ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / KRISHNA HORIZON - II

Registration lapsed No litigation declared Residential / Group Housing project

KRISHNA HORIZON - II

By RAJ DEVELOPERS

RG-MH-62259 · RERA P99000011696 · Last updated on MahaRERA portal: 17 Jun 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 73 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Sep 2020Possession promised73 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 30%
4Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

KRISHNA HORIZON - II is a Residential / Group Housing project by RAJ DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000011696 on 31 Aug 2017. Possession was promised by 30 Sep 2020 and is now 73 months past that date. The completion date has moved by 18 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameKRISHNA HORIZON - II
  • TypeResidential / Group Housing
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000011696
  • ReraGenie IDRG-MH-62259

Builder

  • NameRAJ DEVELOPERS
  • Entity typePartnership
  • PartnersRAJESH PREMJI PATEL, JAMES PHILIP TUSCANO, IRFAN HASANALI ANSARI
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live5 lapsed, de-registered or revoked

Key dates

73 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toSep 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2020
  • Revised completionRevised to 30 Sep 2020 (originally 31 Mar 2019)
  • Buildings2 building records
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BULDING NO 1NA110000
BUILDING NO 1NA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 30%.

BULDING NO 149%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 149%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes90%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
BULDING NO 1156
BUILDING NO 1055

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,349 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4594.98
Proposed, not sanctioned4,595 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP NANDAKHAL CHURCH, AGASHI, DIST PALGHAR

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY WADE & ASSOCIATES
PartnerRole in project
RAJ DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000001621Mar 2019 → Mar 2020

Reason as filed by the promoterDue to bank litigation and for reconstitution of partnership firm we required time to complete the project. we have completed almost 59.40% Construction Work and 24.70% Infra Work and balance finishing work i.e. 40.60% Construction work and 75.30 Infra Work is pending which we shall complete on/or before 30th March 2020 or early.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000198104Pradeep Panigrahi & 33 OthersRaj Developer26/08/2021
CC006000000199080Sana Wasim SHaikhAnsari Mohammad Irfan23/02/2022
CC006000000479977Rushab Nitin HariyaRaj Developers19/04/2024
CC12602514Amit MehtaRAJ DEVELOPERS29/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: FORM NO-5.PDF17 Jun 2019
Certificates of CA (Form 3)File: CA PRITAM NEVREKAR RERA CERTIFICATE.pdf31 Jul 2017
Proforma of Allotment letterFile: 001.pdf31 Jul 2017
Proforma of Allotment letterFile: 003.pdf31 Jul 2017
Proforma of Allotment letterFile: 004.pdf31 Jul 2017
Proforma of Allotment letterFile: 005.pdf31 Jul 2017
Proforma of Allotment letterFile: 006.pdf31 Jul 2017
Proforma of Allotment letterFile: 007.pdf31 Jul 2017
Proforma of Allotment letterFile: 008.pdf31 Jul 2017
Proforma of Allotment letterFile: 009.pdf31 Jul 2017
Proforma of Allotment letterFile: 010.pdf31 Jul 2017
Proforma of Allotment letterFile: 012.pdf31 Jul 2017
Proforma of Allotment letterFile: 013.pdf31 Jul 2017
Proforma of Allotment letterFile: 014.pdf31 Jul 2017
Proforma of Allotment letterFile: 015.pdf31 Jul 2017
Proforma of Allotment letterFile: 015.pdf31 Jul 2017
Proforma of Allotment letterFile: 021.pdf31 Jul 2017
Proforma of Allotment letterFile: 022.pdf31 Jul 2017
Proforma of Allotment letterFile: 023.pdf31 Jul 2017
Proforma of Allotment letterFile: 024.pdf31 Jul 2017
Proforma of Allotment letterFile: 025.pdf31 Jul 2017
Proforma of Allotment letterFile: 026.pdf31 Jul 2017
Proforma of Allotment letterFile: 028.pdf31 Jul 2017
Proforma of Allotment letterFile: 029.pdf31 Jul 2017
Proforma of Allotment letterFile: 030.pdf31 Jul 2017
Proforma of Allotment letterFile: 031.pdf31 Jul 2017
Proforma of Allotment letterFile: 032.pdf31 Jul 2017
Building plan approvalFile: 002 d.pdf30 Jul 2017
Building plan approvalFile: 003 E.pdf30 Jul 2017
Layout approvalFile: Phase-II layout.pdf30 Jul 2017
PAN CardFile: Raj Developers PAN Card.pdf30 Jul 2017
Copy of the legal title reportFile: 003.pdf30 Jul 2017
Copy of the legal title reportFile: 004.pdf30 Jul 2017
Copy of the legal title reportFile: 005.pdf30 Jul 2017
Copy of the legal title reportFile: 006.pdf30 Jul 2017
Copy of the legal title reportFile: 007.pdf30 Jul 2017
Copy of the legal title reportFile: 008.pdf30 Jul 2017
Copy of the legal title reportFile: 009.pdf30 Jul 2017
Details of encumbrancesFile: 003.pdf30 Jul 2017
Details of encumbrancesFile: 004.pdf30 Jul 2017
Details of encumbrancesFile: 005.pdf30 Jul 2017
Details of encumbrancesFile: 009.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Phase-II layout.pdf30 Jul 2017
Building Plan Approval (IOD)File: 002 d.pdf30 Jul 2017
Building Plan Approval (IOD)File: 003 E.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc 001.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc 002.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc 003.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc 004.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc 005.pdf30 Jul 2017
Declaration in FORM BFile: 010.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 001.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 002.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 003.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 001.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 002.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 003.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 004.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 005.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment Phase-II.pdf30 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 18 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNA HORIZON - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmKRISHNA HORIZON - IICompleted 35Lapsed / revoked 24Other 69Dot size: filed unitsN

Filed coordinates, straight-line distance. 128 registered projects within 2 km.

Builder: RAJ DEVELOPERS

RAJ DEVELOPERS has 6 registrations on MahaRERA, including KRISHNA HORIZON - I and KRISHNA HORIZON - II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that KRISHNA HORIZON - II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KRISHNA HORIZON - II is delayed beyond 30 Sep 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNA HORIZON - II?

The registered promoter entity is RAJ DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNA HORIZON - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KRISHNA HORIZON - II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KRISHNA HORIZON - II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNA HORIZON - II?

The professionals named in the filing: Architect: AJAY WADE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA HORIZON - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA HORIZON - II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA HORIZON - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.