-
Proforma AOS-
Proforma allotment letter-
Krishna Kumuda Brochure-
FORM -'B'-
Affidavit3(1)-
Jda affidavit-
MESCOM NOC-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Zonal Certificate-
Unnamed document-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sri Devidayal La GraceSY NO.233/1A2A14, , Padavu Village , Mangalore talukCompleted-No date filed

How this compares with Dakshina Kannada

69%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep KRISHNA KUMUDA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmKRISHNA KUMUDAOther 59Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: SRI DEVIDAYAL BUILDERS & DEVELOPERS

SRI DEVIDAYAL BUILDERS & DEVELOPERS has 1 registration on RERA Karnataka, including KRISHNA KUMUDA. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if KRISHNA KUMUDA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KRISHNA KUMUDA?

The registered promoter entity is SRI DEVIDAYAL BUILDERS & DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29BPPPS6832D1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KRISHNA KUMUDA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KRISHNA KUMUDA?

The professionals named in the filing: Architect: SHALINI SURESH; Engineer: SUBRAMANYA; Chartered Accountant: GAUTHAM NAYAK M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA KUMUDA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA KUMUDA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA KUMUDA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.